Basic Condition and Operating Standard Non-Compliance
In short
It appears in about 1 of every 100 lines studied.
When it appears, it takes on average about 58 % of the line's lost time. Reported by 3 of the 112 studies that could observe it (limited evidence).
What happens
The packaging machine breaks down because fundamental equipment-care practices are not sustained: cleaning, lubrication and fastening are neglected, operators lack the skill to run and adjust the machine correctly, documented operating standards are not followed, and early signs of wear or misalignment go unnoticed until they cause a stoppage. Over time this unmanaged deterioration lowers the machine condition below the point where it can run reliably, producing breakdowns, bag jams, setup difficulties and calibration drift as secondary symptoms.
What is done about it
Implement autonomous and planned maintenance: restore and sustain basic conditions through cleaning, lubrication and inspection checklists, visually mark correct settings and fastener points, and train operators to a documented operating standard with periodic skill verification. Introduce condition monitoring and daily operator checks to detect deterioration early, and audit standard-operating-procedure adherence to prevent drift back to poor practice.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 1.1% [0.3–2.7%]
- Expected share of lost time
- 0.6% [0.2–1.6%]
- Share of lost time when present
- 58% [48–68%]
- Studies / units
- 112 / 155
- Evidence grade
- C
Grade C: 2 to 4 studies, or an interval wider than 0.35.
2Probability by segment
- Dairy products1.1% [0.2–3.6%]14 studies
- Soft drinks, bottled water and juices1.2% [0.2–3.5%]33 studies
- Brewing, wine and spirits1.1% [0.2–3.9%]14 studies
- Bakery and pasta1.8% [0.3–6.2%]6 studies
- Meat, poultry and seafood1.2% [0.2–4.1%]6 studies
- Fruit and vegetable processing1.3% [0.2–4.3%]4 studies
- Grain and oilseed milling1.3% [0.2–4.5%]4 studies
- Sugar and confectionery1.3% [0.2–4.6%]4 studies
- Snacks, coffee, tea and other foods1.2% [0.2–4.0%]8 studies
- Animal feed and pet food1.8% [0.3–6.1%]5 studies
- Food manufacturing (unspecified or mixed)1.1% [0.2–3.6%]14 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceThe packaging machine breaks down because fundamental equipment-care practices are not sustained: cleaning, lubrication and fastening are neglected, operators lack the skill to run and adjust the machine correctly, documented operating standards are not followed, and early signs of wear or misalignment go unnoticed until they cause a stoppage. Over time this unmanaged deterioration lowers the machine condition below the point where it can run reliably, producing breakdowns, bag jams, setup difficulties and calibration drift as secondary symptoms.
How it looks in SCADA data
Engineering guidanceSCADA/MES shows recurrent unplanned stop events on the packaging machine attributed to varying, non-specific fault codes rather than a single repeatable component signature, interspersed with short minor stops (jams, fallen bags) and occasional setup or calibration-related state changes. Downtime reason logs entered by operators frequently reference skill, standard-compliance or condition-check categories rather than a discrete mechanical or electrical fault, and mean time between failures tends to drift downward without a clear single root cause in the historian.
Countermeasure
Engineering guidanceImplement autonomous and planned maintenance: restore and sustain basic conditions through cleaning, lubrication and inspection checklists, visually mark correct settings and fastener points, and train operators to a documented operating standard with periodic skill verification. Introduce condition monitoring and daily operator checks to detect deterioration early, and audit standard-operating-procedure adherence to prevent drift back to poor practice.
4Sources
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceLost time: 119 Hr. · as reported: “Operating Standard not followed”
Show verbatim quote
4 Operating Standard not followed 13 119 25.00 100 25.54 100
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceNumber of events: 13.0 events · as reported: “Operating Standard not followed”
Show verbatim quote
4 Operating Standard not followed 13 119 25.00 100 25.54 100
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceLost time: 44.0 Hr. · as reported: “Operating Standard not followed”
Show verbatim quote
4 Operating Standard not followed 22 44 22.92 100 5.30 100
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceNumber of events: 22.0 events · as reported: “Operating Standard not followed”
Show verbatim quote
4 Operating Standard not followed 22 44 22.92 100 5.30 100
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceShare of loss events: 25.0 % · as reported: “Operating Standard not followed”
Show verbatim quote
4 Operating Standard not followed 13 119 25.00 100 25.54 100
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceShare of loss events: 22.9 % · as reported: “Operating Standard not followed”
Show verbatim quote
4 Operating Standard not followed 22 44 22.92 100 5.30 100
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceLost time: 111 Hr. · as reported: “Basic condition neglect”
Show verbatim quote
2 Basic condition neglect 13 111 25.00 44.20 23.82 42.91
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceNumber of events: 13.0 events · as reported: “Basic condition neglect”
Show verbatim quote
2 Basic condition neglect 13 111 25.00 44.20 23.82 42.91
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceLost time: 313 Hr. · as reported: “Basic condition neglect”
Show verbatim quote
2 Basic condition neglect 30 313 31.25 61.46 37.53 70.98
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceNumber of events: 30.0 events · as reported: “Basic condition neglect”
Show verbatim quote
2 Basic condition neglect 30 313 31.25 61.46 37.53 70.98
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceLost time: 279 Hr. · as reported: “Unchecked deterioration”
Show verbatim quote
1 Unchecked deterioration 29 279 30.21 30.21 33.45 33.45
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceNumber of events: 29.0 events · as reported: “Unchecked deterioration”
Show verbatim quote
1 Unchecked deterioration 29 279 30.21 30.21 33.45 33.45
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceLost time: 147 Hr. · as reported: “Inadequate skill level”
Show verbatim quote
3 Inadequate skill level 16 147 30.80 75.00 31.55 74.46
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceNumber of events: 16.0 events · as reported: “Inadequate skill level”
Show verbatim quote
3 Inadequate skill level 16 147 30.80 75.00 31.55 74.46
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceLost time: 89.0 Hr. · as reported: “Unchecked deterioration”
Show verbatim quote
1 Unchecked deterioration 10 89 19.20 19.20 19.09 19.09
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceNumber of events: 10.0 events · as reported: “Unchecked deterioration”
Show verbatim quote
1 Unchecked deterioration 10 89 19.20 19.20 19.09 19.09
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceLost time: 198 Hr. · as reported: “Inadequate skill level”
Show verbatim quote
3 Inadequate skill level 15 198 15.63 77.09 23.74 94.70
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceNumber of events: 15.0 events · as reported: “Inadequate skill level”
Show verbatim quote
3 Inadequate skill level 15 198 15.63 77.09 23.74 94.70
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceShare of loss events: 25.0 % · as reported: “Basic condition neglect”
Show verbatim quote
2 Basic condition neglect 13 111 25.00 44.20 23.82 42.91
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceShare of loss events: 31.3 % · as reported: “Basic condition neglect”
Show verbatim quote
2 Basic condition neglect 30 313 31.25 61.46 37.53 70.98
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceShare of loss events: 30.2 % · as reported: “Unchecked deterioration”
Show verbatim quote
1 Unchecked deterioration 29 279 30.21 30.21 33.45 33.45
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceShare of loss events: 30.8 % · as reported: “Inadequate skill level”
Show verbatim quote
3 Inadequate skill level 16 147 30.80 75.00 31.55 74.46
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceShare of loss events: 19.2 % · as reported: “Unchecked deterioration”
Show verbatim quote
1 Unchecked deterioration 10 89 19.20 19.20 19.09 19.09
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceShare of loss events: 15.6 % · as reported: “Inadequate skill level”
Show verbatim quote
3 Inadequate skill level 15 198 15.63 77.09 23.74 94.70
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceShare of lost time: 33.5 % · as reported: “Unchecked deterioration”
Show verbatim quote
1 Unchecked deterioration 29 279 30.21 30.21 33.45 33.45
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceShare of lost time: 37.5 % · as reported: “Basic condition neglect”
Show verbatim quote
2 Basic condition neglect 30 313 31.25 61.46 37.53 70.98
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceShare of lost time: 23.7 % · as reported: “Inadequate skill level”
Show verbatim quote
3 Inadequate skill level 15 198 15.63 77.09 23.74 94.70
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceShare of lost time: 5.30 % · as reported: “Operating Standard not followed”
Show verbatim quote
4 Operating Standard not followed 22 44 22.92 100 5.30 100
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceShare of lost time: 19.1 % · as reported: “Unchecked deterioration”
Show verbatim quote
1 Unchecked deterioration 10 89 19.20 19.20 19.09 19.09
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceShare of lost time: 23.8 % · as reported: “Basic condition neglect”
Show verbatim quote
2 Basic condition neglect 13 111 25.00 44.20 23.82 42.91
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceShare of lost time: 31.6 % · as reported: “Inadequate skill level”
Show verbatim quote
3 Inadequate skill level 16 147 30.80 75.00 31.55 74.46
- Maximizing Overall Equipment Effectiveness in a Food Processing Industry: A Case Study (2018)Open sourceShare of lost time: 25.5 % · as reported: “Operating Standard not followed”
Show verbatim quote
4 Operating Standard not followed 13 119 25.00 100 25.54 100
- Mean event duration: 97.0 min · as reported: “Setup time”
Show verbatim quote
Blowing machine Filling machine Labelling machine (bottleneck resource) Packaging machine 85 minutes 69 minutes 148 minutes 97 minutes 57 minutes 73 minutes 0 minutes 51 minutes
- Mean event duration: 51.0 min · as reported: “Idle time”
Show verbatim quote
Blowing machine Filling machine Labelling machine (bottleneck resource) Packaging machine 85 minutes 69 minutes 148 minutes 97 minutes 57 minutes 73 minutes 0 minutes 51 minutes
- The Application of Lean Manufacturing for the Standardization of the Canned Chicken Production Process in Peru Food Companies (2024)Open sourceLost time: 40.0 min · as reported: “Packaging machine decalibration”
Show verbatim quote
Corrective maintenance time 33 min - 102 min - 40 min 20 min
- Improving Overall Equipment Effectiveness in the Packaging Process of Finished Cattle Feed: A Case Study of an Animal Feed Production Facility (2025)Open sourceLost time: 40.0 h · as reported: “Bags falling in machinery”
Show verbatim quote
bags stuck on conveyor Before packaging. Bags falling in machinery. Pallet flow issues. lmoroper bag attachment. Frequent stitching adjiustments. Hour 180 40 23 16 11 Cum % 67% 82% 90% 96% 100% 180 40 23 16 11