organizational external

Delay in upstream supply or support process

Die wissenschaftlichen Inhalte dieser Seite werden auf Englisch und Spanisch veröffentlicht; hier werden sie auf Englisch angezeigt.

Kurz gefasst

Sie tritt bei etwa 1 von 100 untersuchten Linien auf.

Wenn sie auftritt, entfällt auf sie im Mittel etwa 56 % der Verlustzeit der Linie. Berichtet von 2 der 127 Studien, die sie beobachten konnten (begrenzte Evidenz).

Was passiert

The line is starved because a support activity located upstream of the process (washing of containers/trays, batch formulation, feeding of raw materials onto the line, or receipt of external deliveries) does not deliver its output in time. The stoppage does not originate in the line equipment itself but in the scheduling or execution of an upstream task on which the line depends.

Was man dagegen tut

Synchronize the schedule of the upstream support process with the production plan of the line, add buffer stock or intermediate storage of washed containers, formulated batches or incoming materials, and set up early warning or kanban signals so the upstream area anticipates the line's demand and deliveries are coordinated in advance.

Praktische Hinweise auf Basis ingenieurtechnischen Wissens; keine statistische Schätzung.

1Wahrscheinlichkeit und Evidenz

Gepoolt über alle Segmente. Ein breites Intervall ist ein Ergebnis: Es zeigt, wie viel die Evidenz zu wissen erlaubt.
Auftretenswahrscheinlichkeit
0,8 % [0,2–1,9 %]
Erwarteter Anteil an der Verlustzeit
0,4 % [0,1–1,1 %]
Anteil an der Verlustzeit bei Auftreten
56 % [45–66 %]
Studien / Einheiten
127 / 161
Evidenzgrad
C

Grad C: 2 bis 4 Studien oder eine Intervallbreite über 0,35.

2Wahrscheinlichkeit nach Segment

Partiell gepoolte Schätzungen für jedes Branchensegment.
  • Milchprodukte
    0,9 % [0,1–2,9 %]13 Studien
  • Erfrischungsgetränke, abgefülltes Wasser und Säfte
    0,8 % [0,1–2,5 %]26 Studien
  • Bier, Wein und Spirituosen
    0,8 % [0,1–2,8 %]11 Studien
  • Backwaren und Teigwaren
    1,1 % [0,2–3,4 %]24 Studien
  • Fleisch, Geflügel und Fisch
    0,9 % [0,1–3,0 %]9 Studien
  • Obst- und Gemüseverarbeitung
    0,9 % [0,1–2,9 %]7 Studien
  • Getreide- und Ölsaatenmüllerei
    0,9 % [0,1–3,3 %]6 Studien
  • Zucker und Süßwaren
    0,9 % [0,1–3,0 %]9 Studien
  • Snacks, Kaffee, Tee und sonstige Lebensmittel
    0,9 % [0,1–3,1 %]5 Studien
  • Futtermittel und Heimtiernahrung
    0,9 % [0,1–3,0 %]7 Studien
  • Lebensmittelherstellung (nicht spezifiziert oder gemischt)
    1,3 % [0,2–4,4 %]10 Studien

3Mechanismus, SCADA-Signatur und Gegenmaßnahme

Ingenieurpraktische Hinweise, um die Ursache zu erkennen und zu beheben; nicht Teil der statistischen Schätzung.

Mechanismus

Ingenieurpraktische Hinweise

The line is starved because a support activity located upstream of the process (washing of containers/trays, batch formulation, feeding of raw materials onto the line, or receipt of external deliveries) does not deliver its output in time. The stoppage does not originate in the line equipment itself but in the scheduling or execution of an upstream task on which the line depends.

So zeigt sie sich in SCADA-Daten

Ingenieurpraktische Hinweise

Line or station shows an extended idle/waiting state with no equipment fault code active, often logged as waiting for material or waiting for input; counters for infeed accumulation drop to zero while the rest of the line remains available, and the event correlates in time with records or logs of the upstream washing, formulation or logistics area rather than with any machine alarm.

Gegenmaßnahme

Ingenieurpraktische Hinweise

Synchronize the schedule of the upstream support process with the production plan of the line, add buffer stock or intermediate storage of washed containers, formulated batches or incoming materials, and set up early warning or kanban signals so the upstream area anticipates the line's demand and deliveries are coordinated in advance.

4Quellen

Jeder extrahierte Datenpunkt mit Studie, Wert und wörtlichem Zitat.
  1. Verlustzeit: 5,00 h · laut Bericht: “Demora en formulación”
    Wörtliches Zitat anzeigen
    Demora en formulación 5 980 0.5% 99.7%
  2. Anteil an der Verlustzeit: 0,500 % · laut Bericht: “Demora en formulación”
    Wörtliches Zitat anzeigen
    Demora en formulación 5 980 0.5% 99.7%
  3. Verlustzeit: 54,1 h · laut Bericht: “Demora en el lavado de bandejas”
    Wörtliches Zitat anzeigen
    Demora en el lavado de bandejas 54.09 53%
  4. Anteil an der Verlustzeit: 53,0 % · laut Bericht: “Demora en el lavado de bandejas”
    Wörtliches Zitat anzeigen
    Demora en el lavado de bandejas 54.09 53%
  5. Verlustzeit: 14,4 h · laut Bericht: “Demora en el lavado de bandejas”
    Wörtliches Zitat anzeigen
    se concluye que el tiempo de parada por la demora en el lavado de bandejas representa el 53% del total de horas del motivo 3 y presentó su máximo de horas de paradas en el enero del 2023, con 14.4 horas.
  6. Verlustzeit: 17,0 h · laut Bericht: “Demora en la alimentación de la línea”
    Wörtliches Zitat anzeigen
    Demora en la alimentación de la línea 16.97 16%
  7. Anteil an der Verlustzeit: 16,0 % · laut Bericht: “Demora en la alimentación de la línea”
    Wörtliches Zitat anzeigen
    Demora en la alimentación de la línea 16.97 16%
  8. Anteil an den Verlustereignissen: 34,0 % · laut Bericht: “Demora en Entregas”
    Wörtliches Zitat anzeigen
    En los primeros 9 meses del año 2022 se registró un total de 167 incidencias en todo el proceso de producción, ocasionando un 34% en demoras en las entregas finales a los clientes y un 66% en retrasos de procesos.