Capping/seaming line changeover

Setup and adjustmentsAvailabilityCapping and seaming

In short

It appears in about 1 of every 100 lines studied.

When it appears, it takes on average about 57 % of the line's lost time. Reported by 1 of the 82 studies that could observe it (sparse evidence).

What happens

When the can size, lid type or seaming profile changes, the capping or seaming machine must be mechanically reconfigured: chucks, seaming rolls, lifter plates, guide rails and sealing heads are swapped or re-set to the new container geometry. This reconfiguration, together with the trial adjustments needed to reach a correct seam, stops production for the duration of the changeover, and the loss grows when changeovers recur frequently due to small batch sizes or mixed production schedules.

What is done about it

Apply SMED-style standardization: pre-stage and pre-adjust format-specific tooling (chucks, rolls, guides) offline, use quick-release fixtures, and sequence production runs by container family to reduce the number and duration of changeovers.

Practical guidance written from engineering knowledge; it is not a statistical estimate.

1Probability and evidence

Pooled over all segments. A wide interval is a result: it states how much the evidence allows us to know.
Probability of presence
0.6% [0.1–1.7%]
Expected share of lost time
0.3% [0.1–1.0%]
Share of lost time when present
57% [45–68%]
Studies / units
82 / 109
Evidence grade
D

Grade D: 0 or 1 study; the estimate is driven by partial pooling and priors, and the wide interval is the result.

2Probability by segment

Partially pooled estimates for each industry segment.
  • Dairy products
    0.7% [0.1–2.5%]11 studies
  • Soft drinks, bottled water and juices
    0.6% [0.1–2.1%]26 studies
  • Brewing, wine and spirits
    0.7% [0.1–2.5%]11 studies
  • Bakery and pasta
    0.7% [0.1–3.0%]0 studies
  • Meat, poultry and seafood
    1.0% [0.1–3.7%]7 studies
  • Fruit and vegetable processing
    0.7% [0.1–2.6%]4 studies
  • Grain and oilseed milling
    0.7% [0.1–2.8%]3 studies
  • Sugar and confectionery
    0.7% [0.1–2.8%]3 studies
  • Snacks, coffee, tea and other foods
    0.7% [0.1–2.7%]4 studies
  • Animal feed and pet food
    0.7% [0.1–3.0%]4 studies
  • Food manufacturing (unspecified or mixed)
    0.7% [0.1–2.6%]9 studies

3Mechanism, SCADA signature and countermeasure

Engineering guidance that helps recognise and address the cause; it is not part of the statistical estimate.

Mechanism

Engineering guidance

When the can size, lid type or seaming profile changes, the capping or seaming machine must be mechanically reconfigured: chucks, seaming rolls, lifter plates, guide rails and sealing heads are swapped or re-set to the new container geometry. This reconfiguration, together with the trial adjustments needed to reach a correct seam, stops production for the duration of the changeover, and the loss grows when changeovers recur frequently due to small batch sizes or mixed production schedules.

How it looks in SCADA data

Engineering guidance

MES/SCADA logs show the capping-seaming station entering a setup or changeover state with capping head and seam counters frozen at zero, upstream filler and downstream labeler accumulating idle or starved/blocked states, and repeated short-cycle setup events clustering around shift or batch boundaries when changeovers are frequent.

Countermeasure

Engineering guidance

Apply SMED-style standardization: pre-stage and pre-adjust format-specific tooling (chucks, rolls, guides) offline, use quick-release fixtures, and sequence production runs by container family to reduce the number and duration of changeovers.

4Sources

Every extracted datum with its study, value and verbatim quote.
  1. Lost time: 3.00 min · as reported: “Apertar fixação da capsuladora”
    Show verbatim quote
    19 Apertar fixação da capsuladora 3 1
  2. Lost time: 15.0 min · as reported: “Mudar e transportar guias da capsuladora”
    Show verbatim quote
    8, 15, 19 Mudar e transportar guias da capsuladora 15 6
  3. Lost time: 43.0 min · as reported: “Mudar e transportar pistões de capsulagem”
    Show verbatim quote
    9, 12 Mudar e transportar pistões de capsulagem 43 20
  4. Lost time: 57.0 min · as reported: “Resolução de parafuso moído no pistão”
    Show verbatim quote
    14, 16 Resolução de parafuso moído no pistão 57 0
  5. Lost time: 2.00 min · as reported: “Retirar pistão que o operador B se enganou a montar”
    Show verbatim quote
    17 Retirar pistão que o operador B se enganou a montar 2 0
  6. Lost time: 1.00 min · as reported: “Apertar fixação da capsuladora”
    Show verbatim quote
    19 Apertar fixação da capsuladora 3 1
  7. Lost time: 6.00 min · as reported: “Mudar e transportar guias da capsuladora”
    Show verbatim quote
    8, 15, 19 Mudar e transportar guias da capsuladora 15 6
  8. Lost time: 20.0 min · as reported: “Mudar e transportar pistões de capsulagem”
    Show verbatim quote
    9, 12 Mudar e transportar pistões de capsulagem 43 20
  9. Lost time: 0 min · as reported: “Resolução de parafuso moído no pistão”
    Show verbatim quote
    14, 16 Resolução de parafuso moído no pistão 57 0
  10. Lost time: 0 min · as reported: “Retirar pistão que o operador B se enganou a montar”
    Show verbatim quote
    17 Retirar pistão que o operador B se enganou a montar 2 0
  11. Mean event duration: 8.00 мин · as reported: “переналадка линии укупорки консервов”
    Show verbatim quote
    Эти меры привели к снижению времени одной переналадки с 10 до 8 минут (на 20%) и уменьшению на 17% количества переналадок за смену
  12. Lost time: 1.00 час · as reported: “частая переналадка линии укупорки консервов”
    Show verbatim quote
    Анализ потока создания ценности выявил значительные потери времени (1 час в смену) из-за частой переналадки линии укупорки консервов, вызванной большим ассортиментом продукции.
  13. Mean event duration: 10.0 мин · as reported: “переналадка линии укупорки консервов”
    Show verbatim quote
    Эти меры привели к снижению времени одной переналадки с 10 до 8 минут (на 20%) и уменьшению на 17% количества переналадок за смену