In short
It appears in about 1 of every 100 lines studied.
When it appears, it takes on average about 57 % of the line's lost time. Reported by 1 of the 86 studies that could observe it (sparse evidence).
What happens
As part of a product or format changeover, conveyors and accumulation tables must be stopped, emptied and cleaned (removing spilled product, residue or debris) before the next run can start, taking the line out of production. This cleaning step is planned work tied to the changeover rather than a failure, but it consumes time between the last good unit of one run and the first good unit of the next.
What is done about it
Standardize and simplify conveyor cleaning procedures (quick-release guards, accessible wash points, dedicated cleaning tools) and integrate them into a structured changeover sequence (SMED) so cleaning tasks run in parallel with other setup activities rather than sequentially.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 0.6% [0.1–1.7%]
- Expected share of lost time
- 0.3% [0.1–1.0%]
- Share of lost time when present
- 57% [45–67%]
- Studies / units
- 86 / 112
- Evidence grade
- D
Grade D: 0 or 1 study; the estimate is driven by partial pooling and priors, and the wide interval is the result.
2Probability by segment
- Dairy products0.7% [0.1–2.5%]11 studies
- Soft drinks, bottled water and juices0.6% [0.1–2.1%]28 studies
- Brewing, wine and spirits0.7% [0.1–2.4%]12 studies
- Bakery and pasta0.7% [0.1–2.7%]0 studies
- Meat, poultry and seafood0.7% [0.1–2.5%]5 studies
- Fruit and vegetable processing0.7% [0.1–2.9%]4 studies
- Grain and oilseed milling0.7% [0.1–2.7%]4 studies
- Sugar and confectionery0.7% [0.1–2.9%]4 studies
- Snacks, coffee, tea and other foods1.0% [0.1–3.7%]4 studies
- Animal feed and pet food0.7% [0.1–2.8%]5 studies
- Food manufacturing (unspecified or mixed)0.7% [0.1–2.5%]9 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceAs part of a product or format changeover, conveyors and accumulation tables must be stopped, emptied and cleaned (removing spilled product, residue or debris) before the next run can start, taking the line out of production. This cleaning step is planned work tied to the changeover rather than a failure, but it consumes time between the last good unit of one run and the first good unit of the next.
How it looks in SCADA data
Engineering guidanceSCADA/MES shows the conveyor or line in a changeover/cleaning state with motors stopped and zero product counts for an extended, recurring interval that coincides with scheduled changeover events; upstream and downstream equipment show matching idle or standby states rather than fault alarms.
Countermeasure
Engineering guidanceStandardize and simplify conveyor cleaning procedures (quick-release guards, accessible wash points, dedicated cleaning tools) and integrate them into a structured changeover sequence (SMED) so cleaning tasks run in parallel with other setup activities rather than sequentially.
4Sources
- Investigation on a multiscale sustainable manufacturing approach to production changeover complexity reduction and its implementation through smart surfaces and process optimization (2022)Open sourceLost time: 60.0 min · as reported: “Storage conveyor cleaning”
Show verbatim quote
Storage conveyor cleaning 60 minutes
- Investigation on a multiscale sustainable manufacturing approach to production changeover complexity reduction and its implementation through smart surfaces and process optimization (2022)Open sourceLost time: 324 min · as reported: “Cleaning of conveyors”
Show verbatim quote
Cleaning of conveyors 324 minutes