Scheduled maintenance and cleaning stop (excluded from OEE)

In short

It appears in about 1 of every 100 lines studied.

When it appears, it takes on average about 57 % of the line's lost time. Reported by 1 of the 127 studies that could observe it (sparse evidence).

What happens

The line is deliberately stopped according to a schedule to carry out preventive maintenance tasks or sanitation and line cleaning, and may also include other administrative or externally imposed stoppages that fall outside the direct responsibility of production management. Because these stops are anticipated and planned in advance, they are treated as a baseline reduction of available time rather than as a performance loss.

What is done about it

The usual engineering practice is to schedule these stops during periods of low demand, codify them clearly as planned events in the SCADA/MES calendar so they are excluded from availability loss calculations, and periodically audit their actual duration against the plan to prevent drift into unplanned downtime.

Practical guidance written from engineering knowledge; it is not a statistical estimate.

1Probability and evidence

Pooled over all segments. A wide interval is a result: it states how much the evidence allows us to know.
Probability of presence
0.6% [0.1–1.5%]
Expected share of lost time
0.3% [0.1–0.9%]
Share of lost time when present
57% [46–68%]
Studies / units
127 / 161
Evidence grade
D

Grade D: 0 or 1 study; the estimate is driven by partial pooling and priors, and the wide interval is the result.

2Probability by segment

Partially pooled estimates for each industry segment.
  • Dairy products
    0.6% [0.1–2.3%]13 studies
  • Soft drinks, bottled water and juices
    0.6% [0.1–1.9%]26 studies
  • Brewing, wine and spirits
    0.6% [0.1–2.3%]11 studies
  • Bakery and pasta
    0.6% [0.1–2.0%]24 studies
  • Meat, poultry and seafood
    0.6% [0.1–2.4%]9 studies
  • Fruit and vegetable processing
    0.7% [0.1–2.4%]7 studies
  • Grain and oilseed milling
    1.0% [0.1–3.6%]6 studies
  • Sugar and confectionery
    0.6% [0.1–2.3%]9 studies
  • Snacks, coffee, tea and other foods
    0.6% [0.1–2.4%]5 studies
  • Animal feed and pet food
    0.6% [0.1–2.3%]7 studies
  • Food manufacturing (unspecified or mixed)
    0.6% [0.1–2.4%]10 studies

3Mechanism, SCADA signature and countermeasure

Engineering guidance that helps recognise and address the cause; it is not part of the statistical estimate.

Mechanism

Engineering guidance

The line is deliberately stopped according to a schedule to carry out preventive maintenance tasks or sanitation and line cleaning, and may also include other administrative or externally imposed stoppages that fall outside the direct responsibility of production management. Because these stops are anticipated and planned in advance, they are treated as a baseline reduction of available time rather than as a performance loss.

How it looks in SCADA data

Engineering guidance

SCADA/MES records show a line state explicitly tagged as planned stop, maintenance or cleaning, with start and end times aligned to the maintenance or sanitation schedule rather than triggered by a fault alarm. Production and fault counters remain flat during this interval, and no starvation or blocking pattern appears on upstream or downstream equipment.

Countermeasure

Engineering guidance

The usual engineering practice is to schedule these stops during periods of low demand, codify them clearly as planned events in the SCADA/MES calendar so they are excluded from availability loss calculations, and periodically audit their actual duration against the plan to prevent drift into unplanned downtime.

4Sources

Every extracted datum with its study, value and verbatim quote.
  1. Share of lost time: 17.6 % · as reported: “Paradas planejadas (g1) - manutenção preventiva e limpeza de linha”
    Show verbatim quote
    Perdas por paradas planejadas (g1) por causas como manutenção preventiva e limpeza de linha que representavam cerca de 17,6% do tempo total de paradas;
  2. Share of lost time: 71.0 % · as reported: “Causas não consideradas pelo OEEL (a1, b3, e5, g1)”
    Show verbatim quote
    as causas que provocavam paradas não consideradas pelo OEEL (a1, b3, e5, g1) representavam 71% do tempo total de paradas, conforme mostra a Figura 6.
  3. Lost time: 51.9 h · as reported: “Paradas planejadas e outras causas fora da responsabilidade dos gestores”
    Show verbatim quote
    perdas por paradas planejadas e outras causas fora da responsabilidade dos gestores da área operacional, somadas, foram responsáveis por uma perda de volume de produção maior, que se manteve em torno de 187 t por semana (51,9 horas perdidas por semana) nas fases 1 e 2.