Tooling preparation and transport delay for changeover
In short
It appears in fewer than 1 of every 100 lines studied.
When it appears, it takes on average about 57 % of the line's lost time. Reported by 0 of the 76 studies that could observe it (sparse evidence).
What happens
During a format or product changeover the required dies, molds or tooling for the press are not staged at the point of use, so operators must locate, retrieve and physically carry them from a storage area before the new setup can begin. This logistics step is performed as internal setup time, while the press remains stopped and waiting, extending the overall changeover duration.
What is done about it
Apply SMED principles by converting this logistics step into external setup: pre-stage the next job's tooling, carts and fixtures next to the press while the current run is still producing, using kitted tool trolleys, labeled storage locations and a standardized retrieval sequence. Schedule a dedicated handler or forklift pass synchronized with the production schedule so tooling arrives at the press before the machine is stopped.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 0.4% [0.1–1.3%]
- Expected share of lost time
- 0.2% [0.0–0.7%]
- Share of lost time when present
- 57% [45–67%]
- Studies / units
- 76 / 96
- Evidence grade
- D
Grade D: 0 or 1 study; the estimate is driven by partial pooling and priors, and the wide interval is the result.
2Probability by segment
- Dairy products0.5% [0.0–1.9%]5 studies
- Soft drinks, bottled water and juices0.5% [0.0–1.8%]11 studies
- Brewing, wine and spirits0.5% [0.0–2.1%]0 studies
- Bakery and pasta0.4% [0.0–1.6%]25 studies
- Meat, poultry and seafood0.5% [0.0–2.0%]3 studies
- Fruit and vegetable processing0.5% [0.0–1.9%]3 studies
- Grain and oilseed milling0.5% [0.0–2.0%]0 studies
- Sugar and confectionery0.5% [0.0–1.9%]8 studies
- Snacks, coffee, tea and other foods0.5% [0.0–1.8%]7 studies
- Animal feed and pet food0.5% [0.0–1.9%]6 studies
- Food manufacturing (unspecified or mixed)0.5% [0.0–2.1%]8 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceDuring a format or product changeover the required dies, molds or tooling for the press are not staged at the point of use, so operators must locate, retrieve and physically carry them from a storage area before the new setup can begin. This logistics step is performed as internal setup time, while the press remains stopped and waiting, extending the overall changeover duration.
How it looks in SCADA data
Engineering guidanceThe press shows an extended setup or idle machine-state with zero cycles and no active fault or alarm, preceding the first cycle of the new run. The pause duration correlates with operator presence/movement logs or manual changeover timestamps rather than with any equipment fault code, and the same transition recurs identically at every changeover between runs requiring different tooling.
Countermeasure
Engineering guidanceApply SMED principles by converting this logistics step into external setup: pre-stage the next job's tooling, carts and fixtures next to the press while the current run is still producing, using kitted tool trolleys, labeled storage locations and a standardized retrieval sequence. Schedule a dedicated handler or forklift pass synchronized with the production schedule so tooling arrives at the press before the machine is stopped.
4Sources
- Mejora de la Eficiencia General de los Equipos (EGE) en la etapa de prensado: Un estudio de caso en la industria de harina de pescado (2024)Open sourceLost time: 112 s · as reported: “Prepare and transport tools to press”
Show verbatim quote
14 Preparar y trasladar herramientas a la prensa 111,8 X