1Bibliographic record
- Authors
- Chollaya Chotivetthamrong, Jittra Rukijkanpanich
- Year
- 2006
- Venue
- Chula Digiverse
- Country
- Thailand
- Segment
- Dairy products
- Process family
- Refrigeration and freezing
- Study type
- Before/after intervention
- Extraction scope
- Abstract only
- Size
- 1 plants · 1 lines · — machines
- Observation period
- —
- Data collection
- not_reported
- Intervention
Show the setting as described by the study
The objective of this study is to reduce the production time losses in the stick line that has the most serious demands.
2Risk of bias
Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 6High risk
| Item | Score |
|---|---|
| Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product or sector is given but the equipment or process is only partly described. | 1 / 2 |
| Is the observation period long enough and reported?Period not reported. | 0 / 2 |
| How were loss data collected?Interviews, estimates, or method not reported. | 0 / 2 |
| Are OEE, loading time and the loss categories defined explicitly?No definition; metrics are reported as bare numbers. | 0 / 2 |
| Does the loss breakdown account for the total loss it claims to explain?Only selected causes are reported and the total is unknown. | 0 / 2 |
| Is there evidence of selective reporting of favourable results?Intervention study in which baseline and post-intervention periods differ in length or method. | 1 / 2 |
| Are the reported numbers internally consistent?Recomputed totals, shares and OEE factors agree with the reported values within 2 percentage points. | 2 / 2 |
| Could conflicts of interest or the source of the data bias the result?Academic or independent study, or conflicts declared and unrelated to the result. | 2 / 2 |
3Extracted data
Each datum with its classification and the verbatim quote that states it.
| Reported cause | Loss category | Metric | Value | Extraction |
|---|---|---|---|---|
set up timeShow verbatim quote (abstract)the improved processes can reduce set up time from 6.90 hrs per production cycle to 2.43 hrs per production cycle or about 64.78% | Setup and adjustments | Lost time | 2.43 hrs per production cycle | Both extractors agreed |
set up timeShow verbatim quote (abstract)the improved processes can reduce set up time from 6.90 hrs per production cycle to 2.43 hrs per production cycle or about 64.78% | Setup and adjustments | Lost time | 6.90 hrs per production cycle | Both extractors agreed |
Observation units
- Stick line · Whole line or unspecified equipment · After intervention
- Stick line · Whole line or unspecified equipment · Baseline