Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study

Open source

1Bibliographic record

Authors
Christopher Chukwutoo Ihueze, Chukwuebuka Martinjoe U-Dominic
Year
2018
Venue
Archives of Current Research International
Country
Nigeria
Segment
Bakery and pasta
Process family
Filling and packaging line
Study type
Before/after intervention
Extraction scope
Full text
Size
1 plants · 1 lines · 1 machines
Observation period
270 days
Data collection
questionnaire
Intervention
Show the setting as described by the study
The research was carried out in the food manufacturing company, major production of noodles, and the study was limited to bottleneck operation and the identified bottleneck machine in this study was the noodle packaging machine.

2Risk of bias

Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 13Low risk
ItemScore
Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product or sector is given but the equipment or process is only partly described.1 / 2
Is the observation period long enough and reported?Period reported and at least 30 days of production (or at least 100 recorded events).2 / 2
How were loss data collected?Manual logs or maintenance records with unknown completeness.1 / 2
Are OEE, loading time and the loss categories defined explicitly?Formulae or definitions are given for the reported metrics, including what counts as planned time.2 / 2
Does the loss breakdown account for the total loss it claims to explain?The reported causes or categories sum to at least 90% of the stated total, or an explicit "other" class closes the balance.2 / 2
Is there evidence of selective reporting of favourable results?Observational study, or intervention study that reports baseline and post-intervention data with the same method.2 / 2
Are the reported numbers internally consistent?Small inconsistencies (2 to 10 percentage points) or values that cannot be cross-checked.1 / 2
Could conflicts of interest or the source of the data bias the result?Academic or independent study, or conflicts declared and unrelated to the result.2 / 2

3Extracted data

Each datum with its classification and the verbatim quote that states it.
Reported causeLoss categoryMetricValueExtraction
—noodle packaging machine
Show verbatim quote (Results and Analysis)
the Overall equipment effectiveness value increased by 26%, from 48% to 74%.
noneOEE74.0 %Both extractors agreed
—noodle packaging machine
Show verbatim quote (Results and Analysis)
After TPM implementation, the availability factor was raised by 19%; from 70% to 89%, the performance factor experienced a 14% increase, from initial value of 70% to 84%.
nonePerformance84.0 %Both extractors agreed
—noodle packaging machine
Show verbatim quote (Results and Analysis)
After TPM implementation, the availability factor was raised by 19%; from 70% to 89%, the performance factor experienced a 14% increase, from initial value of 70% to 84%.
noneAvailability89.0 %Both extractors agreed
—noodle packaging machine
Show verbatim quote (Results and Analysis, Fig. 2 description)
the OEE rates before TPM implementation are 70% for availability factor, 70% for performance factor, 99% for quality factor and 48% for the OEE value.
noneOEE48.0 %Both extractors agreed
—noodle packaging machine
Show verbatim quote (Results and Analysis, Fig. 2 description)
the OEE rates before TPM implementation are 70% for availability factor, 70% for performance factor, 99% for quality factor and 48% for the OEE value.
nonePerformance70.0 %Both extractors agreed
—noodle packaging machine
Show verbatim quote (Results and Analysis, Fig. 2 description)
the OEE rates before TPM implementation are 70% for availability factor, 70% for performance factor, 99% for quality factor and 48% for the OEE value.
noneAvailability70.0 %Both extractors agreed
Operating Standard not followednoodle packaging machine
Show verbatim quote (Table 5)
4 Operating Standard not followed 13 119 25.00 100 25.54 100
Equipment failure (breakdowns)Lost time119 Hr.Both extractors agreed
Operating Standard not followednoodle packaging machine
Show verbatim quote (Table 5)
4 Operating Standard not followed 13 119 25.00 100 25.54 100
Equipment failure (breakdowns)Number of events13.0 eventsBoth extractors agreed
Operating Standard not followednoodle packaging machine
Show verbatim quote (Table 4)
4 Operating Standard not followed 22 44 22.92 100 5.30 100
Equipment failure (breakdowns)Lost time44.0 Hr.Both extractors agreed
Operating Standard not followednoodle packaging machine
Show verbatim quote (Table 4)
4 Operating Standard not followed 22 44 22.92 100 5.30 100
Equipment failure (breakdowns)Number of events22.0 eventsBoth extractors agreed
Operating Standard not followednoodle packaging machine
Show verbatim quote (Table 5)
4 Operating Standard not followed 13 119 25.00 100 25.54 100
Equipment failure (breakdowns)Share of loss events25.0 %Both extractors agreed
Operating Standard not followednoodle packaging machine
Show verbatim quote (Table 4)
4 Operating Standard not followed 22 44 22.92 100 5.30 100
Equipment failure (breakdowns)Share of loss events22.9 %Both extractors agreed
Basic condition neglectnoodle packaging machine
Show verbatim quote (Table 5)
2 Basic condition neglect 13 111 25.00 44.20 23.82 42.91
Equipment failure (breakdowns)Lost time111 Hr.Both extractors agreed
Basic condition neglectnoodle packaging machine
Show verbatim quote (Table 5)
2 Basic condition neglect 13 111 25.00 44.20 23.82 42.91
Equipment failure (breakdowns)Number of events13.0 eventsBoth extractors agreed
Basic condition neglectnoodle packaging machine
Show verbatim quote (Table 4)
2 Basic condition neglect 30 313 31.25 61.46 37.53 70.98
Equipment failure (breakdowns)Lost time313 Hr.Both extractors agreed
Basic condition neglectnoodle packaging machine
Show verbatim quote (Table 4)
2 Basic condition neglect 30 313 31.25 61.46 37.53 70.98
Equipment failure (breakdowns)Number of events30.0 eventsBoth extractors agreed
Unchecked deteriorationnoodle packaging machine
Show verbatim quote (Table 4)
1 Unchecked deterioration 29 279 30.21 30.21 33.45 33.45
Equipment failure (breakdowns)Lost time279 Hr.Both extractors agreed
Unchecked deteriorationnoodle packaging machine
Show verbatim quote (Table 4)
1 Unchecked deterioration 29 279 30.21 30.21 33.45 33.45
Equipment failure (breakdowns)Number of events29.0 eventsBoth extractors agreed
Inadequate skill levelnoodle packaging machine
Show verbatim quote (Table 5)
3 Inadequate skill level 16 147 30.80 75.00 31.55 74.46
Equipment failure (breakdowns)Lost time147 Hr.Both extractors agreed
Inadequate skill levelnoodle packaging machine
Show verbatim quote (Table 5)
3 Inadequate skill level 16 147 30.80 75.00 31.55 74.46
Equipment failure (breakdowns)Number of events16.0 eventsBoth extractors agreed
Unchecked deteriorationnoodle packaging machine
Show verbatim quote (Table 5)
1 Unchecked deterioration 10 89 19.20 19.20 19.09 19.09
Equipment failure (breakdowns)Lost time89.0 Hr.Both extractors agreed
Unchecked deteriorationnoodle packaging machine
Show verbatim quote (Table 5)
1 Unchecked deterioration 10 89 19.20 19.20 19.09 19.09
Equipment failure (breakdowns)Number of events10.0 eventsBoth extractors agreed
Inadequate skill levelnoodle packaging machine
Show verbatim quote (Table 4)
3 Inadequate skill level 15 198 15.63 77.09 23.74 94.70
Equipment failure (breakdowns)Lost time198 Hr.Both extractors agreed
Inadequate skill levelnoodle packaging machine
Show verbatim quote (Table 4)
3 Inadequate skill level 15 198 15.63 77.09 23.74 94.70
Equipment failure (breakdowns)Number of events15.0 eventsBoth extractors agreed
Basic condition neglectnoodle packaging machine
Show verbatim quote (Table 5)
2 Basic condition neglect 13 111 25.00 44.20 23.82 42.91
Equipment failure (breakdowns)Share of loss events25.0 %Both extractors agreed
Basic condition neglectnoodle packaging machine
Show verbatim quote (Table 4)
2 Basic condition neglect 30 313 31.25 61.46 37.53 70.98
Equipment failure (breakdowns)Share of loss events31.3 %Both extractors agreed
Unchecked deteriorationnoodle packaging machine
Show verbatim quote (Table 4)
1 Unchecked deterioration 29 279 30.21 30.21 33.45 33.45
Equipment failure (breakdowns)Share of loss events30.2 %Both extractors agreed
Inadequate skill levelnoodle packaging machine
Show verbatim quote (Table 5)
3 Inadequate skill level 16 147 30.80 75.00 31.55 74.46
Equipment failure (breakdowns)Share of loss events30.8 %Both extractors agreed
Unchecked deteriorationnoodle packaging machine
Show verbatim quote (Table 5)
1 Unchecked deterioration 10 89 19.20 19.20 19.09 19.09
Equipment failure (breakdowns)Share of loss events19.2 %Both extractors agreed
Inadequate skill levelnoodle packaging machine
Show verbatim quote (Table 4)
3 Inadequate skill level 15 198 15.63 77.09 23.74 94.70
Equipment failure (breakdowns)Share of loss events15.6 %Both extractors agreed
—noodle packaging machine
Show verbatim quote (Table 3)
After TPM 3,735 52 446 71.83
Equipment failure (breakdowns)Time between events71.8 Hr.Both extractors agreed
—noodle packaging machine
Show verbatim quote (Table 3)
Before TPM 3,735 96 834 38.91
Equipment failure (breakdowns)Time between events38.9 Hr.Both extractors agreed
—noodle packaging machine
Show verbatim quote (Table 3)
After TPM 3,735 52 446 71.83
Equipment failure (breakdowns)Lost time446 Hr.Both extractors agreed
—noodle packaging machine
Show verbatim quote (Table 3)
Before TPM 3,735 96 834 38.91
Equipment failure (breakdowns)Lost time834 Hr.Both extractors agreed
—noodle packaging machine
Show verbatim quote (Table 1)
Mar. 66.8 99.0 69.8 46.2
noneQuality99.0 %Both extractors agreed
—noodle packaging machine
Show verbatim quote (Table 1)
Oct. 69.4 96.5 74.9 50.2
noneQuality96.5 %Single extractor
—noodle packaging machine
Show verbatim quote (Table 1)
Nov. 70.6 97.6 66.9 46.1
noneQuality97.6 %Single extractor
—noodle packaging machine
Show verbatim quote (Table 1)
Dec. 71.1 99.2 70.4 49.7
noneQuality99.2 %Single extractor
—noodle packaging machine
Show verbatim quote (Table 1)
Jan. 69.2 98.9 76.3 52.2
noneQuality98.9 %Single extractor
—noodle packaging machine
Show verbatim quote (Table 1)
Feb. 72.4 99.5 63.9 46.0
noneQuality99.5 %Single extractor
—noodle packaging machine
Show verbatim quote (Table 3)
Before TPM 3,735 96 834 38.91
Equipment failure (breakdowns)Number of events96.0 eventsSingle extractor
Unchecked deteriorationnoodle packaging machine
Show verbatim quote (Table 4)
1 Unchecked deterioration 29 279 30.21 30.21 33.45 33.45
Equipment failure (breakdowns)Share of lost time33.5 %Single extractor
Basic condition neglectnoodle packaging machine
Show verbatim quote (Table 4)
2 Basic condition neglect 30 313 31.25 61.46 37.53 70.98
Equipment failure (breakdowns)Share of lost time37.5 %Single extractor
Inadequate skill levelnoodle packaging machine
Show verbatim quote (Table 4)
3 Inadequate skill level 15 198 15.63 77.09 23.74 94.70
Equipment failure (breakdowns)Share of lost time23.7 %Single extractor
Operating Standard not followednoodle packaging machine
Show verbatim quote (Table 4)
4 Operating Standard not followed 22 44 22.92 100 5.30 100
Equipment failure (breakdowns)Share of lost time5.30 %Single extractor
—noodle packaging machine
Show verbatim quote (Table 2)
Jun. 83.1 99.7 81.3 67.4
noneQuality99.7 %Single extractor
—noodle packaging machine
Show verbatim quote (Table 2)
Jul. 85.3 99.5 92.7 78.7
noneQuality99.5 %Single extractor
—noodle packaging machine
Show verbatim quote (Table 2)
Aug. 84.6 99.6 96.3 81.1
noneQuality99.6 %Single extractor
—noodle packaging machine
Show verbatim quote (Table 2)
Sept. 86.0 99.8 83.5 71.7
noneQuality99.8 %Single extractor
—noodle packaging machine
Show verbatim quote (Table 2)
Nov. 83.9 99.9 90.8 76.1
noneQuality99.9 %Single extractor
—noodle packaging machine
Show verbatim quote (Table 3)
After TPM 3,735 52 446 71.83
Equipment failure (breakdowns)Number of events52.0 eventsSingle extractor
Unchecked deteriorationnoodle packaging machine
Show verbatim quote (Table 5)
1 Unchecked deterioration 10 89 19.20 19.20 19.09 19.09
Equipment failure (breakdowns)Share of lost time19.1 %Single extractor
Basic condition neglectnoodle packaging machine
Show verbatim quote (Table 5)
2 Basic condition neglect 13 111 25.00 44.20 23.82 42.91
Equipment failure (breakdowns)Share of lost time23.8 %Single extractor
Inadequate skill levelnoodle packaging machine
Show verbatim quote (Table 5)
3 Inadequate skill level 16 147 30.80 75.00 31.55 74.46
Equipment failure (breakdowns)Share of lost time31.6 %Single extractor
Operating Standard not followednoodle packaging machine
Show verbatim quote (Table 5)
4 Operating Standard not followed 13 119 25.00 100 25.54 100
Equipment failure (breakdowns)Share of lost time25.5 %Single extractor

Observation units

  • Noodle packaging machine · Packaging (forming, sealing, wrapping, case packing, palletizing) · After intervention
  • Noodle packaging machine · Packaging (forming, sealing, wrapping, case packing, palletizing) · Baseline