Application of Lean-Total Productive Maintenance Tools to Reduce Setup Times and Machine Stoppages on the Molding Line of an SME in the Food Industry

Abrir fuente

1Ficha bibliográfica

Autores
Renzo Peralta-Pereda, Frank Zamora, Juan Carlos Quiroz-Flores, Martin Fidel Collao-Diaz, Alberto Flores-Pérez
Año
2023
Publicación
International Journal of Engineering and Technology
País
Peru
Segmento
Productos lácteos
Familia de procesos
Planta completa o sin especificar
Tipo de estudio
Intervención antes/después
Alcance de la extracción
Texto completo
Tamaño
1 plantas · 1 líneas · 7 máquinas
Periodo de observación
30 días
Recolección de datos
manual_logs
Intervención
Ver el contexto tal como lo describe el estudio
For the validation, a data collection of the operation times and the necessary times for the analysis of the indicators was carried out, all this in one month for the production batches of cream ice cream in the presentation of 63 grams, obtaining as data the daily production of 5443 boxes of ice cream

2Riesgo de sesgo

Puntuado con la rúbrica del protocolo: 2 preocupación baja, 1 algunas preocupaciones, 0 preocupación alta.
Puntuación total 12Riesgo moderado
ÍtemPuntuación
Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product, process and equipment are all described.2 / 2
Is the observation period long enough and reported?Period reported and at least 30 days of production (or at least 100 recorded events).2 / 2
How were loss data collected?Manual logs or maintenance records with unknown completeness.1 / 2
Are OEE, loading time and the loss categories defined explicitly?A standard definition is cited but its application is not shown.1 / 2
Does the loss breakdown account for the total loss it claims to explain?Only the top causes are reported and the unexplained remainder can be computed.1 / 2
Is there evidence of selective reporting of favourable results?Intervention study in which baseline and post-intervention periods differ in length or method.1 / 2
Are the reported numbers internally consistent?Recomputed totals, shares and OEE factors agree with the reported values within 2 percentage points.2 / 2
Could conflicts of interest or the source of the data bias the result?Academic or independent study, or conflicts declared and unrelated to the result.2 / 2

3Datos extraídos

Cada dato con su clasificación y la cita textual que lo establece.
Causa reportadaCategoría de pérdidaMétricaValorExtracción
—Wrapper
Ver cita textual (Section IV.B)
During the analysis period, the following machine stops were observed: 2 stops in the Mix Plant, 8 stops in the Freezer, 3 stops in the Cold Compressor and Boiler, 1 stop in the Air Compressor, 86 stops in the Palletizer and 25 in the Wrapper.
Fallas de equipo (averías)Número de eventos25.0 eventsAmbos extractores coincidieron
—Palletizer
Ver cita textual (Section IV.B)
During the analysis period, the following machine stops were observed: 2 stops in the Mix Plant, 8 stops in the Freezer, 3 stops in the Cold Compressor and Boiler, 1 stop in the Air Compressor, 86 stops in the Palletizer and 25 in the Wrapper.
Fallas de equipo (averías)Número de eventos86.0 eventsAmbos extractores coincidieron
—Air Compressor
Ver cita textual (Section IV.B)
During the analysis period, the following machine stops were observed: 2 stops in the Mix Plant, 8 stops in the Freezer, 3 stops in the Cold Compressor and Boiler, 1 stop in the Air Compressor, 86 stops in the Palletizer and 25 in the Wrapper.
Fallas de equipo (averías)Número de eventos1.00 eventsAmbos extractores coincidieron
—Boiler
Ver cita textual (Section IV.B)
During the analysis period, the following machine stops were observed: 2 stops in the Mix Plant, 8 stops in the Freezer, 3 stops in the Cold Compressor and Boiler, 1 stop in the Air Compressor, 86 stops in the Palletizer and 25 in the Wrapper.
Fallas de equipo (averías)Número de eventos3.00 eventsAmbos extractores coincidieron
—Cold Compressor
Ver cita textual (Section IV.B)
During the analysis period, the following machine stops were observed: 2 stops in the Mix Plant, 8 stops in the Freezer, 3 stops in the Cold Compressor and Boiler, 1 stop in the Air Compressor, 86 stops in the Palletizer and 25 in the Wrapper.
Fallas de equipo (averías)Número de eventos3.00 eventsAmbos extractores coincidieron
—Freezer
Ver cita textual (Section IV.B)
During the analysis period, the following machine stops were observed: 2 stops in the Mix Plant, 8 stops in the Freezer, 3 stops in the Cold Compressor and Boiler, 1 stop in the Air Compressor, 86 stops in the Palletizer and 25 in the Wrapper.
Fallas de equipo (averías)Número de eventos8.00 eventsAmbos extractores coincidieron
—Mix Plant
Ver cita textual (Section IV.B)
During the analysis period, the following machine stops were observed: 2 stops in the Mix Plant, 8 stops in the Freezer, 3 stops in the Cold Compressor and Boiler, 1 stop in the Air Compressor, 86 stops in the Palletizer and 25 in the Wrapper.
Fallas de equipo (averías)Número de eventos2.00 eventsAmbos extractores coincidieron
—
Ver cita textual (Section IV.B)
A global average MTBF (Mean Time Between Failures) equivalent to 185.22 h was obtained and concerning the MTTR (Mean Time to Repair), a global average of 88.45 minutes/stop was obtained for the machines.
Fallas de equipo (averías)Duración media del evento88.5 min/stopAmbos extractores coincidieron
—
Ver cita textual (Section IV.B)
A global average MTBF (Mean Time Between Failures) equivalent to 185.22 h was obtained and concerning the MTTR (Mean Time to Repair), a global average of 88.45 minutes/stop was obtained for the machines.
Fallas de equipo (averías)Tiempo entre eventos185 hAmbos extractores coincidieron
Total duration of mold change
Ver cita textual (Section IV.B / Table II)
From the data collection of the total duration of mold change times, a total of 280 minutes on average was obtained, and the times of internal activities, 254 min, and external activities, 26 min.
Setups y ajustesTiempo perdido280 minUn solo extractor
Duration of internal activities
Ver cita textual (Section IV.B / Table II)
From the data collection of the total duration of mold change times, a total of 280 minutes on average was obtained, and the times of internal activities, 254 min, and external activities, 26 min.
Setups y ajustesTiempo perdido254 minUn solo extractor
Duration of external activities
Ver cita textual (Section IV.B / Table II)
From the data collection of the total duration of mold change times, a total of 280 minutes on average was obtained, and the times of internal activities, 254 min, and external activities, 26 min.
Setups y ajustesTiempo perdido26.0 minUn solo extractor
mold change
Ver cita textual (Page 4, Section B (Initial Diagnosis); Table II)
From the data collection of the total duration of mold change times, a total of 280 minutes on average was obtained
Setups y ajustesDuración media del evento280 minUn solo extractor
internal activities
Ver cita textual (Page 4, Section B)
the times of internal activities, 254 min, and external activities, 26 min
Setups y ajustesDuración media del evento254 minUn solo extractor
external activities
Ver cita textual (Page 4, Section B)
the times of internal activities, 254 min, and external activities, 26 min
Setups y ajustesDuración media del evento26.0 minUn solo extractor
—
Ver cita textual (Page 4, Section B)
obtaining as data the daily production of 5443 boxes of ice cream (each box contains 40 popsicles of cream ice cream)
noneCapacidad de producción5,443 boxes/dayUn solo extractor

Unidades de observación

  • Wrapper · Envasado (formado, sellado, envoltura, encajado, paletizado) · Línea base
  • Palletizer · Envasado (formado, sellado, envoltura, encajado, paletizado) · Línea base
  • Air Compressor · Servicios (vapor, aire comprimido, agua helada, energía) · Línea base
  • Boiler · Servicios (vapor, aire comprimido, agua helada, energía) · Línea base
  • Cold Compressor · Servicios (vapor, aire comprimido, agua helada, energía) · Línea base
  • Freezer · Refrigeración y congelación · Línea base
  • Mix Plant · Mezclado · Línea base
  • Molding line (mold change / setup process) · Formado, moldeado y dosificado · Línea base
  • Molding line · Línea completa o equipo sin especificar · Línea base