Included study
CHANGEOVER TIME REDUCTION THROUGH LEAN TOOL “SMED” – A CASE STUDY FROM FOOD SECTOR
1Bibliographic record
- Authors
- Kateřina Gálová
- Year
- 2018
- Venue
- International Bata Conference for Ph.D. Students and Young Researchers (DOKBAT)
- Country
- Czech Republic
- Segment
- Sugar and confectionery
- Process family
- Forming, baking and cooking
- Study type
- Before/after intervention
- Extraction scope
- Full text
- Size
- 1 plants · 5 lines · — machines
- Observation period
- 365 days
- Data collection
- automatic_monitoring
- Intervention
Show the setting as described by the study
The plant itself, in which the case study was processed, focuses on the production of chocolate and chocolate confectionery.
2Risk of bias
Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 10Moderate risk
| Item | Score |
|---|---|
| Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product, process and equipment are all described. | 2 / 2 |
| Is the observation period long enough and reported?Period reported but shorter than 30 days, or only the number of shifts is given. | 1 / 2 |
| How were loss data collected?Manual logs or maintenance records with unknown completeness. | 1 / 2 |
| Are OEE, loading time and the loss categories defined explicitly?A standard definition is cited but its application is not shown. | 1 / 2 |
| Does the loss breakdown account for the total loss it claims to explain?Only the top causes are reported and the unexplained remainder can be computed. | 1 / 2 |
| Is there evidence of selective reporting of favourable results?Observational study, or intervention study that reports baseline and post-intervention data with the same method. | 2 / 2 |
| Are the reported numbers internally consistent?Small inconsistencies (2 to 10 percentage points) or values that cannot be cross-checked. | 1 / 2 |
| Could conflicts of interest or the source of the data bias the result?Authors are employees of the plant or of an equipment/software vendor; no declaration. | 1 / 2 |
3Extracted data
Each datum with its classification and the verbatim quote that states it.
| Reported cause | Loss category | Metric | Value | Extraction |
|---|---|---|---|---|
—Show verbatim quote (Section 4.2 Actual impacts of the project, p.111)Savings in the form of released production were 21 tons / year. | none | Throughput | 21.0 tons/year | Both extractors agreed |
Internal activitiesShow verbatim quote (Section 4.2, Figure 9, p.111)Internal activities occupied 83% of the total time. | Setup and adjustments | Share of lost time | 83.0 % | Both extractors agreed |
changeover (selected type, average, long-run)Show verbatim quote (Section 4.2 Actual impacts of the project, p.111)The new changeover time was even lower than the project goal, but in the long run, the time was 210 minutes. This time is kept without any major problems. | Setup and adjustments | Mean event duration | 210 min | Both extractors agreed |
changeover (selected type, annual frequency)Show verbatim quote (Section 4.2, p.109)At a frequency of 58 changeovers per year and with a given number of operators and wage rates, the annual savings would be 91 thousand. CZK. | Setup and adjustments | Number of events | 58.0 events/year | Both extractors agreed |
changeover (selected type, average)Show verbatim quote (Section 4.2 Specification of the project objective, p.109)The project team decided on the main goal of the project, which was to reduce the time of the selected sort by 10% of the average changeover time, from 244 minutes to 220 minutes. | Setup and adjustments | Mean event duration | 244 min | Both extractors agreed |
Planned stoppagesShow verbatim quote (Section 4.1 / Figure 4, p.108)It is clear from the chart that the most important were planned stoppages with total time 10184 hours. | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 10,184 hours | Single extractor |
Planned stoppagesShow verbatim quote (Section 5 Conclusion, p.113)Plates fall into planned stoppages, accounting for 61% of all stoppages of the company. | Planned downtime (scheduled maintenance, breaks, no demand) | Share of lost time | 61.0 % | Single extractor |
ChangeoversShow verbatim quote (Section 5 Conclusion, p.113)Changeovers on a particular selected line then account for a total of 77% of all planned stoppages on this line. | Setup and adjustments | Share of lost time | 77.0 % | Single extractor |
changeover (most frequent type)Show verbatim quote (Section 4.1, Figure 8, p.109)Of these types of changeovers, the fourth longest changeover was the most frequent (which would take 185 minutes), but the longest and second most frequent type of changeover (240 minutes) was eventually chosen by project team for the next step. | Setup and adjustments | Mean event duration | 185 min | Single extractor |
changeover (selected type for SMED project)Show verbatim quote (Section 4.1, Figure 8, p.109)Of these types of changeovers, the fourth longest changeover was the most frequent (which would take 185 minutes), but the longest and second most frequent type of changeover (240 minutes) was eventually chosen by project team for the next step. | Setup and adjustments | Mean event duration | 240 min | Single extractor |
External activitiesShow verbatim quote (Figure 9, p.111)internal; 83% external; 17% breakdown; 6% Figure 9 Internal vs external activities. Source: own | Setup and adjustments | Share of lost time | 17.0 % | Single extractor |
breakdown (within changeover)valveShow verbatim quote (Figure 9, p.111)internal; 83% external; 17% breakdown; 6% Figure 9 Internal vs external activities. Source: own | Equipment failure (breakdowns) | Share of lost time | 6.00 % | Single extractor |
changeover (selected type, average, first re-measurement)Show verbatim quote (Section 4.2 Actual impacts of the project, p.111)The average throw time dropped from 244 minutes to 194 minutes (Figure 7) and the target was met. | Setup and adjustments | Mean event duration | 194 min | Single extractor |
Flushing massesShow verbatim quote (Table 6 (Changeover activities))Flushing masses: 0:39:00 | Setup and adjustments | Mean event duration | 39.0 min | Single extractor |
Dismantling the dividerShow verbatim quote (Table 6 (Changeover activities))Dismantling the divider: 0:28:00 | Setup and adjustments | Mean event duration | 28.0 min | Single extractor |
Assembly of dividersShow verbatim quote (Table 6 (Changeover activities))Assembly of dividers: 0:22:00 | Setup and adjustments | Mean event duration | 22.0 min | Single extractor |
Valve failureShow verbatim quote (Table 6 (Changeover activities))Valve failure: 0:13:00 | Setup and adjustments | Mean event duration | 13.0 min | Single extractor |
Flush with butterShow verbatim quote (Table 6 (Changeover activities))Flush with butter: 0:06:00 | Setup and adjustments | Mean event duration | 6.00 min | Single extractor |
Exchange of moldsShow verbatim quote (Table 6 (Changeover activities))Exchange of molds: 0:04:00 | Setup and adjustments | Mean event duration | 4.00 min | Single extractor |
Forming of moldsShow verbatim quote (Table 6 (Changeover activities))Forming of molds: 0:07:00 | Setup and adjustments | Mean event duration | 7.00 min | Single extractor |
Blowing the front of the bassShow verbatim quote (Table 6 (Changeover activities))Blowing the front of the bass: 0:06:00 | Setup and adjustments | Mean event duration | 6.00 min | Single extractor |
Start of productionShow verbatim quote (Table 6 (Changeover activities))Start of production: 0:03:00 | Setup and adjustments | Mean event duration | 3.00 min | Single extractor |
First good formShow verbatim quote (Table 6 (Changeover activities))First good form: 0:03:00 | Setup and adjustments | Mean event duration | 3.00 min | Single extractor |
First good productShow verbatim quote (Table 6 (Changeover activities))First good product: 0:27:00 | Setup and adjustments | Mean event duration | 27.0 min | Single extractor |
—Show verbatim quote (Section 4.2, Table 8 (Financial impact of the project))At a frequency of 58 changeovers per year and with a given number of operators and wage rates, the annual savings would be 91 thousand. CZK. | Setup and adjustments | Number of events | 58.0 events | Single extractor |
Observation units
- D1 line · Forming, moulding and depositing · After intervention
- D1 line · Forming, moulding and depositing · Baseline
- Whole plant · Whole line or unspecified equipment · Baseline