Changeover setup time (internal and external activities)
In short
It appears in about 1 of every 100 lines studied.
When it appears, it takes on average about 57 % of the line's lost time. Reported by 1 of the 37 studies that could observe it (sparse evidence).
What happens
When the line switches product, batch or screen configuration on the twin-screw press, the changeover is split into external activities that can be prepared or finished while the press is still running, and internal activities that can only be performed while the press is stopped, such as screw, screen or seal changes and adjustments. The total setup time lost is the sum of these internal and external tasks plus the time needed to reach stable, on-spec operation again.
What is done about it
Apply SMED methodology to systematically convert internal activities into external ones, standardize and pre-stage tooling, screens and spare parts, use quick-change fixtures and locating devices, and sequence operator tasks so that preparation and verification occur while the press is still processing the previous batch, minimizing the machine-stopped portion of the changeover.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 0.8% [0.1–2.6%]
- Expected share of lost time
- 0.5% [0.1–1.5%]
- Share of lost time when present
- 57% [45–68%]
- Studies / units
- 37 / 44
- Evidence grade
- D
Grade D: 0 or 1 study; the estimate is driven by partial pooling and priors, and the wide interval is the result.
2Probability by segment
- Dairy products1.0% [0.1–4.0%]5 studies
- Soft drinks, bottled water and juices1.0% [0.1–4.1%]1 study
- Brewing, wine and spirits1.0% [0.1–4.1%]1 study
- Bakery and pasta1.0% [0.1–4.4%]0 studies
- Meat, poultry and seafood1.0% [0.1–3.9%]2 studies
- Fruit and vegetable processing1.0% [0.1–3.7%]3 studies
- Grain and oilseed milling1.0% [0.1–4.1%]6 studies
- Sugar and confectionery1.0% [0.1–3.8%]3 studies
- Snacks, coffee, tea and other foods1.0% [0.1–4.0%]4 studies
- Animal feed and pet food1.4% [0.1–5.4%]5 studies
- Food manufacturing (unspecified or mixed)1.0% [0.1–4.0%]7 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceWhen the line switches product, batch or screen configuration on the twin-screw press, the changeover is split into external activities that can be prepared or finished while the press is still running, and internal activities that can only be performed while the press is stopped, such as screw, screen or seal changes and adjustments. The total setup time lost is the sum of these internal and external tasks plus the time needed to reach stable, on-spec operation again.
How it looks in SCADA data
Engineering guidanceMES/SCADA logs show an extended machine state transition to changeover or stopped mode between the last good unit of the previous run and the first good unit of the next, with no production counts recorded; internal and external sub-periods may appear as separate operator-logged activity codes or manual timestamps within the same changeover event. Downstream and upstream equipment often show starvation or blocking states correlated with this stop.
Countermeasure
Engineering guidanceApply SMED methodology to systematically convert internal activities into external ones, standardize and pre-stage tooling, screens and spare parts, use quick-change fixtures and locating devices, and sequence operator tasks so that preparation and verification occur while the press is still processing the previous batch, minimizing the machine-stopped portion of the changeover.
4Sources
- Mejora de la Eficiencia General de los Equipos (EGE) en la etapa de prensado: Un estudio de caso en la industria de harina de pescado (2024)Open sourceShare of lost time: 45.9 % · as reported: “actividades externas”
Show verbatim quote
El tiempo para AE aumentó al 45,94% del total, en comparación con el 14,33% previo a la implementación.
- Mejora de la Eficiencia General de los Equipos (EGE) en la etapa de prensado: Un estudio de caso en la industria de harina de pescado (2024)Open sourceShare of lost time: 54.1 % · as reported: “actividades internas”
Show verbatim quote
El tiempo para AI fue el 54,06% del tiempo total de cambio, comparado con el 85,67% antes de la implementación, mostrando una reducción significativa en el tiempo que la línea de producción está detenida.
- Mejora de la Eficiencia General de los Equipos (EGE) en la etapa de prensado: Un estudio de caso en la industria de harina de pescado (2024)Open sourceLost time: 37.5 min · as reported: “actividades externas”
Show verbatim quote
El tiempo para AI pasó de 95,86 minutos a 44,11 minutos (1,6 horas a 0,74 horas), mientras que para AE aumentó de 16,4 minutos a 37,49 minutos.
- Mejora de la Eficiencia General de los Equipos (EGE) en la etapa de prensado: Un estudio de caso en la industria de harina de pescado (2024)Open sourceLost time: 44.1 min · as reported: “actividades internas”
Show verbatim quote
El tiempo para AI pasó de 95,86 minutos a 44,11 minutos (1,6 horas a 0,74 horas), mientras que para AE aumentó de 16,4 minutos a 37,49 minutos.
- Mejora de la Eficiencia General de los Equipos (EGE) en la etapa de prensado: Un estudio de caso en la industria de harina de pescado (2024)Open sourceLost time: 5,752 s · as reported: “actividades internas”
Show verbatim quote
Se determinó que la duración de las actividades internas fue de 5751,7 segundos, es decir, 95,86 minutos (1.6 h), mientras que las actividades externas fue 962,4 segundos (16,4 min).
- Mejora de la Eficiencia General de los Equipos (EGE) en la etapa de prensado: Un estudio de caso en la industria de harina de pescado (2024)Open sourceLost time: 962 s · as reported: “actividades externas”
Show verbatim quote
Se determinó que la duración de las actividades internas fue de 5751,7 segundos, es decir, 95,86 minutos (1.6 h), mientras que las actividades externas fue 962,4 segundos (16,4 min).
- Mejora de la Eficiencia General de los Equipos (EGE) en la etapa de prensado: Un estudio de caso en la industria de harina de pescado (2024)Open sourceShare of lost time: 14.3 % · as reported: “actividades externas”
Show verbatim quote
Y el 14,33% de las actividades realizadas pertenecen a elementos externos y se realizaran mientras la línea de producción se pone en marcha.
- Mejora de la Eficiencia General de los Equipos (EGE) en la etapa de prensado: Un estudio de caso en la industria de harina de pescado (2024)Open sourceNumber of events: 29.0 pasos · as reported: “actividades internas”
Show verbatim quote
Las actividades internas representan 29 pasos, mientras que las externas solo 4.
- Mejora de la Eficiencia General de los Equipos (EGE) en la etapa de prensado: Un estudio de caso en la industria de harina de pescado (2024)Open sourceNumber of events: 4.00 pasos · as reported: “actividades externas”
Show verbatim quote
Las actividades internas representan 29 pasos, mientras que las externas solo 4.
- Mejora de la Eficiencia General de los Equipos (EGE) en la etapa de prensado: Un estudio de caso en la industria de harina de pescado (2024)Open sourceLost time: 4,896 s · as reported: “TOTAL”
Show verbatim quote
Tras implementar SMED, el tiempo total de cambio se redujo significativamente de 6714,1 segundos a 4896 segundos, mejorando tanto en actividades internas como externas.
- Mejora de la Eficiencia General de los Equipos (EGE) en la etapa de prensado: Un estudio de caso en la industria de harina de pescado (2024)Open sourceNumber of events: 18.0 pasos · as reported: “actividades internas”
Show verbatim quote
El número de actividades internas disminuyó de 29 a 18 (un 37,93% menos) y las actividades externas aumentaron de 4 a 10, reconfigurando el proceso para mayor eficiencia (gráfico 6).
- Mejora de la Eficiencia General de los Equipos (EGE) en la etapa de prensado: Un estudio de caso en la industria de harina de pescado (2024)Open sourceNumber of events: 10.0 pasos · as reported: “actividades externas”
Show verbatim quote
El número de actividades internas disminuyó de 29 a 18 (un 37,93% menos) y las actividades externas aumentaron de 4 a 10, reconfigurando el proceso para mayor eficiencia (gráfico 6).