Changeover adjustment time to first good unit
In short
It appears in fewer than 1 of every 100 lines studied.
When it appears, it takes on average about 56 % of the line's lost time. Reported by 0 of the 76 studies that could observe it (sparse evidence).
What happens
After a product or format changeover on the forming station, the mould, mandrel or tooling and the process parameters (temperature, pressure, alignment) must be adjusted and stabilised before the machine can produce a conforming form or product. The time and material consumed between the last good unit of the previous run and the first good form or product of the new run is counted as setup and adjustment loss.
What is done about it
Standardise changeover procedures with predefined set points and tooling positions, use quick-change tooling and automated recipe recall to shorten the adjustment window, and track time and scrap to first good unit as a changeover performance indicator to drive continuous improvement.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 0.4% [0.1–1.3%]
- Expected share of lost time
- 0.2% [0.0–0.7%]
- Share of lost time when present
- 56% [44–67%]
- Studies / units
- 76 / 96
- Evidence grade
- D
Grade D: 0 or 1 study; the estimate is driven by partial pooling and priors, and the wide interval is the result.
2Probability by segment
- Dairy products0.5% [0.0–2.0%]5 studies
- Soft drinks, bottled water and juices0.5% [0.0–1.9%]11 studies
- Brewing, wine and spirits0.5% [0.0–2.0%]0 studies
- Bakery and pasta0.4% [0.0–1.7%]25 studies
- Meat, poultry and seafood0.5% [0.0–1.9%]3 studies
- Fruit and vegetable processing0.5% [0.0–2.0%]3 studies
- Grain and oilseed milling0.5% [0.0–2.0%]0 studies
- Sugar and confectionery0.5% [0.0–1.9%]8 studies
- Snacks, coffee, tea and other foods0.5% [0.0–1.8%]7 studies
- Animal feed and pet food0.5% [0.0–1.9%]6 studies
- Food manufacturing (unspecified or mixed)0.5% [0.0–2.0%]8 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceAfter a product or format changeover on the forming station, the mould, mandrel or tooling and the process parameters (temperature, pressure, alignment) must be adjusted and stabilised before the machine can produce a conforming form or product. The time and material consumed between the last good unit of the previous run and the first good form or product of the new run is counted as setup and adjustment loss.
How it looks in SCADA data
Engineering guidanceSCADA/MES shows a changeover or setup machine state bounded by the end-of-run event and a quality or counter event tagged as first good part, with repeated micro-adjustments of set points and no stable production counter increment during this interval. Rejected or scrap counts from trial pieces may accumulate before the first good unit flag is raised.
Countermeasure
Engineering guidanceStandardise changeover procedures with predefined set points and tooling positions, use quick-change tooling and automated recipe recall to shorten the adjustment window, and track time and scrap to first good unit as a changeover performance indicator to drive continuous improvement.
4Sources
- CHANGEOVER TIME REDUCTION THROUGH LEAN TOOL “SMED” – A CASE STUDY FROM FOOD SECTOR (2018)Open sourceMean event duration: 3.00 min · as reported: “First good form”
Show verbatim quote
First good form: 0:03:00
- CHANGEOVER TIME REDUCTION THROUGH LEAN TOOL “SMED” – A CASE STUDY FROM FOOD SECTOR (2018)Open sourceMean event duration: 27.0 min · as reported: “First good product”
Show verbatim quote
First good product: 0:27:00