In short
It appears in fewer than 1 of every 100 lines studied.
When it appears, it takes on average about 56 % of the line's lost time. Reported by 0 of the 76 studies that could observe it (sparse evidence).
What happens
When switching between products or masses (e.g. butter or other filling/forming compounds), residual material left in hoppers, pipes, dies or depositors must be flushed out before the new product can be run, so forming equipment is fed and cycled with purge material rather than producing saleable units. This purging step is a scheduled part of the changeover sequence and lengthens the time between the last good unit of the previous run and the first good unit of the next.
What is done about it
Standardize and document the flush/purge sequence, minimizing the volume and time of purge material needed by using dedicated purge compounds, optimized line geometry and quick-release fittings, and track purge duration as a changeover KPI to drive continuous improvement toward faster, more repeatable transitions.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 0.4% [0.1–1.2%]
- Expected share of lost time
- 0.2% [0.0–0.7%]
- Share of lost time when present
- 56% [44–67%]
- Studies / units
- 76 / 96
- Evidence grade
- D
Grade D: 0 or 1 study; the estimate is driven by partial pooling and priors, and the wide interval is the result.
2Probability by segment
- Dairy products0.5% [0.0–1.8%]5 studies
- Soft drinks, bottled water and juices0.5% [0.0–1.8%]11 studies
- Brewing, wine and spirits0.5% [0.0–1.9%]0 studies
- Bakery and pasta0.4% [0.0–1.5%]25 studies
- Meat, poultry and seafood0.5% [0.0–1.8%]3 studies
- Fruit and vegetable processing0.5% [0.0–2.0%]3 studies
- Grain and oilseed milling0.5% [0.0–2.0%]0 studies
- Sugar and confectionery0.5% [0.0–2.0%]8 studies
- Snacks, coffee, tea and other foods0.5% [0.0–1.9%]7 studies
- Animal feed and pet food0.5% [0.0–1.9%]6 studies
- Food manufacturing (unspecified or mixed)0.5% [0.0–1.8%]8 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceWhen switching between products or masses (e.g. butter or other filling/forming compounds), residual material left in hoppers, pipes, dies or depositors must be flushed out before the new product can be run, so forming equipment is fed and cycled with purge material rather than producing saleable units. This purging step is a scheduled part of the changeover sequence and lengthens the time between the last good unit of the previous run and the first good unit of the next.
How it looks in SCADA data
Engineering guidanceMES/SCADA shows the line in changeover or setup state with the forming machine cycling but zero or near-zero good-unit counts, together with flow, dosing or temperature signals consistent with purge material passing through the system rather than final product. The duration of this state is logged as part of the setup event and precedes the ramp-up to stable production.
Countermeasure
Engineering guidanceStandardize and document the flush/purge sequence, minimizing the volume and time of purge material needed by using dedicated purge compounds, optimized line geometry and quick-release fittings, and track purge duration as a changeover KPI to drive continuous improvement toward faster, more repeatable transitions.
4Sources
- CHANGEOVER TIME REDUCTION THROUGH LEAN TOOL “SMED” – A CASE STUDY FROM FOOD SECTOR (2018)Open sourceMean event duration: 39.0 min · as reported: “Flushing masses”
Show verbatim quote
Flushing masses: 0:39:00
- CHANGEOVER TIME REDUCTION THROUGH LEAN TOOL “SMED” – A CASE STUDY FROM FOOD SECTOR (2018)Open sourceMean event duration: 6.00 min · as reported: “Flush with butter”
Show verbatim quote
Flush with butter: 0:06:00