APLIKASI OVERALL EQUIPMENT EFFECTIVENESS (OEE) DALAM UPAYA MENGATASI TINGGINYA DOWNTIME PADA STASIUN KETEL DI PG X JAWA TIMUR

Open source

1Bibliographic record

Authors
Mahros Darsin
Year
2020
Venue
MULTITEK INDONESIA
Country
Indonesia
Segment
Sugar and confectionery
Process family
Slaughter, cutting and primary processing
Study type
Single case study
Extraction scope
Full text
Size
1 plants · 1 lines · 1 machines
Observation period
180 days
Data collection
maintenance_records
Intervention
Show the setting as described by the study
PG X in Jember is one of the agro-industries that processing sugar cane into sugar crystals.

2Risk of bias

Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 15Low risk
ItemScore
Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product, process and equipment are all described.2 / 2
Is the observation period long enough and reported?Period reported and at least 30 days of production (or at least 100 recorded events).2 / 2
How were loss data collected?Manual logs or maintenance records with unknown completeness.1 / 2
Are OEE, loading time and the loss categories defined explicitly?Formulae or definitions are given for the reported metrics, including what counts as planned time.2 / 2
Does the loss breakdown account for the total loss it claims to explain?The reported causes or categories sum to at least 90% of the stated total, or an explicit "other" class closes the balance.2 / 2
Is there evidence of selective reporting of favourable results?Observational study, or intervention study that reports baseline and post-intervention data with the same method.2 / 2
Are the reported numbers internally consistent?Recomputed totals, shares and OEE factors agree with the reported values within 2 percentage points.2 / 2
Could conflicts of interest or the source of the data bias the result?Academic or independent study, or conflicts declared and unrelated to the result.2 / 2

3Extracted data

Each datum with its classification and the verbatim quote that states it.
Reported causeLoss categoryMetricValueExtraction
Breakdown lossesbagasse conveyor chain
Show verbatim quote (Tabel 4)
Breakdown losses 0.0192 12.5% 94%
Equipment failure (breakdowns)Share of lost time12.5 %Both extractors agreed
Reduce speed lossesbagasse conveyor chain
Show verbatim quote (Tabel 4)
Reduce speed losses 0.0711 46.2% 46.2%
Reduced speedShare of lost time46.2 %Both extractors agreed
Idle and minorbagasse conveyor chain
Show verbatim quote (Tabel 4)
Idle and minor 0.01 6.5% 100%
Idling and minor stops (micro-stops)Share of lost time6.50 %Both extractors agreed
—bagasse conveyor chain
Show verbatim quote (Tabel 2)
Mei 93.12% 99.45% 100% 91.93%
nonePerformance99.5 %Both extractors agreed
—bagasse conveyor chain
Show verbatim quote (Tabel 2)
Mei 93.12% 99.45% 100% 91.93%
noneAvailability93.1 %Both extractors agreed
—bagasse conveyor chain
Show verbatim quote (Tabel 2)
September 98.53% 99.97% 100% 98.46%
nonePerformance100.0 %Both extractors agreed
—bagasse conveyor chain
Show verbatim quote (Tabel 2)
September 98.53% 99.97% 100% 98.46%
noneAvailability98.5 %Both extractors agreed
—bagasse conveyor chain
Show verbatim quote (Tabel 2)
Juli 90.89% 98.99% 100% 89.98%
nonePerformance99.0 %Both extractors agreed
—bagasse conveyor chain
Show verbatim quote (Tabel 2)
Juni 94.89% 71.94% 100% 68.27%
nonePerformance71.9 %Both extractors agreed
—bagasse conveyor chain
Show verbatim quote (Tabel 2)
Juli 90.89% 98.99% 100% 89.98%
noneAvailability90.9 %Both extractors agreed
—bagasse conveyor chain
Show verbatim quote (Tabel 2)
Juni 94.89% 71.94% 100% 68.27%
noneAvailability94.9 %Both extractors agreed
Startup defectbagasse conveyor chain
Show verbatim quote (Tabel 3)
Rata-rata 1.92% 5.36% 1% 7.11% 0 0
Start-up losses (reduced yield)Share of planned time0 %Both extractors agreed
Defect lossesbagasse conveyor chain
Show verbatim quote (Tabel 3)
Rata-rata 1.92% 5.36% 1% 7.11% 0 0
Process defects (scrap and rework)Share of planned time0 %Both extractors agreed
Reduce speed lossesbagasse conveyor chain
Show verbatim quote (Tabel 3)
Rata-rata 1.92% 5.36% 1% 7.11% 0 0
Reduced speedShare of planned time7.11 %Both extractors agreed
Idle and minorbagasse conveyor chain
Show verbatim quote (Tabel 3)
Rata-rata 1.92% 5.36% 1% 7.11% 0 0
Idling and minor stops (micro-stops)Share of planned time1.00 %Both extractors agreed
Setup and adjustmentbagasse conveyor chain
Show verbatim quote (Tabel 3)
Rata-rata 1.92% 5.36% 1% 7.11% 0 0
Setup and adjustmentsShare of planned time5.36 %Both extractors agreed
Breakdown lossesbagasse conveyor chain
Show verbatim quote (Tabel 3)
Rata-rata 1.92% 5.36% 1% 7.11% 0 0
Equipment failure (breakdowns)Share of planned time1.92 %Both extractors agreed
—bagasse conveyor chain
Show verbatim quote (Tabel 2)
Oktober 85.02% 91.81% 100% 78.06%
nonePerformance91.8 %Both extractors agreed
—bagasse conveyor chain
Show verbatim quote (Tabel 2)
Agustus 94.35% 91.89% 100% 86.70%
nonePerformance91.9 %Both extractors agreed
—bagasse conveyor chain
Show verbatim quote (Tabel 2)
Oktober 85.02% 91.81% 100% 78.06%
noneAvailability85.0 %Both extractors agreed
—bagasse conveyor chain
Show verbatim quote (Tabel 2)
Agustus 94.35% 91.89% 100% 86.70%
noneAvailability94.4 %Both extractors agreed
—bagasse conveyor chain
Show verbatim quote (Results text)
Untuk quality, semua diberi nilai 100% karena ketika penyaluran bahan bakar ke boiler tidak ada produk cacat.
noneQuality100 %Both extractors agreed
—bagasse conveyor chain
Show verbatim quote (Results text)
Rata-rata OEE selama enam bulan adalah 85.57%.
noneOEE85.6 %Single extractor
—bagasse conveyor chain
Show verbatim quote (Tabel 1)
Mei 18.17 264 15525.889
Not classifiable from the reportLost time18.2 jamSingle extractor
—bagasse conveyor chain
Show verbatim quote (Tabel 1)
Juni 29.42 720 23909.813
Not classifiable from the reportLost time29.4 jamSingle extractor
—bagasse conveyor chain
Show verbatim quote (Tabel 1)
Juli 67.75 744 53733.472
Not classifiable from the reportLost time67.8 jamSingle extractor
—bagasse conveyor chain
Show verbatim quote (Tabel 1)
Agu 39.33 744 51019.920
Not classifiable from the reportLost time39.3 jamSingle extractor
—bagasse conveyor chain
Show verbatim quote (Tabel 1)
Sep 10.58 720 44151.314
Not classifiable from the reportLost time10.6 jamSingle extractor
—bagasse conveyor chain
Show verbatim quote (Tabel 1)
Okt 107.83 720 29448.068
Not classifiable from the reportLost time108 jamSingle extractor
Setup and adjustmentbagasse conveyor chain
Show verbatim quote (Tabel 4)
Setup and adjustment 0.0536 35% 81%
Setup and adjustmentsShare of lost time35.0 %Single extractor
Defect lossesbagasse conveyor chain
Show verbatim quote (Tabel 4)
Defect losses 0 0 100%
Process defects (scrap and rework)Share of lost time0 %Single extractor
Startup defectbagasse conveyor chain
Show verbatim quote (Tabel 4)
Startup defect 0 0 100%
Start-up losses (reduced yield)Share of lost time0 %Single extractor
—
Show verbatim quote (Table 2)
Mei | 93.12% | 99.45% | 100% | 91.93%
noneQuality100 %Single extractor
—
Show verbatim quote (Table 2)
Mei | 93.12% | 99.45% | 100% | 91.93%
noneOEE91.9 %Single extractor
—
Show verbatim quote (Table 2)
Juni | 94.89% | 71.94% | 100% | 68.27%
noneOEE68.3 %Single extractor
—
Show verbatim quote (Table 2)
Juli | 90.89% | 98.99% | 100% | 89.98%
noneOEE90.0 %Single extractor
—
Show verbatim quote (Table 2)
Agustus | 94.35% | 91.89% | 100% | 86.70%
noneOEE86.7 %Single extractor
—
Show verbatim quote (Table 2)
September | 98.53% | 99.97% | 100% | 98.46%
noneOEE98.5 %Single extractor
—
Show verbatim quote (Table 2)
Oktober | 85.02% | 91.81% | 100% | 78.06%
noneOEE78.1 %Single extractor

Observation units

  • Bagasse conveyor chain (stasiun ketel) · Conveying and accumulation · Baseline
  • Bagasse conveyor · Conveying and accumulation · Baseline