Pre-production resource staging and preparation
In short
It appears in fewer than 1 of every 100 lines studied.
When it appears, it takes on average about 56 % of the line's lost time. Reported by 0 of the 37 studies that could observe it (sparse evidence).
What happens
Before a run can start the operator must physically move and connect auxiliary resources such as hoses and lines, and must check and stage the raw material, and none of this preparatory work can begin until the previous run has ended, so the equipment remains stopped while these internal setup tasks are carried out.
What is done about it
Apply SMED principles to convert these tasks into external setup performed while the previous run is still active, pre-stage hoses, connections and verified raw material near the point of use, and use standardized checklists so preparation starts before the line actually stops.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 0.5% [0.1–1.6%]
- Expected share of lost time
- 0.3% [0.0–0.9%]
- Share of lost time when present
- 56% [44–66%]
- Studies / units
- 37 / 44
- Evidence grade
- D
Grade D: 0 or 1 study; the estimate is driven by partial pooling and priors, and the wide interval is the result.
2Probability by segment
- Dairy products0.6% [0.0–2.5%]5 studies
- Soft drinks, bottled water and juices0.6% [0.0–2.7%]1 study
- Brewing, wine and spirits0.6% [0.0–2.6%]1 study
- Bakery and pasta0.6% [0.0–2.4%]0 studies
- Meat, poultry and seafood0.6% [0.0–2.4%]2 studies
- Fruit and vegetable processing0.6% [0.0–2.4%]3 studies
- Grain and oilseed milling0.6% [0.0–2.5%]6 studies
- Sugar and confectionery0.6% [0.0–2.5%]3 studies
- Snacks, coffee, tea and other foods0.6% [0.0–2.6%]4 studies
- Animal feed and pet food0.6% [0.0–2.3%]5 studies
- Food manufacturing (unspecified or mixed)0.6% [0.0–2.4%]7 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceBefore a run can start the operator must physically move and connect auxiliary resources such as hoses and lines, and must check and stage the raw material, and none of this preparatory work can begin until the previous run has ended, so the equipment remains stopped while these internal setup tasks are carried out.
How it looks in SCADA data
Engineering guidanceThe equipment state log shows an extended changeover or setup state with zero throughput and no fault or failure alarm active, often with manually entered stop reasons referencing hose placement, line connection or raw material checks, and the duration is tied to operator availability rather than to any machine signal.
Countermeasure
Engineering guidanceApply SMED principles to convert these tasks into external setup performed while the previous run is still active, pre-stage hoses, connections and verified raw material near the point of use, and use standardized checklists so preparation starts before the line actually stops.
4Sources
- Mejora de la Eficiencia General de los Equipos (EGE) en la etapa de prensado: Un estudio de caso en la industria de harina de pescado (2024)Open sourceLost time: 201 s · as reported: “Verificar y preparar la materia prima”
Show verbatim quote
Verificar y preparar la materia prima 201, 4
- Mejora de la Eficiencia General de los Equipos (EGE) en la etapa de prensado: Un estudio de caso en la industria de harina de pescado (2024)Open sourceLost time: 86.7 s · as reported: “Trasladar y preparar manguera de agua”
Show verbatim quote
Trasladar y preparar manguera de agua 86,7