In-process quality check (Brix, acidity, pH, appearance)
In short
It appears in about 1 of every 100 lines studied.
When it appears, it takes on average about 57 % of the line's lost time. Reported by 1 of the 79 studies that could observe it (sparse evidence).
What happens
The production flow includes a quality check step where samples are drawn from the batch or line and tested for Brix, titratable acidity, pH and visual appearance before the product can be released to continue; this requires transporting the sample to a check station, performing the measurement or correlation calculation, and waiting for QC clearance. The physical location of the check station and the hand-off between production and quality personnel can add idle time that is organizational rather than mechanical in origin.
What is done about it
Replace or complement off-line laboratory testing with inline or at-line rapid Brix-pH-acidity measurement to shorten the wait for release, position the check station to minimize sample transport distance, and establish clear hand-off procedures and release criteria between production and quality teams so that waiting time is kept to a minimum.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 0.7% [0.1–1.9%]
- Expected share of lost time
- 0.4% [0.1–1.1%]
- Share of lost time when present
- 57% [46–68%]
- Studies / units
- 79 / 101
- Evidence grade
- D
Grade D: 0 or 1 study; the estimate is driven by partial pooling and priors, and the wide interval is the result.
2Probability by segment
- Dairy products0.8% [0.1–2.9%]10 studies
- Soft drinks, bottled water and juices0.9% [0.1–2.8%]26 studies
- Brewing, wine and spirits0.7% [0.1–2.8%]12 studies
- Bakery and pasta0.8% [0.1–3.2%]0 studies
- Meat, poultry and seafood0.8% [0.1–3.0%]4 studies
- Fruit and vegetable processing0.8% [0.1–3.1%]4 studies
- Grain and oilseed milling0.8% [0.1–2.8%]3 studies
- Sugar and confectionery0.8% [0.1–3.0%]3 studies
- Snacks, coffee, tea and other foods0.8% [0.1–3.1%]4 studies
- Animal feed and pet food0.8% [0.1–3.1%]4 studies
- Food manufacturing (unspecified or mixed)0.8% [0.1–2.9%]9 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceThe production flow includes a quality check step where samples are drawn from the batch or line and tested for Brix, titratable acidity, pH and visual appearance before the product can be released to continue; this requires transporting the sample to a check station, performing the measurement or correlation calculation, and waiting for QC clearance. The physical location of the check station and the hand-off between production and quality personnel can add idle time that is organizational rather than mechanical in origin.
How it looks in SCADA data
Engineering guidanceSCADA/MES records the line or workstation in a hold or wait state with no product movement and no active equipment fault alarm, often logged as an unspecified or organizational stop. Cycle or batch counters pause while awaiting lab or correlation-based results, and relocating the check station can shift the timing or sequence of logged events relative to upstream and downstream stations.
Countermeasure
Engineering guidanceReplace or complement off-line laboratory testing with inline or at-line rapid Brix-pH-acidity measurement to shorten the wait for release, position the check station to minimize sample transport distance, and establish clear hand-off procedures and release criteria between production and quality teams so that waiting time is kept to a minimum.
4Sources
- An implementation of lean technology to improve the lead time of syrup batching process and reduce hot fill line downtime (2023)Open sourceLost time: 20.0 min · as reported: “quality check step (QC parameters: Brix, acidity, pH, appearance)”
Show verbatim quote
The total time for QC to complete the job is around 20 minutes.
- An implementation of lean technology to improve the lead time of syrup batching process and reduce hot fill line downtime (2023)Open sourceLost time: 5.00 min · as reported: “quality check step after rearrangement”
Show verbatim quote
After rearranging the quality test for syrup output parameters, the time to complete batching and move to filling step is shortened to only 5 minutes.
- An implementation of lean technology to improve the lead time of syrup batching process and reduce hot fill line downtime (2023)Open sourceShare of lost time: 8.57 % · as reported: “Brix check station relocation”
Show verbatim quote
The process is cut down 10-12 minutes of downtime (8.57%).
- An implementation of lean technology to improve the lead time of syrup batching process and reduce hot fill line downtime (2023)Open sourceMean event duration: 20.0 min · as reported: “quality check for Brix, acidity (TA), pH, appearance”
Show verbatim quote
The total time for QC to complete the job is around 20 minutes.
- An implementation of lean technology to improve the lead time of syrup batching process and reduce hot fill line downtime (2023)Open sourceMean event duration: 5.00 min · as reported: “quality check for Brix, pH, TA using correlation equation method”
Show verbatim quote
After rearranging the quality test for syrup output parameters, the time to complete batching and move to filling step is shortened to only 5 minutes. In addition, it ensures that the product quality meet the standards when the TA measurement step is taken place at the same time with the filling stage.