Filler equipment breakdown (unspecified failure mode)
In short
It appears in about 4 of every 100 lines studied.
When it appears, it takes on average about 58 % of the line's lost time. Reported by 17 of the 120 studies that could observe it (strong evidence).
What happens
The filling machine stops unexpectedly due to a mechanical, electrical, pneumatic or control fault that degrades or interrupts its function, and the line cannot resume normal operation until maintenance personnel diagnose and repair the fault. The primary records only report the event as a generic breakdown without identifying the specific failed component or subsystem.
What is done about it
Apply root-cause failure analysis supported by condition monitoring and detailed fault logging to identify the specific failing component, then implement targeted preventive or predictive maintenance, spare-parts readiness and operator fault-detection training to reduce repair time and recurrence.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 3.7% [1.4–7.5%]
- Expected share of lost time
- 2.2% [0.8–4.4%]
- Share of lost time when present
- 58% [48–66%]
- Studies / units
- 120 / 162
- Evidence grade
- A
Grade A: 10 or more studies and 10 or more distinct lines, with a 95% credible interval narrower than 0.20.
2Probability by segment
- Dairy products5.5% [1.3–13.0%]18 studies
- Soft drinks, bottled water and juices6.1% [2.4–11.6%]44 studies
- Brewing, wine and spirits3.1% [0.7–7.9%]16 studies
- Bakery and pasta4.4% [0.8–13.1%]0 studies
- Meat, poultry and seafood5.0% [1.1–13.9%]6 studies
- Fruit and vegetable processing4.0% [0.7–11.6%]4 studies
- Grain and oilseed milling3.8% [0.7–10.8%]6 studies
- Sugar and confectionery4.0% [0.7–11.8%]3 studies
- Snacks, coffee, tea and other foods5.0% [1.0–13.5%]6 studies
- Animal feed and pet food4.0% [0.7–11.5%]4 studies
- Food manufacturing (unspecified or mixed)6.5% [1.5–17.3%]13 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceThe filling machine stops unexpectedly due to a mechanical, electrical, pneumatic or control fault that degrades or interrupts its function, and the line cannot resume normal operation until maintenance personnel diagnose and repair the fault. The primary records only report the event as a generic breakdown without identifying the specific failed component or subsystem.
How it looks in SCADA data
Engineering guidanceSCADA/MES logs show the filler entering a fault or down state with a stop duration exceeding the minor-stop threshold, often with a generic or unspecific alarm code, no cycling of the filling heads, and starvation downstream while upstream buffers fill or block, until a maintenance work order closes the event.
Countermeasure
Engineering guidanceApply root-cause failure analysis supported by condition monitoring and detailed fault logging to identify the specific failing component, then implement targeted preventive or predictive maintenance, spare-parts readiness and operator fault-detection training to reduce repair time and recurrence.
4Sources
- Lost time: 124 h · as reported: “breakdown”
Show verbatim quote
Total number hours of breakdown per year(hours) 123.66 107.33 146.33 153.4 108.5
- Lost time: 107 h · as reported: “breakdown”
Show verbatim quote
Total number hours of breakdown per year(hours) 123.66 107.33 146.33 153.4 108.5
- Lost time: 146 h · as reported: “breakdown”
Show verbatim quote
Total number hours of breakdown per year(hours) 123.66 107.33 146.33 153.4 108.5
- Lost time: 153 h · as reported: “breakdown”
Show verbatim quote
Total number hours of breakdown per year(hours) 123.66 107.33 146.33 153.4 108.5
- Lost time: 109 h · as reported: “breakdown”
Show verbatim quote
Total number hours of breakdown per year(hours) 123.66 107.33 146.33 153.4 108.5
- Lost time: 120 h · as reported: “breakdown”
Show verbatim quote
Total number hours of breakdown per year(hours) 120 130 217.5 386 114.5
- Lost time: 130 h · as reported: “breakdown”
Show verbatim quote
Total number hours of breakdown per year(hours) 120 130 217.5 386 114.5
- Lost time: 218 h · as reported: “breakdown”
Show verbatim quote
Total number hours of breakdown per year(hours) 120 130 217.5 386 114.5
- Lost time: 386 h · as reported: “breakdown”
Show verbatim quote
Total number hours of breakdown per year(hours) 120 130 217.5 386 114.5
- Lost time: 115 h · as reported: “breakdown”
Show verbatim quote
Total number hours of breakdown per year(hours) 120 130 217.5 386 114.5
- PLANT MAINTENANCE STRATEGY FOR IMPROVED PRODUCTION IN THE FOOD AND BEVERAGE INDUSTRIES (2024)Open sourceLost time: 124 hours · as reported: “machine breakdown”
Show verbatim quote
Total number of hours of breakdown per year(hours) 123.66 107.33 146.33 153.4 108.5
- PLANT MAINTENANCE STRATEGY FOR IMPROVED PRODUCTION IN THE FOOD AND BEVERAGE INDUSTRIES (2024)Open sourceLost time: 107 hours · as reported: “machine breakdown”
Show verbatim quote
Total number of hours of breakdown per year(hours) 123.66 107.33 146.33 153.4 108.5
- PLANT MAINTENANCE STRATEGY FOR IMPROVED PRODUCTION IN THE FOOD AND BEVERAGE INDUSTRIES (2024)Open sourceLost time: 146 hours · as reported: “machine breakdown”
Show verbatim quote
Total number of hours of breakdown per year(hours) 123.66 107.33 146.33 153.4 108.5
- PLANT MAINTENANCE STRATEGY FOR IMPROVED PRODUCTION IN THE FOOD AND BEVERAGE INDUSTRIES (2024)Open sourceLost time: 153 hours · as reported: “machine breakdown”
Show verbatim quote
Total number of hours of breakdown per year(hours) 123.66 107.33 146.33 153.4 108.5
- PLANT MAINTENANCE STRATEGY FOR IMPROVED PRODUCTION IN THE FOOD AND BEVERAGE INDUSTRIES (2024)Open sourceLost time: 109 hours · as reported: “machine breakdown”
Show verbatim quote
Total number of hours of breakdown per year(hours) 123.66 107.33 146.33 153.4 108.5
- Efficiency Improvement of Glass Bottle Filler Machine Using Autonomous Maintenance-A Case Study (2025)Open sourceLost time: 20.0 min · as reported: “ABIBUS fault filler”
Show verbatim quote
ABIBUS fault filler 0 0 0 0 20 0 20 1.37
- Efficiency Improvement of Glass Bottle Filler Machine Using Autonomous Maintenance-A Case Study (2025)Open sourceShare of lost time: 1.37 % · as reported: “ABIBUS fault filler”
Show verbatim quote
ABIBUS fault filler 0 0 0 0 20 0 20 1.37
- Efficiency Improvement of Glass Bottle Filler Machine Using Autonomous Maintenance-A Case Study (2025)Open sourceLost time: 20.0 min · as reported: “ABIBUS fault filler”
Show verbatim quote
1 | ABIBUS fault filler | 0 | 0 | 0 | 0 | 20 | 0 | 20 | 1.37
- EFFECT OF EQUIPMENT MAINTENANCE ON THE PERFORMANCE EVALUATION OF FOOD AND BEVERAGE MANUFACTURING INDUSTRIES IN NIGERIA. (2023)Open sourceLost time: 386 h · as reported: “breakdown”
Show verbatim quote
Total number hours of breakdown per year(hours) 120 130 217.5 386 114.5
- EFFECT OF EQUIPMENT MAINTENANCE ON THE PERFORMANCE EVALUATION OF FOOD AND BEVERAGE MANUFACTURING INDUSTRIES IN NIGERIA. (2023)Open sourceLost time: 130 h · as reported: “breakdown”
Show verbatim quote
Total number hours of breakdown per year(hours) 120 130 217.5 386 114.5
- EFFECT OF EQUIPMENT MAINTENANCE ON THE PERFORMANCE EVALUATION OF FOOD AND BEVERAGE MANUFACTURING INDUSTRIES IN NIGERIA. (2023)Open sourceLost time: 120 h · as reported: “breakdown”
Show verbatim quote
Total number hours of breakdown per year(hours) 120 130 217.5 386 114.5
- EFFECT OF EQUIPMENT MAINTENANCE ON THE PERFORMANCE EVALUATION OF FOOD AND BEVERAGE MANUFACTURING INDUSTRIES IN NIGERIA. (2023)Open sourceLost time: 124 h · as reported: “breakdown”
Show verbatim quote
Total number hours of breakdown per year(hours) 123.66 107.33 146.33 153.4 108.5
- EFFECT OF EQUIPMENT MAINTENANCE ON THE PERFORMANCE EVALUATION OF FOOD AND BEVERAGE MANUFACTURING INDUSTRIES IN NIGERIA. (2023)Open sourceLost time: 115 h · as reported: “breakdown”
Show verbatim quote
Total number hours of breakdown per year(hours) 120 130 217.5 386 114.5
- EFFECT OF EQUIPMENT MAINTENANCE ON THE PERFORMANCE EVALUATION OF FOOD AND BEVERAGE MANUFACTURING INDUSTRIES IN NIGERIA. (2023)Open sourceLost time: 218 h · as reported: “breakdown”
Show verbatim quote
Total number hours of breakdown per year(hours) 120 130 217.5 386 114.5
- EFFECT OF EQUIPMENT MAINTENANCE ON THE PERFORMANCE EVALUATION OF FOOD AND BEVERAGE MANUFACTURING INDUSTRIES IN NIGERIA. (2023)Open sourceLost time: 109 h · as reported: “breakdown”
Show verbatim quote
Total number hours of breakdown per year(hours) 123.66 107.33 146.33 153.4 108.5
- EFFECT OF EQUIPMENT MAINTENANCE ON THE PERFORMANCE EVALUATION OF FOOD AND BEVERAGE MANUFACTURING INDUSTRIES IN NIGERIA. (2023)Open sourceLost time: 153 h · as reported: “breakdown”
Show verbatim quote
Total number hours of breakdown per year(hours) 123.66 107.33 146.33 153.4 108.5
- EFFECT OF EQUIPMENT MAINTENANCE ON THE PERFORMANCE EVALUATION OF FOOD AND BEVERAGE MANUFACTURING INDUSTRIES IN NIGERIA. (2023)Open sourceLost time: 146 h · as reported: “breakdown”
Show verbatim quote
Total number hours of breakdown per year(hours) 123.66 107.33 146.33 153.4 108.5
- EFFECT OF EQUIPMENT MAINTENANCE ON THE PERFORMANCE EVALUATION OF FOOD AND BEVERAGE MANUFACTURING INDUSTRIES IN NIGERIA. (2023)Open sourceLost time: 107 h · as reported: “breakdown”
Show verbatim quote
Total number hours of breakdown per year(hours) 123.66 107.33 146.33 153.4 108.5
- ANALISIS TOTAL PRODUCTIVE MAINTENANCE PADA LINE 8/CARBONATED SOFT DRINK PT COCA-COLA BOTTLING INDONESIA CENTRAL JAVA (2012)Open sourceLost time: 20.0 min · as reported: “case filler”
Show verbatim quote
case filler 2 20 109 3248 97.32 92.37
- ANALISIS TOTAL PRODUCTIVE MAINTENANCE PADA LINE 8/CARBONATED SOFT DRINK PT COCA-COLA BOTTLING INDONESIA CENTRAL JAVA (2012)Open sourceNumber of events: 2.00 events · as reported: “case filler”
Show verbatim quote
case filler 2 20 109 3248 97.32 92.37
- Proposal for OEE (Overall Equipment Effectiveness) Indicator Deployment in a Beverage Plant (2012)Open sourceNumber of events: 44.0 events · as reported: “Problem in the filler (code 6003)”
Show verbatim quote
The code 6003, referring to downtimes caused by problems with the filler, consumed 473 minutes, having occurred 44 times during the period assessed in this work (Figure 3).
- Proposal for OEE (Overall Equipment Effectiveness) Indicator Deployment in a Beverage Plant (2012)Open sourceLost time: 473 min · as reported: “Problem in the filler (code 6003)”
Show verbatim quote
The code 6003, referring to downtimes caused by problems with the filler, consumed 473 minutes, having occurred 44 times during the period assessed in this work (Figure 3).
- Penerapan Metode Total Productive Maintenance untuk Mereduksi Downtime pada Lini Produksi Botol 1 di PT. Grahamas Intitirta (2020)Open sourceLost time: 67.6 h · as reported: “breakdown loss”
Show verbatim quote
This can reduce Filling 1 downtime from 393.78 hours to 67.62 hours and Blowing 1 from 91.35 hours to 14.75 hours.
- Application of the Concept of Total Productive Maintenance in Automatic Bottle Filling Machines (2019)Open sourceTime between events: 38,693 not reported · as reported: “Filling Roller”
Show verbatim quote
Waktu Kerusakan Weibull MTTF 38693,38
- Application of the Concept of Total Productive Maintenance in Automatic Bottle Filling Machines (2019)Open sourceTime between events: 22,079 not reported · as reported: “Pegas Tiang Filler”
Show verbatim quote
Waktu Kerusakan Weibull MTTF 22078,51
- Application of the Concept of Total Productive Maintenance in Automatic Bottle Filling Machines (2019)Open sourceShare of lost time: 69.1 % · as reported: “Breakdown Losses”
Show verbatim quote
Breakdown Losses 22.049,83 69,12 1
- Application of the Concept of Total Productive Maintenance in Automatic Bottle Filling Machines (2019)Open sourceLost time: 22,050 min · as reported: “Breakdown Losses”
Show verbatim quote
Breakdown Losses 22.049,83 69,12 1
- Application of the Concept of Total Productive Maintenance in Automatic Bottle Filling Machines (2019)Open sourceMean event duration: 197 not reported · as reported: “Pegas Tiang Filler”
Show verbatim quote
Waktu Perbaikan Weibull MTTR 197
- Application of the Concept of Total Productive Maintenance in Automatic Bottle Filling Machines (2019)Open sourceMean event duration: 211 not reported · as reported: “Filling Roller”
Show verbatim quote
Waktu Perbaikan Weibull MTTR 211
- Lost time: 60.0 min · as reported: “Lunch”
Show verbatim quote
Lunch (L) 1 times per 60 min. – 60 min.
- Lost time: 5.20 h · as reported: “Prepared”
Show verbatim quote
Prepared 4.6 12.4 5.2 8.1 3.5 3.3
- Specific energy: 8.10 Wh/1000 Bottles · as reported: “Prepared”
Show verbatim quote
Prepared 4.6 12.4 5.2 8.1 3.5 3.3
- Lost time: 0 h · as reported: “Lack”
Show verbatim quote
Lack 0.1 1.3 0.0 0.0 4.6 4.4
- Specific energy: 0 Wh/1000 Bottles · as reported: “Lack”
Show verbatim quote
Lack 0.1 1.3 0.0 0.0 4.6 4.4
- Lost time: 7.80 h · as reported: “Tailback”
Show verbatim quote
Tailback 6.8 145.8 7.8 9.9 4.8 4.6
- Specific energy: 9.90 Wh/1000 Bottles · as reported: “Tailback”
Show verbatim quote
Tailback 6.8 145.8 7.8 9.9 4.8 4.6
- Lost time: 4.90 h · as reported: “Equipment failure”
Show verbatim quote
Equipment failure 8.1 195.6 4.9 6.5 2.5 2.2
- Specific energy: 6.50 Wh/1000 Bottles · as reported: “Equipment failure”
Show verbatim quote
Equipment failure 8.1 195.6 4.9 6.5 2.5 2.2
- Lost time: 33.0 h · as reported: “Held”
Show verbatim quote
Held 29.2 48.7 33 37.4 31.7 25.2
- Specific energy: 37.4 Wh/1000 Bottles · as reported: “Held”
Show verbatim quote
Held 29.2 48.7 33 37.4 31.7 25.2
- Peningkatan Efektivitas Mesin Susu Kental Manis dengan Metode Overall Equipment Effectiveness dan Diagram Ishikawa (2021)Open sourceLost time: 97.2 jam · as reported: “Failure”
Show verbatim quote
Failure = 97.2 Jam Setup & adjustment = 6.6 jam Downtime = 103.8 jam
- Set Up Time Reduction Using Single Minute Exchange of Dies (SMED) and 5S: A Case Study (2021)Open sourceShare of lost time: 3.00 % · as reported: “meals or break”
Show verbatim quote
The next is 34% of cleaning inspection and lubrication process, 19% of operational stoppages, 3% of meals or break, 2% of change over time, and the last 1% of planned maintenance.
- Performance Analysis of Filling Machine Using Overall Equipment Effectiveness Metric in Beverage Company (2023)Open sourceLost time: 3,835 min · as reported: “Equipment Failure”
Show verbatim quote
the Equipment Failure factor (52.7%), or equivalent,t to 3,835 minutes
- Performance Analysis of Filling Machine Using Overall Equipment Effectiveness Metric in Beverage Company (2023)Open sourceShare of lost time: 52.7 % · as reported: “Equipment Failure”
Show verbatim quote
the Equipment Failure factor (52.7%), or equivalent,t to 3,835 minutes
- Analisis Overall Equipment Effectiveness untuk Meningkatkan Efektivitas Mesin Filling Multiline pada PT-XYZ (2023)Open sourceLost time: 12.1 jam · as reported: “Equipment Failure Losses”
Show verbatim quote
Equipment Failure Losses 12,13 39,23 77,67%
- Lost time: 0 mnt · as reported: “Breakdown”
Show verbatim quote
1 Breakdow n 0 0 0
- Lost time: 0 mnt · as reported: “Breakdown”
Show verbatim quote
1 Breakdow n 0 0 0
- Lost time: 0 mnt · as reported: “Breakdown”
Show verbatim quote
1 Breakdow n 0 0 0
- Lost time: 0 mnt · as reported: “Breakdown”
Show verbatim quote
Breakdown 0 mnt 0 mnt
- Lost time: 0 mnt · as reported: “Breakdown”
Show verbatim quote
Breakdown 0 mnt 0 mnt
- Lean and RCM-Based Production Model to Improve Operational Efficiency in the Production Line of a Peruvian Dairy SME (2025)Open sourceShare of lost time: 55.8 % · as reported: “filling machine break down often”
Show verbatim quote
The first reason had a lot of problems that caused the filling machine to break down often (55.8% of the problems) and setup time delays (44.2% of the inefficiencies).
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceTime between events: 5.03 h · as reported: “averías de la máquina de envasado”
Show verbatim quote
el MTBF es de 5.03 horas y el MTTR es de 1.69 horas, afectando estas la disponibilidad del equipo
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceMean event duration: 1.69 h · as reported: “averías de la máquina de envasado”
Show verbatim quote
el MTBF es de 5.03 horas y el MTTR es de 1.69 horas, afectando estas la disponibilidad del equipo
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceShare of lost time: 41.1 % · as reported: “averías/reparaciones”
Show verbatim quote
los motivos son las averías / reparaciones, reprocesos, cambios de formato y otros donde estas representan el 41.1%, 35.7% y 23.3% respectivamente
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceShare of lost time: 35.7 % · as reported: “reprocesos”
Show verbatim quote
los motivos son las averías / reparaciones, reprocesos, cambios de formato y otros donde estas representan el 41.1%, 35.7% y 23.3% respectivamente
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceShare of planned time: 7.38 % · as reported: “Averías/Paros”
Show verbatim quote
Preparación de línea Averías / Paros Reprocesos en envasado 1,15% 7,38% 6,35%
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceShare of planned time: 4.62 % · as reported: “Regulaciones”
Show verbatim quote
Regulaciones 4,62%
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceShare of planned time: 1.90 % · as reported: “Limpieza”
Show verbatim quote
Limpieza 1,90%
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceShare of planned time: 5.10 % · as reported: “Tiempos de inactividad”
Show verbatim quote
Tiempos de inactividad 5,10%
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceShare of planned time: 3.70 % · as reported: “Alimentación”
Show verbatim quote
Alimentación 3,70%
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceTime between events: 13.3 hr · as reported: “averías de la máquina de envasado”
Show verbatim quote
MTBF 5,03 hr 13.32 hr 15,00 hr
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceTime between events: 3.33 min · as reported: “averías de la máquina de envasado”
Show verbatim quote
MTBF 12,67 14,62 12,67 3.33
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceMean event duration: 0.200 min · as reported: “averías de la máquina de envasado”
Show verbatim quote
MTTR 0,80 0,77 0,80 0,20
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceShare of planned time: 1.00 % · as reported: “Averías/Paros”
Show verbatim quote
Preparación de línea Averías / Paros ELIMINADO 1,15% 1,00%
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceShare of planned time: 1.30 % · as reported: “Regulaciones”
Show verbatim quote
Regulaciones 1,30% REDUCIDO
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceShare of planned time: 1.90 % · as reported: “Limpieza”
Show verbatim quote
Limpieza 1,90%
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceShare of planned time: 1.50 % · as reported: “Tiempos de inactividad”
Show verbatim quote
Tiempos de inactividad 1,50% REDUCIDO
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceShare of planned time: 3.70 % · as reported: “Alimentación”
Show verbatim quote
Alimentación 3,70%
- Analysis of Filling Machine Effectiveness Using the Overall Equipment Effectiveness and Six Big Losses Method (2025)Open sourceShare of planned time: 9.39 % · as reported: “machine damage”
Show verbatim quote
losses due to machine damage with a losses value of 9.389%
- Lost time: 160 min · as reported: “Filler”
Show verbatim quote
Planned losses (min) | 0 | 160 | 0 | 0 | 0 | 160 | 7
- Lost time: 494 min · as reported: “Filler”
Show verbatim quote
Operational losses (min) | 278 | 494 | 106 | 53 | 157 | 1088 | 48
- Lost time: 364 min · as reported: “Filler”
Show verbatim quote
Equipment losses (min) | 420 | 364 | 24 | 55 | 152 | 1015 | 44.8