Analysis Of Overall Equipment Effectiveness (OEE) Rice Milling Unit Machines to At CV Fajar Samudra
1Bibliographic record
- Authors
- Ismi Mashabai, Marisa Desita Ramdani, Ulfaturrahmi, Koko Hermanto
- Year
- 2025
- Venue
- Metode Jurnal Teknik Industri
- Country
- Indonesia
- Segment
- Grain and oilseed milling
- Process family
- Slaughter, cutting and primary processing
- Study type
- Single case study
- Extraction scope
- Full text
- Size
- 1 plants · 1 lines · 1 machines
- Observation period
- 182 days
- Data collection
- manual_logs
- Intervention
Show the setting as described by the study
Alur produksi mesin Rice Milling Unit diawali dari pengeringan dimana sebelum masuk proses pengeringan terlebih dulu dilakukan penimbangan selanjutnya dimasukan ke mesin dryer yang kemudian dimasukan ke Rice Milling Unit (RMU).
2Risk of bias
Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 12Moderate risk
| Item | Score |
|---|---|
| Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product, process and equipment are all described. | 2 / 2 |
| Is the observation period long enough and reported?Period reported and at least 30 days of production (or at least 100 recorded events). | 2 / 2 |
| How were loss data collected?Manual logs or maintenance records with unknown completeness. | 1 / 2 |
| Are OEE, loading time and the loss categories defined explicitly?A standard definition is cited but its application is not shown. | 1 / 2 |
| Does the loss breakdown account for the total loss it claims to explain?Only the top causes are reported and the unexplained remainder can be computed. | 1 / 2 |
| Is there evidence of selective reporting of favourable results?Observational study, or intervention study that reports baseline and post-intervention data with the same method. | 2 / 2 |
| Are the reported numbers internally consistent?Small inconsistencies (2 to 10 percentage points) or values that cannot be cross-checked. | 1 / 2 |
| Could conflicts of interest or the source of the data bias the result?Academic or independent study, or conflicts declared and unrelated to the result. | 2 / 2 |
3Extracted data
Each datum with its classification and the verbatim quote that states it.
| Reported cause | Loss category | Metric | Value | Extraction |
|---|---|---|---|---|
—Show verbatim quote (Table 4 (Six Big Losses))Oktober 2023 2,19 3,46 39,33 48,49 0,18 | Process defects (scrap and rework) | Share of lost time | 0.180 % | Both extractors agreed |
—Show verbatim quote (Table 4 (Six Big Losses))Oktober 2023 2,19 3,46 39,33 48,49 0,18 | Reduced speed | Share of lost time | 48.5 % | Both extractors agreed |
—Show verbatim quote (Table 4 (Six Big Losses))Oktober 2023 2,19 3,46 39,33 48,49 0,18 | Idling and minor stops (micro-stops) | Share of lost time | 39.3 % | Both extractors agreed |
—Show verbatim quote (Table 4 (Six Big Losses))Oktober 2023 2,19 3,46 39,33 48,49 0,18 | Setup and adjustments | Share of lost time | 3.46 % | Both extractors agreed |
—Show verbatim quote (Table 4 (Six Big Losses))Oktober 2023 2,19 3,46 39,33 48,49 0,18 | Equipment failure (breakdowns) | Share of lost time | 2.19 % | Both extractors agreed |
—Show verbatim quote (Table 3 (Quality))Okt-23 390.000 1.450 99,62% | none | Quality | 99.6 % | Both extractors agreed |
—Show verbatim quote (Table 2 (Performance))Okt-23 8,180 700,000 390,000 0,011 85,57 52,44 | none | Performance | 52.4 % | Both extractors agreed |
—Show verbatim quote (Table 1 (Availability))Okt-23 9.240 600 8,670 300 190 8,180 94,34% | none | Availability | 94.3 % | Both extractors agreed |
—Show verbatim quote (Section 3.4 (Nilai OEE))Di peroleh rata-rata nilai OEE pada mesin rice milling unit sebesar 57,02%, masih jauh dari nilai OEE Institute Of Plant Maintenance yaitu 84%. | none | OEE | 57.0 % | Both extractors agreed |
—Show verbatim quote (Table 1 (Availability))Okt-23 9.240 600 8,670 300 190 8,180 94,34% | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 600 min | Single extractor |
—Show verbatim quote (Table 1 (Availability))Okt-23 9.240 600 8,670 300 190 8,180 94,34% | Setup and adjustments | Lost time | 300 min | Single extractor |
—Show verbatim quote (Table 1 (Availability))Okt-23 9.240 600 8,670 300 190 8,180 94,34% | Equipment failure (breakdowns) | Lost time | 190 min | Single extractor |
—Show verbatim quote (Table 1 (Availability))Nov-23 9.240 750 8,490 300 160 8,030 94,58% | none | Availability | 94.6 % | Single extractor |
—Show verbatim quote (Table 1 (Availability))Nov-23 9.240 750 8,490 300 160 8,030 94,58% | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 750 min | Single extractor |
—Show verbatim quote (Table 1 (Availability))Nov-23 9.240 750 8,490 300 160 8,030 94,58% | Equipment failure (breakdowns) | Lost time | 160 min | Single extractor |
—Show verbatim quote (Table 1 (Availability))Des-23 8.820 650 8,170 285 145 7,738 94,73% | none | Availability | 94.7 % | Single extractor |
—Show verbatim quote (Table 1 (Availability))Des-23 8.820 650 8,170 285 145 7,738 94,73% | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 650 min | Single extractor |
—Show verbatim quote (Table 1 (Availability))Des-23 8.820 650 8,170 285 145 7,738 94,73% | Setup and adjustments | Lost time | 285 min | Single extractor |
—Show verbatim quote (Table 1 (Availability))Des-23 8.820 650 8,170 285 145 7,738 94,73% | Equipment failure (breakdowns) | Lost time | 145 min | Single extractor |
—Show verbatim quote (Table 1 (Availability))Jan-24 9.660 550 9,410 315 145 8,950 97,92% | none | Availability | 97.9 % | Single extractor |
—Show verbatim quote (Table 1 (Availability))Jan-24 9.660 550 9,410 315 145 8,950 97,92% | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 550 min | Single extractor |
—Show verbatim quote (Table 1 (Availability))Jan-24 9.660 550 9,410 315 145 8,950 97,92% | Setup and adjustments | Lost time | 315 min | Single extractor |
—Show verbatim quote (Table 1 (Availability))Feb-24 8.820 690 8,130 285 160 7,685 94,52% | none | Availability | 94.5 % | Single extractor |
—Show verbatim quote (Table 1 (Availability))Feb-24 8.820 690 8,130 285 160 7,685 94,52% | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 690 min | Single extractor |
—Show verbatim quote (Table 1 (Availability))Mar-24 8.820 500 8,320 285 175 95,19% | none | Availability | 95.2 % | Single extractor |
—Show verbatim quote (Table 1 (Availability))Mar-24 8.820 500 8,320 285 175 95,19% | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 500 min | Single extractor |
—Show verbatim quote (Table 1 (Availability))Mar-24 8.820 500 8,320 285 175 95,19% | Equipment failure (breakdowns) | Lost time | 175 min | Single extractor |
—Show verbatim quote (Table 2 (Performance))Nov-23 8,030 495,000 320,000 0,016 61,64 63,76 | none | Performance | 63.8 % | Single extractor |
—Show verbatim quote (Table 2 (Performance))Des-23 7,738 490,000 315,000 0,015 63,32 61,06 | none | Performance | 61.1 % | Single extractor |
—Show verbatim quote (Table 2 (Performance))Jan-24 8,950 570,000 390,000 0,015 63,68 65,36 | none | Performance | 65.4 % | Single extractor |
—Show verbatim quote (Table 2 (Performance))Feb-24 7,658 505,000 295,000 0,015 65,71 56,99 | none | Performance | 57.0 % | Single extractor |
—Show verbatim quote (Table 3 (Quality))Nov-24 320.000 1.365 99,57% | none | Quality | 99.6 % | Single extractor |
—Show verbatim quote (Table 3 (Quality))Des-23 315.000 1.100 99,65% | none | Quality | 99.7 % | Single extractor |
—Show verbatim quote (Table 3 (Quality))Jan-24 390.000 1.575 99,59% | none | Quality | 99.6 % | Single extractor |
—Show verbatim quote (Table 3 (Quality))Mar-24 300.000 1.550 99,48% | none | Quality | 99.5 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))November 2023 1,88 3,53 32,03 59,58 0,25 | Equipment failure (breakdowns) | Share of lost time | 1.88 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))November 2023 1,88 3,53 32,03 59,58 0,25 | Setup and adjustments | Share of lost time | 3.53 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))November 2023 1,88 3,53 32,03 59,58 0,25 | Idling and minor stops (micro-stops) | Share of lost time | 32.0 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))November 2023 1,88 3,53 32,03 59,58 0,25 | Reduced speed | Share of lost time | 59.6 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))November 2023 1,88 3,53 32,03 59,58 0,25 | Process defects (scrap and rework) | Share of lost time | 0.250 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))Desember 2023 1,77 3,48 32,12 57,05 0,20 | Equipment failure (breakdowns) | Share of lost time | 1.77 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))Desember 2023 1,77 3,48 32,12 57,05 0,20 | Setup and adjustments | Share of lost time | 3.48 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))Desember 2023 1,77 3,48 32,12 57,05 0,20 | Idling and minor stops (micro-stops) | Share of lost time | 32.1 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))Desember 2023 1,77 3,48 32,12 57,05 0,20 | Reduced speed | Share of lost time | 57.1 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))Desember 2023 1,77 3,48 32,12 57,05 0,20 | Process defects (scrap and rework) | Share of lost time | 0.200 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))Januari 2024 1,54 3,34 28,69 61,49 0,25 | Equipment failure (breakdowns) | Share of lost time | 1.54 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))Januari 2024 1,54 3,34 28,69 61,49 0,25 | Setup and adjustments | Share of lost time | 3.34 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))Januari 2024 1,54 3,34 28,69 61,49 0,25 | Idling and minor stops (micro-stops) | Share of lost time | 28.7 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))Januari 2024 1,54 3,34 28,69 61,49 0,25 | Reduced speed | Share of lost time | 61.5 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))Febuari 2024 1,96 3,50 38,74 53,61 0,23 | Equipment failure (breakdowns) | Share of lost time | 1.96 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))Febuari 2024 1,96 3,50 38,74 53,61 0,23 | Setup and adjustments | Share of lost time | 3.50 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))Febuari 2024 1,96 3,50 38,74 53,61 0,23 | Idling and minor stops (micro-stops) | Share of lost time | 38.7 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))Febuari 2024 1,96 3,50 38,74 53,61 0,23 | Reduced speed | Share of lost time | 53.6 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))Febuari 2024 1,96 3,50 38,74 53,61 0,23 | Process defects (scrap and rework) | Share of lost time | 0.230 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))Maret 2024 2,10 3,42 34,61 56,95 0,29 | Equipment failure (breakdowns) | Share of lost time | 2.10 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))Maret 2024 2,10 3,42 34,61 56,95 0,29 | Setup and adjustments | Share of lost time | 3.42 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))Maret 2024 2,10 3,42 34,61 56,95 0,29 | Idling and minor stops (micro-stops) | Share of lost time | 34.6 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))Maret 2024 2,10 3,42 34,61 56,95 0,29 | Reduced speed | Share of lost time | 57.0 % | Single extractor |
—Show verbatim quote (Table 4 (Six Big Losses))Maret 2024 2,10 3,42 34,61 56,95 0,29 | Process defects (scrap and rework) | Share of lost time | 0.290 % | Single extractor |
v-belt mesin putus/kendorv-beltShow verbatim quote (Section 1 (Pendahuluan))Berdasarkan informasi dari pemilik perusahaan permasalahan yang terjadi pada mesin pengiling beras (Rice Milling Unit) yakni v-belt putus atau kendor sehingga mengakibatkan mesin berhenti dan tidak beroperasi + selama 4 jam. | Equipment failure (breakdowns) | Mean event duration | 4.00 jam | Single extractor |
Observation units
- Rice Milling Unit · Milling and grinding · Baseline