In short
It appears in fewer than 1 of every 100 lines studied.
When it appears, it takes on average about 55 % of the line's lost time. Reported by 0 of the 60 studies that could observe it (sparse evidence).
What happens
During a product or format change on the baking line, intermediate materials, trays, molds or semi-finished product must be moved into or retrieved from a storage or staging area before the line can be reconfigured and restarted. This handling and waiting activity extends the gap between the last good unit of one run and the first good unit of the next, even though no fault or mechanical repair is involved.
What is done about it
Pre-stage trays, molds or ingredients close to the line before the scheduled changeover begins, and synchronize storage retrieval or putaway with the changeover plan so it runs in parallel with other setup tasks. Use buffer stock or kanban-type staging areas near the baking line to decouple storage movement time from the critical changeover path.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 0.4% [0.1–1.4%]
- Expected share of lost time
- 0.2% [0.0–0.8%]
- Share of lost time when present
- 55% [42–66%]
- Studies / units
- 60 / 73
- Evidence grade
- D
Grade D: 0 or 1 study; the estimate is driven by partial pooling and priors, and the wide interval is the result.
2Probability by segment
- Dairy products0.5% [0.0–2.2%]5 studies
- Soft drinks, bottled water and juices0.5% [0.0–2.0%]1 study
- Brewing, wine and spirits0.5% [0.0–2.1%]0 studies
- Bakery and pasta0.5% [0.0–1.8%]27 studies
- Meat, poultry and seafood0.5% [0.0–2.2%]2 studies
- Fruit and vegetable processing0.5% [0.0–2.1%]2 studies
- Grain and oilseed milling0.5% [0.0–2.3%]0 studies
- Sugar and confectionery0.5% [0.0–2.1%]8 studies
- Snacks, coffee, tea and other foods0.5% [0.0–2.3%]4 studies
- Animal feed and pet food0.5% [0.0–2.1%]4 studies
- Food manufacturing (unspecified or mixed)0.5% [0.0–2.1%]7 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceDuring a product or format change on the baking line, intermediate materials, trays, molds or semi-finished product must be moved into or retrieved from a storage or staging area before the line can be reconfigured and restarted. This handling and waiting activity extends the gap between the last good unit of one run and the first good unit of the next, even though no fault or mechanical repair is involved.
How it looks in SCADA data
Engineering guidanceShows up as an extended changeover or idle machine-state with no cycle counts and no fault alarms, often bracketed by logged transactions or signals from an adjacent storage/buffer area indicating material movement. Line status transitions directly from changeover to running with a long dwell time that does not correlate with any maintenance work order.
Countermeasure
Engineering guidancePre-stage trays, molds or ingredients close to the line before the scheduled changeover begins, and synchronize storage retrieval or putaway with the changeover plan so it runs in parallel with other setup tasks. Use buffer stock or kanban-type staging areas near the baking line to decouple storage movement time from the critical changeover path.
4Sources
- Modelo propuesto para la implementación de la metodología SMED en una empresa de alimentos de Santiago de Cali (2017)Open sourceNumber of events: 21.0 events · as reported: “Storage”
Show verbatim quote
Almacenajes 21 24:30