Included study
PLANT MAINTENANCE STRATEGY FOR IMPROVED PRODUCTION IN THE FOOD AND BEVERAGE INDUSTRIES
1Bibliographic record
- Authors
- Onyejaka, Chidi Maurice
- Year
- 2024
- Venue
- —
- Country
- Nigeria
- Segment
- Soft drinks, bottled water and juices
- Process family
- Filling and packaging line
- Study type
- Multiple case study
- Extraction scope
- Full text
- Size
- 3 plants · — lines · 5 machines
- Observation period
- 1,825 days
- Data collection
- manual_logs
- Intervention
Show the setting as described by the study
Table 4.1 shows that the Filler machine – Benin Plant was purchased in 2008 and the type of maintenance approaches carried out were preventive and usage-based maintenance. The machine has a capacity of 1650CPH – (CPH: Cases Per Hour).
2Risk of bias
Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 12Moderate risk
| Item | Score |
|---|---|
| Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product, process and equipment are all described. | 2 / 2 |
| Is the observation period long enough and reported?Period reported and at least 30 days of production (or at least 100 recorded events). | 2 / 2 |
| How were loss data collected?Manual logs or maintenance records with unknown completeness. | 1 / 2 |
| Are OEE, loading time and the loss categories defined explicitly?Formulae or definitions are given for the reported metrics, including what counts as planned time. | 2 / 2 |
| Does the loss breakdown account for the total loss it claims to explain?Only the top causes are reported and the unexplained remainder can be computed. | 1 / 2 |
| Is there evidence of selective reporting of favourable results?Observational study, or intervention study that reports baseline and post-intervention data with the same method. | 2 / 2 |
| Are the reported numbers internally consistent?Inconsistencies above 10 percentage points, or OEE factors above 100%. | 0 / 2 |
| Could conflicts of interest or the source of the data bias the result?Academic or independent study, or conflicts declared and unrelated to the result. | 2 / 2 |
3Extracted data
Each datum with its classification and the verbatim quote that states it.
| Reported cause | Loss category | Metric | Value | Extraction |
|---|---|---|---|---|
—Filler machineShow verbatim quote (Table 4.5)Year five (2021) 99.9 | none | Quality | 99.9 % | Both extractors agreed |
—Filler machineShow verbatim quote (Table 4.4)Year Five (2021) 113.63% | none | Performance | 114 % | Both extractors agreed |
—Filler machineShow verbatim quote (Table 4.4)Year Four (2020) 66.23% | none | Performance | 66.2 % | Both extractors agreed |
—Filler machineShow verbatim quote (Table 4.4)Year Three(2019) 129.32% | none | Performance | 129 % | Both extractors agreed |
—Filler machineShow verbatim quote (Table 4.4)Year Two (2018) 108.25% | none | Performance | 108 % | Both extractors agreed |
—Filler machineShow verbatim quote (Table 4.4)Year One (2017) 104.11% | none | Performance | 104 % | Both extractors agreed |
—Filler machineShow verbatim quote (Table 4.3)Year Five (2021) 96.9 | none | Availability | 96.9 % | Both extractors agreed |
—Filler machineShow verbatim quote (Table 4.3)Year Four (2020) 92.5 | none | Availability | 92.5 % | Both extractors agreed |
—Filler machineShow verbatim quote (Table 4.3)Year Three(2019) 96.0 | none | Availability | 96.0 % | Both extractors agreed |
—Filler machineShow verbatim quote (Table 4.3)Year Two (2018) 95.6 | none | Availability | 95.6 % | Both extractors agreed |
—Filler machineShow verbatim quote (Table 4.3)Year One (2017) 94.8 | none | Availability | 94.8 % | Both extractors agreed |
machine breakdownFiller machineShow verbatim quote (Table 4.2)Total number of hours of breakdown per year(hours) 123.66 107.33 146.33 153.4 108.5 | Equipment failure (breakdowns) | Lost time | 124 hours | Single extractor |
machine breakdownFiller machineShow verbatim quote (Table 4.2)Total number of hours of breakdown per year(hours) 123.66 107.33 146.33 153.4 108.5 | Equipment failure (breakdowns) | Lost time | 107 hours | Single extractor |
machine breakdownFiller machineShow verbatim quote (Table 4.2)Total number of hours of breakdown per year(hours) 123.66 107.33 146.33 153.4 108.5 | Equipment failure (breakdowns) | Lost time | 146 hours | Single extractor |
machine breakdownFiller machineShow verbatim quote (Table 4.2)Total number of hours of breakdown per year(hours) 123.66 107.33 146.33 153.4 108.5 | Equipment failure (breakdowns) | Lost time | 153 hours | Single extractor |
machine breakdownFiller machineShow verbatim quote (Table 4.2)Total number of hours of breakdown per year(hours) 123.66 107.33 146.33 153.4 108.5 | Equipment failure (breakdowns) | Lost time | 109 hours | Single extractor |
Observation units
- Filler Machine - NBC Benin Plant · Filling · Baseline