Manual transfer of product trays to cold storage
In short
It appears in fewer than 1 of every 100 lines studied.
When it appears, it takes on average about 57 % of the line's lost time. Reported by 1 of the 127 studies that could observe it (sparse evidence).
What happens
At the end of a run or during a changeover, operators must physically move trays of finished or semi-finished product from the line to the cold storage area before the next production step or format can start. This manual material-handling task is on the critical path of the transition and adds non-value-adding time to the changeover.
What is done about it
Decouple the tray transfer from the critical changeover path by assigning dedicated logistics personnel or using conveyors, carts or AGVs that can move product to cold storage in parallel with other setup tasks, and standardize the handover sequence so the line can start the next step without waiting for storage to be cleared.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 0.5% [0.1–1.3%]
- Expected share of lost time
- 0.3% [0.1–0.7%]
- Share of lost time when present
- 57% [45–67%]
- Studies / units
- 127 / 161
- Evidence grade
- D
Grade D: 0 or 1 study; the estimate is driven by partial pooling and priors, and the wide interval is the result.
2Probability by segment
- Dairy products0.6% [0.1–2.1%]13 studies
- Soft drinks, bottled water and juices0.5% [0.1–1.7%]26 studies
- Brewing, wine and spirits0.6% [0.1–2.0%]11 studies
- Bakery and pasta0.5% [0.1–1.9%]24 studies
- Meat, poultry and seafood0.6% [0.1–2.1%]9 studies
- Fruit and vegetable processing0.6% [0.1–2.3%]7 studies
- Grain and oilseed milling0.6% [0.1–2.2%]6 studies
- Sugar and confectionery0.6% [0.1–2.2%]9 studies
- Snacks, coffee, tea and other foods0.6% [0.1–2.1%]5 studies
- Animal feed and pet food0.8% [0.1–3.0%]7 studies
- Food manufacturing (unspecified or mixed)0.6% [0.1–2.0%]10 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceAt the end of a run or during a changeover, operators must physically move trays of finished or semi-finished product from the line to the cold storage area before the next production step or format can start. This manual material-handling task is on the critical path of the transition and adds non-value-adding time to the changeover.
How it looks in SCADA data
Engineering guidanceThe line remains in a changeover or idle state for longer than the logged machine-level setup activities would explain, with no equipment fault or alarm recorded; operator or MES event logs show a manual transfer or logistics task bridging the gap between last-good-unit and first-good-unit timestamps.
Countermeasure
Engineering guidanceDecouple the tray transfer from the critical changeover path by assigning dedicated logistics personnel or using conveyors, carts or AGVs that can move product to cold storage in parallel with other setup tasks, and standardize the handover sequence so the line can start the next step without waiting for storage to be cleared.
4Sources
- Production Management Model Based on Lean Manufacturing Tools and SLP to Increase Productivity in a Meatball (BARF) Plant (2026)Open sourceMean event duration: 4.58 min · as reported: “Move trays to cold storage”
Show verbatim quote
Move trays to cold storage 4.58 Internal Internal
- Production Management Model Based on Lean Manufacturing Tools and SLP to Increase Productivity in a Meatball (BARF) Plant (2026)Open sourceLost time: 4.58 min · as reported: “Move trays to cold storage”
Show verbatim quote
Move trays to cold storage 4.58