Automatic translation of plant data into management performance metrics: a case for real-time and predictive production control
1Bibliographic record
- Authors
- Alireza Mousavi, H.R.A. Siervo
- Year
- 2016
- Venue
- International Journal of Production Research
- Country
- Germany
- Segment
- Brewing, wine and spirits
- Process family
- Thermal processing
- Study type
- Single case study
- Extraction scope
- Full text
- Size
- 1 plants · 1 lines · 12 machines
- Observation period
- 1 days
- Data collection
- automatic_monitoring
- Intervention
Show the setting as described by the study
The brewhouse production line model measures the utilisation of resources, Overall Equipment Effectiveness, and Overall Line Effectiveness in real-time and fast-forward mode simulation.
2Risk of bias
Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 14Low risk
| Item | Score |
|---|---|
| Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product, process and equipment are all described. | 2 / 2 |
| Is the observation period long enough and reported?Period reported but shorter than 30 days, or only the number of shifts is given. | 1 / 2 |
| How were loss data collected?Automatic line monitoring, or systematic logs covering every stop in the period. | 2 / 2 |
| Are OEE, loading time and the loss categories defined explicitly?Formulae or definitions are given for the reported metrics, including what counts as planned time. | 2 / 2 |
| Does the loss breakdown account for the total loss it claims to explain?Only the top causes are reported and the unexplained remainder can be computed. | 1 / 2 |
| Is there evidence of selective reporting of favourable results?Observational study, or intervention study that reports baseline and post-intervention data with the same method. | 2 / 2 |
| Are the reported numbers internally consistent?Recomputed totals, shares and OEE factors agree with the reported values within 2 percentage points. | 2 / 2 |
| Could conflicts of interest or the source of the data bias the result?Academic or independent study, or conflicts declared and unrelated to the result. | 2 / 2 |
3Extracted data
Each datum with its classification and the verbatim quote that states it.
| Reported cause | Loss category | Metric | Value | Extraction |
|---|---|---|---|---|
—LauterstarShow verbatim quote (Figure 10)1.00 0.73 0.27 1.00 Lauterstar OEE Efficiency components | none | Availability | 1.00 ratio | Both extractors agreed |
—Malt TransportShow verbatim quote (Figure 9)1.00 0.40 0.93 1.00 Availability (AE) Operational (OE) Rate (RE) Quality (QE) Malt Transport OEE Efficiency components | none | Availability | 1.00 ratio | Single extractor |
—Malt TransportShow verbatim quote (Figure 9)1.00 0.40 0.93 1.00 Availability (AE) Operational (OE) Rate (RE) Quality (QE) Malt Transport OEE Efficiency components | none | Performance | 0.930 ratio | Single extractor |
—Malt TransportShow verbatim quote (Figure 9)1.00 0.40 0.93 1.00 Availability (AE) Operational (OE) Rate (RE) Quality (QE) Malt Transport OEE Efficiency components | none | Quality | 1.00 ratio | Single extractor |
—LauterstarShow verbatim quote (Figure 10)1.00 0.73 0.27 1.00 Lauterstar OEE Efficiency components | none | Performance | 0.270 ratio | Single extractor |
—LauterstarShow verbatim quote (Figure 10)1.00 0.73 0.27 1.00 Lauterstar OEE Efficiency components | none | Quality | 1.00 ratio | Single extractor |
—Prerun TankShow verbatim quote (Figure 10)1.00 0.30 0.93 1.00 PRerun Tank OEE Efficiency components | none | Availability | 1.00 ratio | Single extractor |
—Prerun TankShow verbatim quote (Figure 10)1.00 0.30 0.93 1.00 PRerun Tank OEE Efficiency components | none | Performance | 0.930 ratio | Single extractor |
—Prerun TankShow verbatim quote (Figure 10)1.00 0.30 0.93 1.00 PRerun Tank OEE Efficiency components | none | Quality | 1.00 ratio | Single extractor |
—Brewhouse lineShow verbatim quote (Figure 11)1.00 0.68 LA LPQP OLE components | none | Availability | 1.00 ratio | Single extractor |
—MashtunShow verbatim quote (Page 11)In this example, the real bottleneck is the Mashtun with a scheduled utilisation of 0.907. | none | Share of planned time | 0.907 - | Single extractor |
Observation units
- Lauterstar · Separation (centrifugation, filtration, membranes) · Baseline
- Malt Transport · Conveying and accumulation · Baseline
- Prerun Tank · Separation (centrifugation, filtration, membranes) · Baseline
- Brewhouse line · Whole line or unspecified equipment · Baseline
- Mashtun · Mixing and blending · Baseline