Changeover / setup time
In short
It appears in about 11 of every 100 lines studied.
When it appears, it takes on average about 66 % of the line's lost time. Reported by 33 of the 127 studies that could observe it (strong evidence).
What happens
Time is lost between the last good unit of one production run and the first good unit of the next while the line is stopped or run at non-production rate to change product, format, tooling or recipe, including cleaning, warm-up and the restart ramp after a cold start. The duration depends on the complexity of the mechanical, electrical and process adjustments required and on how standardized or manual the changeover procedure is.
What is done about it
Apply SMED methodology to separate internal from external setup tasks, standardize and pre-stage tools, parts and recipes, and use quick-change fixtures or format parts to reduce manual adjustment. Train operators on documented standard changeover sequences and track changeover duration as a key performance indicator to drive continuous improvement.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 11% [6–17%]
- Expected share of lost time
- 7.0% [3.7–11.6%]
- Share of lost time when present
- 66% [58–74%]
- Studies / units
- 127 / 161
- Evidence grade
- A
Grade A: 10 or more studies and 10 or more distinct lines, with a 95% credible interval narrower than 0.20.
2Probability by segment
- Dairy products24% [10–43%]13 studies
- Soft drinks, bottled water and juices11% [5–20%]26 studies
- Brewing, wine and spirits14% [5–29%]11 studies
- Bakery and pasta11% [4–21%]24 studies
- Meat, poultry and seafood10% [3–23%]9 studies
- Fruit and vegetable processing15% [4–33%]7 studies
- Grain and oilseed milling8.8% [2.2–21.7%]6 studies
- Sugar and confectionery16% [5–31%]9 studies
- Snacks, coffee, tea and other foods11% [3–26%]5 studies
- Animal feed and pet food11% [3–24%]7 studies
- Food manufacturing (unspecified or mixed)15% [4–32%]10 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceTime is lost between the last good unit of one production run and the first good unit of the next while the line is stopped or run at non-production rate to change product, format, tooling or recipe, including cleaning, warm-up and the restart ramp after a cold start. The duration depends on the complexity of the mechanical, electrical and process adjustments required and on how standardized or manual the changeover procedure is.
How it looks in SCADA data
Engineering guidanceExtended machine-state intervals in a non-running or manual/setup mode between the last cycle of one SKU and the first cycle of the next, with order or recipe change events bracketing the stop, flat production counters, and absence of fault alarms distinguishing it from unplanned downtime. Repeated changeover events correlate with product or format code transitions logged in MES.
Countermeasure
Engineering guidanceApply SMED methodology to separate internal from external setup tasks, standardize and pre-stage tools, parts and recipes, and use quick-change fixtures or format parts to reduce manual adjustment. Train operators on documented standard changeover sequences and track changeover duration as a key performance indicator to drive continuous improvement.
4Sources
- Analisis Efektivitas Mesin pada Divisi Pengalengan Jamur Di PT XYZ Menggunakan Metode Overall Equipment Effectiveness (2019)Open sourceShare of planned time: 9.30 % · as reported: “Setup & Adjustment Losses”
Show verbatim quote
Rata-Rata 0,099271 9,29814 30,74813 0,00000 0,00000 0,13414
- Analisis Efektivitas Mesin pada Divisi Pengalengan Jamur Di PT XYZ Menggunakan Metode Overall Equipment Effectiveness (2019)Open sourceShare of lost time: 23.1 % · as reported: “Setup & Adjustment Losses”
Show verbatim quote
Dapat dilihat di grafik bahwa nilai losses terbesar ada pada idle & minor stoppages losses dan setup & adjustment losses yang mewakili 76,34% dan 23,08% dari total losses perusahaan, hal ini tentu saja harus diperbaiki.
- Optimización de los tiempos de operación del área de envasado de yogurt en industrias lácteas Toni S.A. (2018)Open sourceLost time: 34.0 min · as reported: “cambio de formato”
Show verbatim quote
el tiempo total empleado fue de 34 minutos 0 segundos, realizándose un total de 36 actividades, las actividades que se realizan respecto a esta máquina son principalmente del tipo Operación.
- Optimización de los tiempos de operación del área de envasado de yogurt en industrias lácteas Toni S.A. (2018)Open sourceNumber of events: 36.0 activities · as reported: “cambio de formato”
Show verbatim quote
el tiempo total empleado fue de 34 minutos 0 segundos, realizándose un total de 36 actividades, las actividades que se realizan respecto a esta máquina son principalmente del tipo Operación.
- Optimización de los tiempos de operación del área de envasado de yogurt en industrias lácteas Toni S.A. (2018)Open sourceLost time: 54.0 min · as reported: “cambio de formato”
Show verbatim quote
El tiempo total empleado para la realización de todas las actividades que comprenden el cambio de formato fue de 54 minutos 0 segundos, realizándose un total de 65 actividades, siendo la máquina con la mayor cantidad de actividades realizadas en comparación con la Fogg, Karlville y Edos.
- Optimización de los tiempos de operación del área de envasado de yogurt en industrias lácteas Toni S.A. (2018)Open sourceNumber of events: 65.0 activities · as reported: “cambio de formato”
Show verbatim quote
El tiempo total empleado para la realización de todas las actividades que comprenden el cambio de formato fue de 54 minutos 0 segundos, realizándose un total de 65 actividades, siendo la máquina con la mayor cantidad de actividades realizadas en comparación con la Fogg, Karlville y Edos.
- Optimización de los tiempos de operación del área de envasado de yogurt en industrias lácteas Toni S.A. (2018)Open sourceLost time: 21.0 min · as reported: “cambio de formato”
Show verbatim quote
El tiempo total propuesto para el cambio de formato se acortó en un 4,76%, de 21 a 20 minutos, respecto al de las videograbaciones.
- Optimización de los tiempos de operación del área de envasado de yogurt en industrias lácteas Toni S.A. (2018)Open sourceNumber of events: 37.0 activities · as reported: “cambio de formato”
Show verbatim quote
en el cual se disminuyeron las actividades en gran medida, de 37 a 7, la mayoría operativa.
- Optimización de los tiempos de operación del área de envasado de yogurt en industrias lácteas Toni S.A. (2018)Open sourceLost time: 20.0 min · as reported: “cambio de formato”
Show verbatim quote
El tiempo total propuesto para el cambio de formato se acortó en un 4,76%, de 21 a 20 minutos, respecto al de las videograbaciones.
- Optimización de los tiempos de operación del área de envasado de yogurt en industrias lácteas Toni S.A. (2018)Open sourceNumber of events: 7.00 activities · as reported: “cambio de formato”
Show verbatim quote
en el cual se disminuyeron las actividades en gran medida, de 37 a 7, la mayoría operativa.
- Optimizing beverage manufacturing: integrating lean manufacturing and machine learning to enhance efficiency and reduce waste (2025)Open sourceLost time: 42.0 min · as reported: “Line changeover”
Show verbatim quote
Line change time | Average | 42 | 16
- Optimizing beverage manufacturing: integrating lean manufacturing and machine learning to enhance efficiency and reduce waste (2025)Open sourceLost time: 16.0 min · as reported: “Line changeover”
Show verbatim quote
Line change time | Average | 42 | 16
- Enhancing operational efficiency in craft beer production: implementation of lean manufacturing and TPM methodologies in SMES (2025)Open sourceLost time: 41.0 min · as reported: “Setup time”
Show verbatim quote
Setup time was reduced from 41 to 29 minutes, representing a 29% decrease.
- Enhancing operational efficiency in craft beer production: implementation of lean manufacturing and TPM methodologies in SMES (2025)Open sourceLost time: 29.0 min · as reported: “Setup time”
Show verbatim quote
Setup time was reduced from 41 to 29 minutes, representing a 29% decrease.
- Investigation on a multiscale sustainable manufacturing approach to production changeover complexity reduction and its implementation through smart surfaces and process optimization (2022)Open sourceShare of lost time: 16.5 % · as reported: “Change Over”
Show verbatim quote
Change Over 55 16.50%
- Investigation on a multiscale sustainable manufacturing approach to production changeover complexity reduction and its implementation through smart surfaces and process optimization (2022)Open sourceLost time: 55.0 min · as reported: “Set up and Change Over”
Show verbatim quote
Set up and Change Over 27 28 55
- Share of planned time: 20.0 % · as reported: “Tip dönüşüm süreleri”
Show verbatim quote
Tip dönüşüm sürelerinin tüm üretim zamanının %20’sini oluşturduğu gözlemlenmiştir.
- Lost time: 300 dk · as reported: “Toplam Tip Dönüş Süresi”
Show verbatim quote
Toplam Tip Dönüş Süresi 300 325 120 300 460 400 540
- Lost time: 325 dk · as reported: “Toplam Tip Dönüş Süresi”
Show verbatim quote
Toplam Tip Dönüş Süresi 300 325 120 300 460 400 540
- Lost time: 120 dk · as reported: “Toplam Tip Dönüş Süresi”
Show verbatim quote
Toplam Tip Dönüş Süresi 300 325 120 300 460 400 540
- Lost time: 460 dk · as reported: “Toplam Tip Dönüş Süresi”
Show verbatim quote
Toplam Tip Dönüş Süresi 300 325 120 300 460 400 540
- Lost time: 400 dk · as reported: “Toplam Tip Dönüş Süresi”
Show verbatim quote
Toplam Tip Dönüş Süresi 300 325 120 300 460 400 540
- Lost time: 540 dk · as reported: “Toplam Tip Dönüş Süresi”
Show verbatim quote
Toplam Tip Dönüş Süresi 300 325 120 300 460 400 540
- Lost time: 1,230 dk · as reported: “Toplam tip dönüştürme süresi”
Show verbatim quote
Toplam tip dönüştürme süresi 1230 dk
- Enhancing Machinery Availability in a Food Company: An Integrated Approach Using TPM, SMED, and RCM Methodologies (2024)Open sourceLost time: 25.6 min · as reported: “Internal activities time (final)”
Show verbatim quote
At the end of the activities, a final process time of 105.69 minutes was obtained, with eight internal and 25 external activities, each with a time of 25.62 and 80.07 minutes, respectively.
- Enhancing Machinery Availability in a Food Company: An Integrated Approach Using TPM, SMED, and RCM Methodologies (2024)Open sourceLost time: 148 min · as reported: “Total production time of changeover activities”
Show verbatim quote
147.54 15 23 63.22 84.32
- Enhancing Machinery Availability in a Food Company: An Integrated Approach Using TPM, SMED, and RCM Methodologies (2024)Open sourceNumber of events: 15.0 events · as reported: “Internal activities”
Show verbatim quote
147.54 15 23 63.22 84.32
- Enhancing Machinery Availability in a Food Company: An Integrated Approach Using TPM, SMED, and RCM Methodologies (2024)Open sourceNumber of events: 23.0 events · as reported: “External activities”
Show verbatim quote
147.54 15 23 63.22 84.32
- Enhancing Machinery Availability in a Food Company: An Integrated Approach Using TPM, SMED, and RCM Methodologies (2024)Open sourceLost time: 63.2 min · as reported: “Internal activities time”
Show verbatim quote
147.54 15 23 63.22 84.32
- Enhancing Machinery Availability in a Food Company: An Integrated Approach Using TPM, SMED, and RCM Methodologies (2024)Open sourceLost time: 84.3 min · as reported: “External activities time”
Show verbatim quote
147.54 15 23 63.22 84.32
- Enhancing Machinery Availability in a Food Company: An Integrated Approach Using TPM, SMED, and RCM Methodologies (2024)Open sourceLost time: 106 min · as reported: “Final process time after SMED implementation”
Show verbatim quote
At the end of the activities, a final process time of 105.69 minutes was obtained, with eight internal and 25 external activities, each with a time of 25.62 and 80.07 minutes, respectively.
- Enhancing Machinery Availability in a Food Company: An Integrated Approach Using TPM, SMED, and RCM Methodologies (2024)Open sourceNumber of events: 25.0 events · as reported: “External activities (final)”
Show verbatim quote
At the end of the activities, a final process time of 105.69 minutes was obtained, with eight internal and 25 external activities, each with a time of 25.62 and 80.07 minutes, respectively.
- Enhancing Machinery Availability in a Food Company: An Integrated Approach Using TPM, SMED, and RCM Methodologies (2024)Open sourceLost time: 80.1 min · as reported: “External activities time (final)”
Show verbatim quote
At the end of the activities, a final process time of 105.69 minutes was obtained, with eight internal and 25 external activities, each with a time of 25.62 and 80.07 minutes, respectively.
- Number of events: 15.0 changeovers/month · as reported: “changeover”
Show verbatim quote
Machines operating the line had, on average, 15 changeovers/month, each taking significant times.
- Number of events: 19.0 changeovers/month · as reported: “changeover”
Show verbatim quote
The number of machines in lines 1, 2, 3 and 4/5 was respectively 5, 10, 9 and 12, while changeovers per month in the same lines were on average 19, 28, 22 and 35.
- Number of events: 28.0 changeovers/month · as reported: “changeover”
Show verbatim quote
The number of machines in lines 1, 2, 3 and 4/5 was respectively 5, 10, 9 and 12, while changeovers per month in the same lines were on average 19, 28, 22 and 35.
- Number of events: 22.0 changeovers/month · as reported: “changeover”
Show verbatim quote
The number of machines in lines 1, 2, 3 and 4/5 was respectively 5, 10, 9 and 12, while changeovers per month in the same lines were on average 19, 28, 22 and 35.
- Number of events: 35.0 changeovers/month · as reported: “changeover”
Show verbatim quote
The number of machines in lines 1, 2, 3 and 4/5 was respectively 5, 10, 9 and 12, while changeovers per month in the same lines were on average 19, 28, 22 and 35.
- Share of lost time: 7.60 % · as reported: “SMED (changeover) time reduction”
Show verbatim quote
Latest fine-tuning in 2012 decreased SMED time for 7.6% or 3473 minutes
- Share of lost time: 36.0 % · as reported: “Setup”
Show verbatim quote
verificou-se que as paradas do equipamento Klockner representa 30% de todos estes desperdício e que 36 % estão relacionadas com set ups e 34% são relativas a outro problemas.
- Lost time: 2.00 min · as reported: “Separate necessary keys for setup”
Show verbatim quote
1 Separar as chaves necessárias para setup 00:00:00 00:02:00 00:02:00 00:02:00 -
- Lost time: 2.00 min · as reported: “Fetch test bottles”
Show verbatim quote
2 Buscar garrafas testes 00:02:00 00:04:00 00:02:00 00:02:00 -
- Lost time: 13.0 min · as reported: “Adjust flaps”
Show verbatim quote
5 Ajuste das aletas 00:45:00 00:58:00 00:13:00 00:13:00 -
- Lost time: 18.0 min · as reported: “Adjust pneumatic classifier”
Show verbatim quote
6 Ajuste no classificador pneumáti co 00:58:00 01:16:00 00:18:00 00:18:00 -
- Lost time: 6.00 min · as reported: “Adjust film reading sensor”
Show verbatim quote
8 Ajuste no sensor de leitura do filme 01:23:00 01:29:00 00:06:00 00:06:00 -
- Lost time: 5.00 min · as reported: “Set pusher chain to zero point”
Show verbatim quote
11 Colocar a cadeia empurradora no ponto zero 01:35:00 01:40:00 00:05:00 00:05:00 -
- Lost time: 2.00 min · as reported: “Disengage table regulator”
Show verbatim quote
12 Desacoplar regulador da mesa 01:40:00 01:42:00 00:02:00 00:02:00 -
- Lost time: 6.00 min · as reported: “Set wrapping chain to zero point”
Show verbatim quote
13 Colocar cadeia de envolvimento ponto zero 01:42:00 01:48:00 00:06:00 00:06:00 -
- Lost time: 2.00 min · as reported: “Get 250 ml dividers (verandas)”
Show verbatim quote
14 Pegar varandas de 250 ml 01:48:00 01:50:00 00:02:00 00:02:00 -
- Lost time: 4.00 min · as reported: “Change dividers position”
Show verbatim quote
15 Trocar posição de varandas 01:50:00 01:54:00 00:04:00 00:04:00 -
- Lost time: 10.0 min · as reported: “Get film for 250 ml”
Show verbatim quote
16 Pegar filme para 250 ml 01:54:00 02:04:00 00:10:00 00:10:00 -
- Lost time: 4.00 min · as reported: “Change film from 2 liters to 250 ml”
Show verbatim quote
17 Trocar filme de 2 litros para 250 ml 02:04:00 02:08:00 00:04:00 00:04:00 -
- Lost time: 4.00 min · as reported: “Test machine”
Show verbatim quote
18 Testar máquina 02:08:00 02:12:00 00:04:00 00:04:00 -
- Lost time: 3.00 min · as reported: “Organize tools used in setup”
Show verbatim quote
19 Organizar chaves usadas no set up 02:12:00 02:15:00 00:03:00 00:03:00 -
- Lost time: 3.00 min · as reported: “Adjust flaps”
Show verbatim quote
4 Ajuste das aletas 00:07:00 00:10:00 00:03:00 00:03:00 -
- Lost time: 4.00 min · as reported: “Adjust pneumatic classifier”
Show verbatim quote
5 Ajuste no classificador pneumático 00:10:00 00:14:00 00:04:00 00:04:00 -
- Lost time: 1.00 min · as reported: “Adjust film reading sensor”
Show verbatim quote
7 Ajuste no sensor de leitura do filme 00:15:00 00:16:00 00:01:00 00:01:00 -
- Lost time: 2.00 min · as reported: “Set pusher chain to zero point”
Show verbatim quote
9 Colocar a cadeia empurradora no ponto zero 00:17:00 00:19:00 00:02:00 00:02:00 -
- Lost time: 1.00 min · as reported: “Disengage wrapping table regulator”
Show verbatim quote
10 Desacoplar regulador mesa de envolvi mento 00:19:00 00:20:00 00:01:00 00:01:00 -
- Lost time: 1.00 min · as reported: “Set wrapping chain to zero point”
Show verbatim quote
11 Colocar cadeia envolvimento no ponto zero 00:20:00 00:21:00 00:01:00 00:01:00 -
- Lost time: 1.00 min · as reported: “Get 250 ml dividers (verandas)”
Show verbatim quote
12 Pegar varandas de 250 ml 00:21:00 00:22:00 00:01:00 - 00:01:00
- Lost time: 1.00 min · as reported: “Change dividers position”
Show verbatim quote
13 Trocar posição de varandas 00:22:00 00:23:00 00:01:00 00:01:00 -
- Lost time: 2.00 min · as reported: “Get film for 250 ml”
Show verbatim quote
14 Pegar filme para 250 ml 00:23:00 00:25:00 00:02:00 - 00:02:00
- Lost time: 4.00 min · as reported: “Change film from 2 liters to 250 ml”
Show verbatim quote
15 Trocar filme de 2 litros para 250 ml 00:25:00 00:29:00 00:04:00 00:04:00 -
- Lost time: 8.00 min · as reported: “Clean the equipment”
Show verbatim quote
17 Limpeza do equipamento 00:32:00 00:40:00 00:08:00 00:08:00 -
- IMPLEMENTASI 5R+1S SEBAGAI UPAYA PENINGKATAN EFEKTIVITAS PRODUKSI DENGAN METODE OVERALL EQUIPMENT EFFECTIVENESS (OEE) DI PT. COCA-COLA BOTTLING INDONESIA (2018)Open sourceLost time: 992 menit · as reported: “Set up”
Show verbatim quote
Juni 992 2.171 6.164
- IMPLEMENTASI 5R+1S SEBAGAI UPAYA PENINGKATAN EFEKTIVITAS PRODUKSI DENGAN METODE OVERALL EQUIPMENT EFFECTIVENESS (OEE) DI PT. COCA-COLA BOTTLING INDONESIA (2018)Open sourceLost time: 980 menit · as reported: “Set up”
Show verbatim quote
Mei 980 6.341 4.452
- IMPLEMENTASI 5R+1S SEBAGAI UPAYA PENINGKATAN EFEKTIVITAS PRODUKSI DENGAN METODE OVERALL EQUIPMENT EFFECTIVENESS (OEE) DI PT. COCA-COLA BOTTLING INDONESIA (2018)Open sourceLost time: 1,599 menit · as reported: “Set up”
Show verbatim quote
April 1.599 8.680 5.376
- IMPLEMENTASI 5R+1S SEBAGAI UPAYA PENINGKATAN EFEKTIVITAS PRODUKSI DENGAN METODE OVERALL EQUIPMENT EFFECTIVENESS (OEE) DI PT. COCA-COLA BOTTLING INDONESIA (2018)Open sourceLost time: 1,957 menit · as reported: “Set up”
Show verbatim quote
Maret 1.957 14.278 1.707
- IMPLEMENTASI 5R+1S SEBAGAI UPAYA PENINGKATAN EFEKTIVITAS PRODUKSI DENGAN METODE OVERALL EQUIPMENT EFFECTIVENESS (OEE) DI PT. COCA-COLA BOTTLING INDONESIA (2018)Open sourceLost time: 2,051 menit · as reported: “Set up”
Show verbatim quote
Februari 2.051 10.424 1.098
- IMPLEMENTASI 5R+1S SEBAGAI UPAYA PENINGKATAN EFEKTIVITAS PRODUKSI DENGAN METODE OVERALL EQUIPMENT EFFECTIVENESS (OEE) DI PT. COCA-COLA BOTTLING INDONESIA (2018)Open sourceLost time: 1,278 menit · as reported: “Set up”
Show verbatim quote
Januari 1.278 13.731 929
- IMPLEMENTASI 5R+1S SEBAGAI UPAYA PENINGKATAN EFEKTIVITAS PRODUKSI DENGAN METODE OVERALL EQUIPMENT EFFECTIVENESS (OEE) DI PT. COCA-COLA BOTTLING INDONESIA (2018)Open sourceLost time: 986 menit · as reported: “Set up”
Show verbatim quote
Desember 986 9.274 9.307
- IMPLEMENTASI 5R+1S SEBAGAI UPAYA PENINGKATAN EFEKTIVITAS PRODUKSI DENGAN METODE OVERALL EQUIPMENT EFFECTIVENESS (OEE) DI PT. COCA-COLA BOTTLING INDONESIA (2018)Open sourceLost time: 1,687 menit · as reported: “Set up”
Show verbatim quote
Oktober 1.687 8.213 15.131
- IMPLEMENTASI 5R+1S SEBAGAI UPAYA PENINGKATAN EFEKTIVITAS PRODUKSI DENGAN METODE OVERALL EQUIPMENT EFFECTIVENESS (OEE) DI PT. COCA-COLA BOTTLING INDONESIA (2018)Open sourceLost time: 1,120 menit · as reported: “Set up”
Show verbatim quote
Agustus 1.120 6.057 16.715
- IMPLEMENTASI 5R+1S SEBAGAI UPAYA PENINGKATAN EFEKTIVITAS PRODUKSI DENGAN METODE OVERALL EQUIPMENT EFFECTIVENESS (OEE) DI PT. COCA-COLA BOTTLING INDONESIA (2018)Open sourceLost time: 1,025 menit · as reported: “Set up”
Show verbatim quote
Juli 1.025 8.963 14.174
- IMPLEMENTASI 5R+1S SEBAGAI UPAYA PENINGKATAN EFEKTIVITAS PRODUKSI DENGAN METODE OVERALL EQUIPMENT EFFECTIVENESS (OEE) DI PT. COCA-COLA BOTTLING INDONESIA (2018)Open sourceLost time: 1,768 menit · as reported: “Set up”
Show verbatim quote
September 1.768 12.412 9.943
- IMPLEMENTASI 5R+1S SEBAGAI UPAYA PENINGKATAN EFEKTIVITAS PRODUKSI DENGAN METODE OVERALL EQUIPMENT EFFECTIVENESS (OEE) DI PT. COCA-COLA BOTTLING INDONESIA (2018)Open sourceLost time: 788 menit · as reported: “Set up”
Show verbatim quote
November 788 12.512 9.670
- Lost time: 103 min · as reported: “Bottle size changeover”
Show verbatim quote
Entre 2015 e 2017, a mudança de tara, a mudança de cápsula e a mudança de tara e cápsula duravam em média 102,5 minutos, 119,4 minutos e 151,8 minutos respetivamente
- Lost time: 119 min · as reported: “Capsule type changeover”
Show verbatim quote
Entre 2015 e 2017, a mudança de tara, a mudança de cápsula e a mudança de tara e cápsula duravam em média 102,5 minutos, 119,4 minutos e 151,8 minutos respetivamente
- Lost time: 152 min · as reported: “Bottle size and capsule type changeover”
Show verbatim quote
Entre 2015 e 2017, a mudança de tara, a mudança de cápsula e a mudança de tara e cápsula duravam em média 102,5 minutos, 119,4 minutos e 151,8 minutos respetivamente
- Share of lost time: 23.8 % · as reported: “Bottle size changeover”
Show verbatim quote
as mudanças que resultam na maior percentagem de tempo improdutivo são as mudanças de tara, de cápsula e de ambas em simultâneo, sem que haja mudança de cerveja, representando um peso percentual de 23,8%, 23,7% e 16,7% respetivamente
- Share of lost time: 23.7 % · as reported: “Capsule type changeover”
Show verbatim quote
as mudanças que resultam na maior percentagem de tempo improdutivo são as mudanças de tara, de cápsula e de ambas em simultâneo, sem que haja mudança de cerveja, representando um peso percentual de 23,8%, 23,7% e 16,7% respetivamente
- Share of lost time: 16.7 % · as reported: “Bottle size and capsule type changeover”
Show verbatim quote
as mudanças que resultam na maior percentagem de tempo improdutivo são as mudanças de tara, de cápsula e de ambas em simultâneo, sem que haja mudança de cerveja, representando um peso percentual de 23,8%, 23,7% e 16,7% respetivamente
- Lost time: 42.0 min · as reported: “Bottle size changeover”
Show verbatim quote
Considera-se que a mudança de tara, a mudança de cápsula e a mudança de tara e cápsula, após as melhorias desenvolvidas no projeto, passam a durar em média 42, 55 e 84 minutos (ver secção 4.6)
- Lost time: 55.0 min · as reported: “Capsule type changeover”
Show verbatim quote
Considera-se que a mudança de tara, a mudança de cápsula e a mudança de tara e cápsula, após as melhorias desenvolvidas no projeto, passam a durar em média 42, 55 e 84 minutos (ver secção 4.6)
- Lost time: 84.0 min · as reported: “Bottle size and capsule type changeover”
Show verbatim quote
Considera-se que a mudança de tara, a mudança de cápsula e a mudança de tara e cápsula, após as melhorias desenvolvidas no projeto, passam a durar em média 42, 55 e 84 minutos (ver secção 4.6)
- CHANGEOVER TIME REDUCTION THROUGH LEAN TOOL “SMED” – A CASE STUDY FROM FOOD SECTOR (2018)Open sourceShare of lost time: 83.0 % · as reported: “Internal activities”
Show verbatim quote
Internal activities occupied 83% of the total time.
- CHANGEOVER TIME REDUCTION THROUGH LEAN TOOL “SMED” – A CASE STUDY FROM FOOD SECTOR (2018)Open sourceShare of lost time: 77.0 % · as reported: “Changeovers”
Show verbatim quote
Changeovers on a particular selected line then account for a total of 77% of all planned stoppages on this line.
- CHANGEOVER TIME REDUCTION THROUGH LEAN TOOL “SMED” – A CASE STUDY FROM FOOD SECTOR (2018)Open sourceShare of lost time: 17.0 % · as reported: “External activities”
Show verbatim quote
internal; 83% external; 17% breakdown; 6% Figure 9 Internal vs external activities. Source: own
- Perancangan Ulang Mesin Pengaduk Sari Pati dengan Metode Reverse Engineering(Studi Kasus: UKM Pembuat Mie Soun Cap “Burung Sriti” Tulung, Klaten) (2017)Open sourceLost time: 7.00 min · as reported: “set up time”
Show verbatim quote
The result of the old machine indicate the set up time consuming about 7 minutes
- Aplicación de metodología SMED para reducir tiempos de cambio en formato de la línea de embotellado Grupo Bebidas Refrigerantes S.A. (2018)Open sourceMean event duration: 0.870 h · as reported: “format change”
Show verbatim quote
reducing the time in change from 1.5 hours to 0.87 hours
- Aplicación de metodología SMED para reducir tiempos de cambio en formato de la línea de embotellado Grupo Bebidas Refrigerantes S.A. (2018)Open sourceMean event duration: 1.50 h · as reported: “format change”
Show verbatim quote
reducing the time in change from 1.5 hours to 0.87 hours
- Aplicación de metodología SMED para reducir tiempos de cambio en formato de la línea de embotellado Grupo Bebidas Refrigerantes S.A. (2018)Open sourceShare of lost time: 42.2 % · as reported: “format change”
Show verbatim quote
reduction in the times of the format change up to 42.22%
- Aplicación de metodología SMED para reducir tiempos de cambio en formato de la línea de embotellado Grupo Bebidas Refrigerantes S.A. (2018)Open sourceLost time: 84.7 hours · as reported: “format change”
Show verbatim quote
When implementing the SMED methodology in the months of July to December, a time of 84.7 hours was increased
- Implantación de Herramientas Industriales para la Optimización del Proceso Industrial Lácteo-Fermentado (2019)Open sourceLost time: 16.1 Ton · as reported: “Cambio de Sabor”
Show verbatim quote
reducir de 22.9 a 16.1 toneladas un 30.2% por las causas de cambios de sabor, plásticos equivocados y falta de material en línea
- Implantación de Herramientas Industriales para la Optimización del Proceso Industrial Lácteo-Fermentado (2019)Open sourceLost time: 22.9 Ton · as reported: “Cambio de Sabor”
Show verbatim quote
reducir de 22.9 a 16.1 toneladas un 30.2% por las causas de cambios de sabor, plásticos equivocados y falta de material en línea
- Share of planned time: 28.0 % · as reported: “changeovers”
Show verbatim quote
Changeovers consumed 536 hours (28%), while machine breakdowns totalled 485 hours (25%).
- Lost time: 536 h · as reported: “changeovers”
Show verbatim quote
Changeovers consumed 536 hours (28%), while machine breakdowns totalled 485 hours (25%).
- Mean event duration: 66.1 min · as reported: “Product Exchange (Refrigerant)”
Show verbatim quote
Product Exchange (Refrigerant) 66.1 27.0 59.1
- Mean event duration: 19.7 min · as reported: “Product Exchange (Beer)”
Show verbatim quote
Product Exchange (Beer) 19.7 6.0 69.5
- Mean event duration: 89.3 min · as reported: “Format Exchange (Hs Mp For P12p)”
Show verbatim quote
Format Exchange (Hs Mp For P12p) 89.3 35.9 59.8
- Mean event duration: 27.0 min · as reported: “Product Exchange (Refrigerant)”
Show verbatim quote
Product Exchange (Refrigerant) 66.1 27.0 59.1
- Mean event duration: 6.00 min · as reported: “Product Exchange (Beer)”
Show verbatim quote
Product Exchange (Beer) 19.7 6.0 69.5
- Mean event duration: 35.9 min · as reported: “Format Exchange (Hs Mp For P12p)”
Show verbatim quote
Format Exchange (Hs Mp For P12p) 89.3 35.9 59.8
- Analisis Efektivitas Mesin pada Divisi Pengalengan Jamur Di PT. Suryajaya Abadiperkasa Menggunakan Metode Overall Equipment Effectiveness (2020)Open sourceShare of lost time: 9.30 % · as reported: “Setup & Adjustment Losses”
Show verbatim quote
Rata-Rata 0,099271 9,29814 30,74813 0,00000 0,00000 0,13414
- Analisis Efektivitas Mesin pada Divisi Pengalengan Jamur Di PT. Suryajaya Abadiperkasa Menggunakan Metode Overall Equipment Effectiveness (2020)Open sourceShare of lost time: 23.1 % · as reported: “Setup & Adjustment Losses”
Show verbatim quote
nilai losses terbesar ada pada idle & minor stoppages losses dan setup & adjustment losses yang mewakili 76,34% dan 23,08% dari total losses perusahaan
- Analisis Total Productive Maintenance Mesin Wrapping Line 4 Menggunkan Overall Equipment Effectiveness dan Six Big Losses di PT XY, Cirebon - Jawa Barat (2020)Open sourceShare of lost time: 0 % · as reported: “Setup and Adjustment Losses”
Show verbatim quote
Setup and Adjustment Losses 0% 0% 100%
- Maintenance Performance Evaluation and Downtime Analysis of Manufacturing Equipment in a Food Manufacturing Company (2021)Open sourceLost time: 1,797 min · as reported: “Miscellaneous activities”
Show verbatim quote
Miscellaneous activities 1797 1.71 100.00
- Maintenance Performance Evaluation and Downtime Analysis of Manufacturing Equipment in a Food Manufacturing Company (2021)Open sourceShare of lost time: 1.71 % · as reported: “Miscellaneous activities”
Show verbatim quote
Miscellaneous activities 1797 1.71 100.00
- Mean event duration: 156 min · as reported: “setup operation”
Show verbatim quote
Before the intervention, the time to conclude a setup operation was approximately 156 minutes. After the intervention, it was reduced to approximately 104 minutes.
- Mean event duration: 104 min · as reported: “setup operation”
Show verbatim quote
Before the intervention, the time to conclude a setup operation was approximately 156 minutes. After the intervention, it was reduced to approximately 104 minutes.
- Mean event duration: 45.0 s · as reported: “Changeover for new batch”
Show verbatim quote
The changeover time reduced from 94 second to 45 second per changeover.
- Number of events: 15.0 changeover/Month · as reported: “Changeover for new batch”
Show verbatim quote
Number of changeover per month = 15 changeover/Month.
- Mean event duration: 94.0 min · as reported: “Changeover for new batch”
Show verbatim quote
Changeover time is calculated with 94 min.
- Lost time: 1,410 Minutes · as reported: “Changeover for new batch”
Show verbatim quote
Changeover for new batch 1410 Waiting
- Lost time: 45.0 ton · as reported: “Changeover for new batch”
Show verbatim quote
Average waste Per Month (Ton/Month) 45
- Peningkatan Overall Equipment Effectiveness (OEE) dengan Pendekatan Total Productive Maintenance (TPM) di Line X PT Kraft Ultrajaya Indonesia (2023)Open sourceShare of lost time: 5.00 % · as reported: “Setup and Adjustment”
Show verbatim quote
the loss factors that affect the OEE line X value are Idling and Minor Stoppage with a percentage of 8%, Setup and Adjustment with a percentage of 5%, Defect Amount with a percentage of 4%.
- Application of Lean-Total Productive Maintenance Tools to Reduce Setup Times and Machine Stoppages on the Molding Line of an SME in the Food Industry (2023)Open sourceLost time: 254 min · as reported: “Duration of internal activities”
Show verbatim quote
From the data collection of the total duration of mold change times, a total of 280 minutes on average was obtained, and the times of internal activities, 254 min, and external activities, 26 min.
- Application of Lean-Total Productive Maintenance Tools to Reduce Setup Times and Machine Stoppages on the Molding Line of an SME in the Food Industry (2023)Open sourceLost time: 26.0 min · as reported: “Duration of external activities”
Show verbatim quote
From the data collection of the total duration of mold change times, a total of 280 minutes on average was obtained, and the times of internal activities, 254 min, and external activities, 26 min.
- Application of Lean-Total Productive Maintenance Tools to Reduce Setup Times and Machine Stoppages on the Molding Line of an SME in the Food Industry (2023)Open sourceMean event duration: 280 min · as reported: “mold change”
Show verbatim quote
From the data collection of the total duration of mold change times, a total of 280 minutes on average was obtained
- Application of Lean-Total Productive Maintenance Tools to Reduce Setup Times and Machine Stoppages on the Molding Line of an SME in the Food Industry (2023)Open sourceMean event duration: 254 min · as reported: “internal activities”
Show verbatim quote
the times of internal activities, 254 min, and external activities, 26 min
- Application of Lean-Total Productive Maintenance Tools to Reduce Setup Times and Machine Stoppages on the Molding Line of an SME in the Food Industry (2023)Open sourceMean event duration: 26.0 min · as reported: “external activities”
Show verbatim quote
the times of internal activities, 254 min, and external activities, 26 min
- Analisis Pengukuran Nilai Overall Equipment Effectiveness (OEE) Pada Mesin Rice Milling Unit (RMU) di PT. FSTJ (2023)Open sourceShare of planned time: 2.87 % · as reported: “Setup”
Show verbatim quote
Jika kita lihat total waktu Preventive Maintenance (PM) selama 1.905 menit terhadap waktu operasional yang 65.880 menit atau 2,89% dari waktu operasional dan waktu setup 1,890 menit atau 2,87% dari waktu operasional
- Analisis Pengukuran Nilai Overall Equipment Effectiveness (OEE) Pada Mesin Rice Milling Unit (RMU) di PT. FSTJ (2023)Open sourceLost time: 1,890 min · as reported: “Setup”
Show verbatim quote
Selama rentang waktu tersebut waktu operasional adalah 65.880 menit, preventive maintenance 1.905 menit, setup 1.890 menit dan breakdown 960 menit , maka persen availabilitynya adalah
- Enhancing sustainability in manufacturing: A case study on reducing changeover time through single minute exchange of dies and risk analysis (2024)Open sourceShare of lost time: 35.5 % · as reported: “changeover”
Show verbatim quote
At stations A and B, the results of a post-SMED time analysis showed a reduction in changeover time of 35.54% and 49.94%, respectively.
- Enhancing sustainability in manufacturing: A case study on reducing changeover time through single minute exchange of dies and risk analysis (2024)Open sourceShare of lost time: 49.9 % · as reported: “changeover”
Show verbatim quote
At stations A and B, the results of a post-SMED time analysis showed a reduction in changeover time of 35.54% and 49.94%, respectively.
- Share of planned time: 0 % · as reported: “Setup and adjustment losses”
Show verbatim quote
𝑆𝑒𝑡𝑢𝑝 𝑎𝑛𝑑 𝑎𝑑𝑗𝑢𝑠𝑚𝑒𝑛𝑡 𝑙𝑜𝑠𝑠𝑒𝑠= 0 %
- Mejora de la Eficiencia General de los Equipos (EGE) en la etapa de prensado: Un estudio de caso en la industria de harina de pescado (2024)Open sourceLost time: 112 min · as reported: “cambio de formato”
Show verbatim quote
La duración promedio de un cambio es de 111,9 minutos, lo que representa aproximadamente el 7.79% del tiempo total de producción disponible en un día y puede ocurrir diariamente.
- Mejora de la Eficiencia General de los Equipos (EGE) en la etapa de prensado: Un estudio de caso en la industria de harina de pescado (2024)Open sourceShare of planned time: 7.79 % · as reported: “cambio de formato”
Show verbatim quote
La duración promedio de un cambio es de 111,9 minutos, lo que representa aproximadamente el 7.79% del tiempo total de producción disponible en un día y puede ocurrir diariamente.
- Optimizing Productivity in the Animal Feed Industry: A Lean Approach for Enhanced Efficiency and Quality Assurance (2024)Open sourceLost time: 525 seconds · as reported: “Line preparation time (changeover)”
Show verbatim quote
Line preparation time (seconds) SMED 524.92 140 140.36 -73%
- Optimizing Productivity in the Animal Feed Industry: A Lean Approach for Enhanced Efficiency and Quality Assurance (2024)Open sourceLost time: 140 seconds · as reported: “Line preparation time (changeover)”
Show verbatim quote
Line preparation time (seconds) SMED 524.92 140 140.36 -73%
- Increase of the Availability of Machinery in a Food Company Applying the TPM, SMED and RCM Methodologies (2024)Open sourceNumber of events: 15.0 events · as reported: “Internal activities”
Show verbatim quote
147.54 15 23 63.22 84.32
- Increase of the Availability of Machinery in a Food Company Applying the TPM, SMED and RCM Methodologies (2024)Open sourceNumber of events: 23.0 events · as reported: “External activities”
Show verbatim quote
147.54 15 23 63.22 84.32
- Increase of the Availability of Machinery in a Food Company Applying the TPM, SMED and RCM Methodologies (2024)Open sourceLost time: 63.2 min · as reported: “Internal activities”
Show verbatim quote
147.54 15 23 63.22 84.32
- Increase of the Availability of Machinery in a Food Company Applying the TPM, SMED and RCM Methodologies (2024)Open sourceLost time: 84.3 min · as reported: “External activities”
Show verbatim quote
147.54 15 23 63.22 84.32
- Increase of the Availability of Machinery in a Food Company Applying the TPM, SMED and RCM Methodologies (2024)Open sourceNumber of events: 9.00 events · as reported: “Internal activities”
Show verbatim quote
138.14 9 29 40.72 97.42
- Increase of the Availability of Machinery in a Food Company Applying the TPM, SMED and RCM Methodologies (2024)Open sourceNumber of events: 29.0 events · as reported: “External activities”
Show verbatim quote
138.14 9 29 40.72 97.42
- Increase of the Availability of Machinery in a Food Company Applying the TPM, SMED and RCM Methodologies (2024)Open sourceLost time: 40.7 min · as reported: “Internal activities”
Show verbatim quote
138.14 9 29 40.72 97.42
- Increase of the Availability of Machinery in a Food Company Applying the TPM, SMED and RCM Methodologies (2024)Open sourceLost time: 97.4 min · as reported: “External activities”
Show verbatim quote
138.14 9 29 40.72 97.42
- Increase of the Availability of Machinery in a Food Company Applying the TPM, SMED and RCM Methodologies (2024)Open sourceNumber of events: 25.0 events · as reported: “External activities”
Show verbatim quote
At the end of the activities, a final process time of 105.69 minutes was obtained, with eight internal and 25 external activities, each with a time of 25.62 and 80.07 minutes, respectively.
- Increase of the Availability of Machinery in a Food Company Applying the TPM, SMED and RCM Methodologies (2024)Open sourceLost time: 25.6 min · as reported: “Internal activities”
Show verbatim quote
At the end of the activities, a final process time of 105.69 minutes was obtained, with eight internal and 25 external activities, each with a time of 25.62 and 80.07 minutes, respectively.
- Increase of the Availability of Machinery in a Food Company Applying the TPM, SMED and RCM Methodologies (2024)Open sourceLost time: 80.1 min · as reported: “External activities”
Show verbatim quote
At the end of the activities, a final process time of 105.69 minutes was obtained, with eight internal and 25 external activities, each with a time of 25.62 and 80.07 minutes, respectively.
- Enhancing Operational Efficiency in Craft Beer Production: Implementation of Lean Manufacturing and TPM Methodologies in SMEs (2024)Open sourceMean event duration: 41.0 min · as reported: “setup time”
Show verbatim quote
Setup time was reduced from 41 to 29 minutes, representing a 29% decrease.
- Enhancing Operational Efficiency in Craft Beer Production: Implementation of Lean Manufacturing and TPM Methodologies in SMEs (2024)Open sourceMean event duration: 29.0 min · as reported: “setup time”
Show verbatim quote
Setup time was reduced from 41 to 29 minutes, representing a 29% decrease.
- The implementation of an integrated Lean Management-HACCP model: application in the food industry in Casablanca,Morocco (2025)Open sourceMean event duration: 20.0 min · as reported: “series changeover”
Show verbatim quote
The series changeover time is 20 min .
- The implementation of an integrated Lean Management-HACCP model: application in the food industry in Casablanca,Morocco (2025)Open sourceMean event duration: 10.0 min · as reported: “series changeover”
Show verbatim quote
Series changeover time reduced from 20 min to 10 min
- The implementation of an integrated Lean Management-HACCP model: application in the food industry in Casablanca,Morocco (2025)Open sourceLost time: 20.0 min · as reported: “series changeover”
Show verbatim quote
The series changeover time is 20 min.
- A Lean Manufacturing Case Study: Enhancing Efficiency and Reducing Waste in Latin American Food Production (2024)Open sourceShare of lost time: 13.5 % · as reported: “product fragility”
Show verbatim quote
At the third level, the root causes were further detailed as clogging of cookies in conveyor belt chutes (55%), product fragility (13.5%), inadequate sealing of packaging (11.5%), and conveyor belt failures (20%).
- Share of lost time: 8.90 % · as reported: “size changeovers”
Show verbatim quote
Specifically,label changeovers account for a 16% loss,followed closely by CIP processes at 15% and size changeovers at 8.9%.
- Share of lost time: 40.0 % · as reported: “changeovers”
Show verbatim quote
A notable finding is that changeovers contribute to 40% of the total losses,emphasising the impact of equipment and process adjustments on operational performance.
- Share of lost time: 16.0 % · as reported: “label changeovers”
Show verbatim quote
Specifically,label changeovers account for a 16% loss,followed closely by CIP processes at 15% and size changeovers at 8.9%.
- Number of events: 7,121 events · as reported: “changeovers during liquid filling operations (2017)”
Show verbatim quote
Starting from 7121 changeovers in 2017,there was a steady annual increase,culminating in 15 388 changeovers projected for 2023.
- Number of events: 15,388 events · as reported: “changeovers during liquid filling operations (2023, projected)”
Show verbatim quote
Starting from 7121 changeovers in 2017,there was a steady annual increase,culminating in 15 388 changeovers projected for 2023.
- Lean-TPM Production Model for Efficiency and Quality Enhancement in the Brewing Industry: Insights from a Peruvian Case Study (2025)Open sourceMean event duration: 41.0 min · as reported: “setup time”
Show verbatim quote
Setup time experienced a notable improvement, decreasing by 29%, from 41 to 29 minutes, reflecting substantial optimization in process efficiency.
- Lean-TPM Production Model for Efficiency and Quality Enhancement in the Brewing Industry: Insights from a Peruvian Case Study (2025)Open sourceShare of lost time: 19.8 % · as reported: “extended equipment setup times”
Show verbatim quote
Lastly, process stoppages due to machinery were the most significant factor, with an impact of 46.85%, stemming from extended equipment setup times, which represented 19.84%, suggesting the implementation of the SMED methodology to reduce these delays.
- Lean-TPM Production Model for Efficiency and Quality Enhancement in the Brewing Industry: Insights from a Peruvian Case Study (2025)Open sourceMean event duration: 29.0 min · as reported: “setup time”
Show verbatim quote
Setup time experienced a notable improvement, decreasing by 29%, from 41 to 29 minutes, reflecting substantial optimization in process efficiency.
- Performance Improvement Model Integrating Lean and Internet of things: AFoodProductionCase (2024)Open sourceLost time: 35.0 % · as reported: “setup time”
Show verbatim quote
a 35% decrease in setup time
- Lean Manufacturing: effective tools to optimize dairy beverage production. Evidence based on a statistical analysis. (2025)Open sourceMean event duration: 42.6 min · as reported: “Shift changeover time without Kanban”
Show verbatim quote
Tiempo de cambio sin KANBAN (min) 42,62 8,15 19 %
- Lean Manufacturing: effective tools to optimize dairy beverage production. Evidence based on a statistical analysis. (2025)Open sourceMean event duration: 12.4 min · as reported: “Shift changeover time with Kanban”
Show verbatim quote
Tiempo de cambio con KANBAN (min) 12,43 1,36 11 %
- Aggregate Analysis of Packaging Machine Effectiveness Using the OEE Method at PT. XYZ (2025)Open sourceShare of lost time: 6.00 % · as reported: “Setup and Adjusments Losses”
Show verbatim quote
Setup and Adjusments Losses 2.425 40.410 6% 100%
- Aggregate Analysis of Packaging Machine Effectiveness Using the OEE Method at PT. XYZ (2025)Open sourceLost time: 2,425 Minutes · as reported: “Setup and Adjusments Losses”
Show verbatim quote
Setup and Adjusments Losses 2.425 40.410 6% 100%
- Lost time: 140 min · as reported: “breaks, reference change”
Show verbatim quote
-Planned downtimes: 140 minutes, breaks, reference change, …
- Propuesta para incrementar la disponibilidad de equipos a través de la implementación de Lean Manufacturing e IoT en una industria de galletas (2025)Open sourceNumber of events: 731 events · as reported: “Elevados tiempos de setup”
Show verbatim quote
AS IS 731 52,802 72.24 23.3% TO BE 408 22,606 55.41
- Propuesta para incrementar la disponibilidad de equipos a través de la implementación de Lean Manufacturing e IoT en una industria de galletas (2025)Open sourceLost time: 22,606 min · as reported: “Elevados tiempos de setup”
Show verbatim quote
AS IS 731 52,802 72.24 23.3% TO BE 408 22,606 55.41
- Propuesta para incrementar la disponibilidad de equipos a través de la implementación de Lean Manufacturing e IoT en una industria de galletas (2025)Open sourceNumber of events: 408 events · as reported: “Elevados tiempos de setup”
Show verbatim quote
AS IS 731 52,802 72.24 23.3% TO BE 408 22,606 55.41
- Propuesta para incrementar la disponibilidad de equipos a través de la implementación de Lean Manufacturing e IoT en una industria de galletas (2025)Open sourceMean event duration: 55.4 min · as reported: “Elevados tiempos de setup”
Show verbatim quote
AS IS 731 52,802 72.24 23.3% TO BE 408 22,606 55.41
- Propuesta para incrementar la disponibilidad de equipos a través de la implementación de Lean Manufacturing e IoT en una industria de galletas (2025)Open sourceLost time: 52,802 min · as reported: “Elevados tiempos de setup”
Show verbatim quote
AS IS 731 52,802 72.24 23.3% TO BE 408 22,606 55.41
- Propuesta para incrementar la disponibilidad de equipos a través de la implementación de Lean Manufacturing e IoT en una industria de galletas (2025)Open sourceMean event duration: 72.2 min · as reported: “Elevados tiempos de setup”
Show verbatim quote
AS IS 731 52,802 72.24 23.3% TO BE 408 22,606 55.41
- Propuesta para incrementar la disponibilidad de equipos a través de la implementación de Lean Manufacturing e IoT en una industria de galletas (2025)Open sourceLost time: 0 min · as reported: “Cambio de Programación”
Show verbatim quote
Cambio de Programación 0 0.00% S/ -
- Propuesta para incrementar la disponibilidad de equipos a través de la implementación de Lean Manufacturing e IoT en una industria de galletas (2025)Open sourceShare of lost time: 185 % · as reported: “Elevados tiempos de setup”
Show verbatim quote
Elevados tiempos de setup 52,802 184.900% S/2,375,887.99
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceShare of lost time: 23.3 % · as reported: “cambios de formato”
Show verbatim quote
los motivos son las averías / reparaciones, reprocesos, cambios de formato y otros donde estas representan el 41.1%, 35.7% y 23.3% respectivamente
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceMean event duration: 26.0 min · as reported: “cambio de formato”
Show verbatim quote
La variación del tiempo del Set – up a lo largo del año es en promedio de 26 minutos siendo el objetivo de 19 minutos
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceNumber of events: 278 events · as reported: “cambio de formato”
Show verbatim quote
con respecto a las 278 paradas de cambio de formato hace una demora anual de 1946 minutos
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceShare of planned time: 4.24 % · as reported: “Cambios de formato”
Show verbatim quote
Cambios de formato 4,24%
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceMean event duration: 19.5 min · as reported: “cambio de formato”
Show verbatim quote
Tiempo de Set Up 26 min 19,5 min 19,00 min
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceShare of planned time: 1.50 % · as reported: “Cambios de formato”
Show verbatim quote
Cambios de formato 1,50% REDUCIDO
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceMean event duration: 19.5 min · as reported: “cambio de formato”
Show verbatim quote
donde el promedio del cambio de formato es de 19.53 minutos
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceLost time: 26.0 min · as reported: “Cambio de formato”
Show verbatim quote
La variación del tiempo del Set – up a lo largo del año es en promedio de 26 minutos
- Proposal for improvement to increase the overall equipment effectiveness (OEE) of a dairy products company through a Preventive Maintenance Plan, Standardized Work, and SMED (2025)Open sourceLost time: 19.5 min · as reported: “Cambio de formato”
Show verbatim quote
Tiempo de Set Up 26 min → 19,5 min
- Share of lost time: 42.0 % · as reported: “setup and adjustment loss”
Show verbatim quote
The Six Big Losses analysis showed that the largest losses came from setup and adjustment losses, accounting for 42%.
- Share of lost time: 42.0 % · as reported: “setup and adjustment loss”
Show verbatim quote
The Six Big Losses analysis showed that the largest losses came from setup and adjustment losses, accounting for 42%
- Propuesta de mejora para incrementar el rendimiento de la línea de salsas usando SMED, Kanban, Industria 4.0 y 5S en una empresa del sector alimenticio (2026)Open sourceShare of lost time: 39.9 % · as reported: “Demoras por cambios de Formato”
Show verbatim quote
Demoras por cambios de Formato 9262.27 39.85% 39.85%
- Propuesta de mejora para incrementar el rendimiento de la línea de salsas usando SMED, Kanban, Industria 4.0 y 5S en una empresa del sector alimenticio (2026)Open sourceLost time: 9,262 min · as reported: “Demoras por cambios de Formato”
Show verbatim quote
Demoras por cambios de Formato 9262.27 39.85% 39.85%
- Propuesta de mejora para incrementar el rendimiento de la línea de salsas usando SMED, Kanban, Industria 4.0 y 5S en una empresa del sector alimenticio (2026)Open sourceMean event duration: 3.20 h · as reported: “cambio de producto”
Show verbatim quote
Setup inicial (horas) 3.20 3.20 3.20 3.20 3.20 3.20
- Propuesta de mejora para incrementar el rendimiento de la línea de salsas usando SMED, Kanban, Industria 4.0 y 5S en una empresa del sector alimenticio (2026)Open sourceMean event duration: 0.630 h · as reported: “cambio de presentación”
Show verbatim quote
Setup inicial (horas) 0.63 0.63 0.63 0.63 0.63 0.63
- Propuesta de mejora para incrementar el rendimiento de la línea de salsas usando SMED, Kanban, Industria 4.0 y 5S en una empresa del sector alimenticio (2026)Open sourceNumber of events: 52.0 events/year · as reported: “cambio de producto”
Show verbatim quote
Cambio de producto / año 52 55 57 60 63 66
- Propuesta de mejora para incrementar el rendimiento de la línea de salsas usando SMED, Kanban, Industria 4.0 y 5S en una empresa del sector alimenticio (2026)Open sourceNumber of events: 208 events/year · as reported: “cambio de presentación”
Show verbatim quote
Cambio de presentación / año 208 218 229 241 253 265
- Propuesta de mejora para incrementar el rendimiento de la línea de salsas usando SMED, Kanban, Industria 4.0 y 5S en una empresa del sector alimenticio (2026)Open sourceMean event duration: 1.99 h · as reported: “cambio de producto”
Show verbatim quote
Tiempo setup logrado (horas) 1.99 1.99 1.92 1.92 1.92 1.92
- Propuesta de mejora para incrementar el rendimiento de la línea de salsas usando SMED, Kanban, Industria 4.0 y 5S en una empresa del sector alimenticio (2026)Open sourceMean event duration: 0.440 h · as reported: “cambio de presentación”
Show verbatim quote
Tiempo setup logrado (horas) 0.44 0.44 0.38 0.38 0.38 0.38
- Productivity Improvement Through the Application of Lean Six Sigma Tools in a Non-Alcoholic Beverage Company (2025)Open sourceLost time: 16,800 min/year · as reported: “format changeover (Set Up)”
Show verbatim quote
A total of 16,800 minutes per year associated with format changeover (Set Up) were identified, equivalent to 10.45% of productive time.
- Productivity Improvement Through the Application of Lean Six Sigma Tools in a Non-Alcoholic Beverage Company (2025)Open sourceShare of planned time: 10.5 % · as reported: “format changeover (Set Up)”
Show verbatim quote
A total of 16,800 minutes per year associated with format changeover (Set Up) were identified, equivalent to 10.45% of productive time.
- Reducing Changeover Time Through SMED Methodology: A Review and Case Application in Beverage Bottling (2026)Open sourceLost time: 28.0 min · as reported: “product changeover”
Show verbatim quote
The intervention reduced average changeover time from 40 minutes to approximately 28 minutes - a 30% reduction
- Reducing Changeover Time Through SMED Methodology: A Review and Case Application in Beverage Bottling (2026)Open sourceLost time: 40.0 min · as reported: “product changeover”
Show verbatim quote
The intervention reduced average changeover time from 40 minutes to approximately 28 minutes - a 30% reduction
- Impact evaluation of operator training on the understanding of performance indicators (2025)Open sourceMean event duration: 9.00 min · as reported: “setup time”
Show verbatim quote
a 16.7% reduction in average setup time was observed (from 10.8 to 9.0 minutes)
- Impact evaluation of operator training on the understanding of performance indicators (2025)Open sourceMean event duration: 10.8 min · as reported: “setup time”
Show verbatim quote
a 16.7% reduction in average setup time was observed (from 10.8 to 9.0 minutes)
- Lost time: 360 min · as reported: “setup time”
Show verbatim quote
The objective is to achieve a significant reduction in setup time, from 360 to 240 minutes, representing a decrease of approximately 33.33%.
- Share of lost time: 4.10 % · as reported: “setup time”
Show verbatim quote
reducing the impact on production stoppages from 4.1% to 3%, as well as practical and applicable recommendations for managers and professionals in the chocolate industry.
- Lost time: 240 min · as reported: “setup time”
Show verbatim quote
The objective is to achieve a significant reduction in setup time, from 360 to 240 minutes, representing a decrease of approximately 33.33%.
- Share of lost time: 3.00 % · as reported: “setup time”
Show verbatim quote
reducing the impact on production stoppages from 4.1% to 3%, as well as practical and applicable recommendations for managers and professionals in the chocolate industry.
- Productivity Improvement in a Bakery and Pastry Premix Company by Applying Preventive Maintenance, SMED and 5´S (2026)Open sourceMean event duration: 24.9 min · as reported: “Changeover (SKU average)”
Show verbatim quote
1 - 5 24.91 16.66 33.1%
- Productivity Improvement in a Bakery and Pastry Premix Company by Applying Preventive Maintenance, SMED and 5´S (2026)Open sourceMean event duration: 16.7 min · as reported: “Changeover (SKU average)”
Show verbatim quote
1 - 5 24.91 16.66 33.1%
- Waste Management and Operational Efficiency Improvement in Cake and Pastry Factory Through Adapting DMAIC Methodology (2026)Open sourceShare of planned time: 9.77 % · as reported: “changeover time”
Show verbatim quote
Changeover activities during January 2025 consumed 66.63 hours, which accounted for 9.77% of total production time, a relatively high percentage attributed to the product variety.
- Waste Management and Operational Efficiency Improvement in Cake and Pastry Factory Through Adapting DMAIC Methodology (2026)Open sourceLost time: 66.6 h · as reported: “changeover time”
Show verbatim quote
Changeover activities during January 2025 consumed 66.63 hours, which accounted for 9.77% of total production time, a relatively high percentage attributed to the product variety.
- Analisis Overall Equipment Effectiveness dan Six Big Losses pada Mesin Packaging Makanan di PT XYZ (2026)Open sourceShare of lost time: 11.8 % · as reported: “Setup and Adjustment Losses”
Show verbatim quote
Kegagalan karena Setup and Adjustment Losses 31,20 11,82 Sedang
- Analisis Overall Equipment Effectiveness dan Six Big Losses pada Mesin Packaging Makanan di PT XYZ (2026)Open sourceLost time: 31.2 Jam · as reported: “Setup and Adjustment Losses”
Show verbatim quote
Kegagalan karena Setup and Adjustment Losses 31,20 11,82 Sedang
- Improvement proposal to increase machine availability in yogurt packaging by applying TPM tools autonomous, planned and SMED maintenance in a food industry company (2026)Open sourceLost time: 90.0 min · as reported: “tiempo de cambio de formato”
Show verbatim quote
el tiempo de cambio de formato disminuyó de 90 a 55 minutos (-38.89%) mediante la aplicación de SMED
- Improvement proposal to increase machine availability in yogurt packaging by applying TPM tools autonomous, planned and SMED maintenance in a food industry company (2026)Open sourceMean event duration: 90.0 min · as reported: “format change”
Show verbatim quote
el tiempo de cambio de formato disminuyó de 90 a 55 minutos
- Proposal for improving production efficiency in a food sector company, using SMED, Planned Maintenance and Poka-Yoke (2026)Open sourceShare of lost time: 17.4 % · as reported: “high setup times”
Show verbatim quote
Esta situación fue originada por cuatro causas raíz: averías en equipos (35.41%), elevados tiempos de setup (17.38%), producto final golpeado (32.69%) y etiquetado incorrecto (14.52%)
- Proposal for improving production efficiency in a food sector company, using SMED, Planned Maintenance and Poka-Yoke (2026)Open sourceShare of lost time: 32.7 % · as reported: “damaged final product”
Show verbatim quote
Esta situación fue originada por cuatro causas raíz: averías en equipos (35.41%), elevados tiempos de setup (17.38%), producto final golpeado (32.69%) y etiquetado incorrecto (14.52%)
- Integrating SMED and Mechanical Design for Changeover Reduction in Beverage Packaging Lines (2026)Open sourceShare of planned time: 7.20 % · as reported: “Changeover Time (COT) and Ramp-Up Time (RUT)”
Show verbatim quote
Although breakdown and malfunction losses (18.04%) are greater in aggregate than changeover and ramp-up losses (≈7.2%), they are not the focus of this study.
- Mean event duration: 136 min · as reported: “cambio de formato (tiempo por ciclo)”
Show verbatim quote
reduciendo, en promedio, los tiempos de parada rutinarias de 136 min por ciclo del proceso de llenado en el pretest a 21 min después de la implementación
- Mean event duration: 22.0 min · as reported: “tiempo de cambio de setup (gráfica de control)”
Show verbatim quote
El tiempo promedio de cambio de setup se estabilizó en un valor central de 21.988, manteniéndose alejado de los límites de control superior (36.056) e inferior (7.921).
- Lost time: 3,341 min · as reported: “cambio de formato”
Show verbatim quote
La mejora buscó reducir las paradas asociados con los 59 cambios de formato en la presentación de 3,030 ml que totalizó 3,341 minutos el año 2023 equivalentes al 46.91% del porcentaje total de paradas
- Share of lost time: 46.9 % · as reported: “cambio de formato”
Show verbatim quote
La mejora buscó reducir las paradas asociados con los 59 cambios de formato en la presentación de 3,030 ml que totalizó 3,341 minutos el año 2023 equivalentes al 46.91% del porcentaje total de paradas
- Number of events: 59.0 events · as reported: “cambio de formato”
Show verbatim quote
La mejora buscó reducir las paradas asociados con los 59 cambios de formato en la presentación de 3,030 ml que totalizó 3,341 minutos el año 2023
- Mean event duration: 64.0 min · as reported: “cambio de formato (llenadora)”
Show verbatim quote
La toma de tiempos identificó a la llenadora como el equipo cuyo cambio de formato tomaba en promedio 64 minutos siendo el equipo crítico en la línea de producción
- Mean event duration: 21.0 min · as reported: “cambio de formato (tiempo por ciclo)”
Show verbatim quote
reduciendo, en promedio, los tiempos de parada rutinarias de 136 min por ciclo del proceso de llenado en el pretest a 21 min después de la implementación
- Share of planned time: 9.06 % · as reported: “cambios de formato”
Show verbatim quote
los estimados porcentuales de tiempos estándar respecto al tiempo total del proceso fue de 9.06% para las paradas rutinarias y 90.94% para el proceso de embotellado
- Share of planned time: 6.90 % · as reported: “cambios de formato”
Show verbatim quote
La reducción del tiempo estándar por la reducción en los tiempos de cambios de formato pasó a representar el 6.9%, del tiempo total
- Melhoria do Indicador OEE em Linhas de Enchimento e Embalamento de Óleos e Azeites (2025)Open sourceLost time: 10.0 horas · as reported: “tempo de setup”
Show verbatim quote
Numa linha automática aplica-se a metodologia SMED, que permitiu reduzir o tempo de setup em 50 por cento, correspondendo a cerca de 10 horas de capacidade libertada num único mês.
- Розроблення заходів операційного вдосконалення виробничих процесів виготовлення вермішелі швидкого приготування “Reeva зі смаком гострої курки” для оператора ринку ТОВ «Евро Фуд Сервіс» (2025)Open sourceMean event duration: 2,100 с · as reported: “розгінна фаза (Setup Time) виробництва після зупинки та запуску із холодного старту”
Show verbatim quote
Особливе значення має розгінна фаза (Setup Time) виробництва після зупинки та запуску із холодного старту, вона триває в середньому 2 100 секунд (35 хвилин) (Табл 3.3).
- Enterprise Resource Planning System Integrated with Overall Equipment Effectiveness for Enhanced Performance Tracking Metrics: Mixed-Methods Case Study of a Nigerian Feed Mill (2026)Open sourceShare of lost time: 2.59 % · as reported: “Production change”
Show verbatim quote
5 Production change 34.76 2.59 100.00 Trivial many
- Enterprise Resource Planning System Integrated with Overall Equipment Effectiveness for Enhanced Performance Tracking Metrics: Mixed-Methods Case Study of a Nigerian Feed Mill (2026)Open sourceLost time: 34.8 hrs · as reported: “Production change”
Show verbatim quote
5 Production change 34.76 2.59 100.00 Trivial many
- Lost time: 2.43 hrs per production cycle · as reported: “set up time”
Show verbatim quote
the improved processes can reduce set up time from 6.90 hrs per production cycle to 2.43 hrs per production cycle or about 64.78%
- Lost time: 6.90 hrs per production cycle · as reported: “set up time”
Show verbatim quote
the improved processes can reduce set up time from 6.90 hrs per production cycle to 2.43 hrs per production cycle or about 64.78%
- Integrasi OEE–Pareto–FMEA–Ishikawa untuk Peningkatan Efektivitas Mesin dan Mutu Kemasan Kecap Pouch 550 mL: Integrated OEE–Pareto–FMEA–Ishikawa Approach for Improving Machine Effectiveness and Packaging Quality of 550 mL Soy Sauce Pouch (2026)Open sourceShare of lost time: 19.0 % · as reported: “Setup and adjustment loss”
Show verbatim quote
Setup and adjustment loss 19