Setup and adjustments

Pre-production resource staging and preparation

In short

It appears in fewer than 1 of every 100 lines studied.

When it appears, it takes on average about 56 % of the line's lost time. Reported by 0 of the 37 studies that could observe it (sparse evidence).

What happens

Before a run can start the operator must physically move and connect auxiliary resources such as hoses and lines, and must check and stage the raw material, and none of this preparatory work can begin until the previous run has ended, so the equipment remains stopped while these internal setup tasks are carried out.

What is done about it

Apply SMED principles to convert these tasks into external setup performed while the previous run is still active, pre-stage hoses, connections and verified raw material near the point of use, and use standardized checklists so preparation starts before the line actually stops.

Practical guidance written from engineering knowledge; it is not a statistical estimate.

1Probability and evidence

Pooled over all segments. A wide interval is a result: it states how much the evidence allows us to know.
Probability of presence
0.5% [0.1–1.6%]
Expected share of lost time
0.3% [0.0–0.9%]
Share of lost time when present
56% [44–66%]
Studies / units
37 / 44
Evidence grade
D

Grade D: 0 or 1 study; the estimate is driven by partial pooling and priors, and the wide interval is the result.

2Probability by segment

Partially pooled estimates for each industry segment.
  • Dairy products
    0.6% [0.0–2.5%]5 studies
  • Soft drinks, bottled water and juices
    0.6% [0.0–2.7%]1 study
  • Brewing, wine and spirits
    0.6% [0.0–2.6%]1 study
  • Bakery and pasta
    0.6% [0.0–2.4%]0 studies
  • Meat, poultry and seafood
    0.6% [0.0–2.4%]2 studies
  • Fruit and vegetable processing
    0.6% [0.0–2.4%]3 studies
  • Grain and oilseed milling
    0.6% [0.0–2.5%]6 studies
  • Sugar and confectionery
    0.6% [0.0–2.5%]3 studies
  • Snacks, coffee, tea and other foods
    0.6% [0.0–2.6%]4 studies
  • Animal feed and pet food
    0.6% [0.0–2.3%]5 studies
  • Food manufacturing (unspecified or mixed)
    0.6% [0.0–2.4%]7 studies

3Mechanism, SCADA signature and countermeasure

Engineering guidance that helps recognise and address the cause; it is not part of the statistical estimate.

Mechanism

Engineering guidance

Before a run can start the operator must physically move and connect auxiliary resources such as hoses and lines, and must check and stage the raw material, and none of this preparatory work can begin until the previous run has ended, so the equipment remains stopped while these internal setup tasks are carried out.

How it looks in SCADA data

Engineering guidance

The equipment state log shows an extended changeover or setup state with zero throughput and no fault or failure alarm active, often with manually entered stop reasons referencing hose placement, line connection or raw material checks, and the duration is tied to operator availability rather than to any machine signal.

Countermeasure

Engineering guidance

Apply SMED principles to convert these tasks into external setup performed while the previous run is still active, pre-stage hoses, connections and verified raw material near the point of use, and use standardized checklists so preparation starts before the line actually stops.

4Sources

Every extracted datum with its study, value and verbatim quote.
  1. Lost time: 201 s · as reported: “Verificar y preparar la materia prima”
    Show verbatim quote
    Verificar y preparar la materia prima 201, 4
  2. Lost time: 86.7 s · as reported: “Trasladar y preparar manguera de agua”
    Show verbatim quote
    Trasladar y preparar manguera de agua 86,7