Raw material supply interruption causing filler readjustment
In short
It appears in about 1 of every 100 lines studied.
When it appears, it takes on average about 57 % of the line's lost time. Reported by 1 of the 120 studies that could observe it (sparse evidence).
What happens
An upstream break or shortfall in the flow of product to be filled (raw material, bulk product, or component) halts the vacuum filler; once supply resumes, the equipment has to be readjusted (vacuum level, dosing parameters, nozzle timing) before stable filling can continue. The stoppage itself originates outside the filler, but the recovery requires a manual equipment adjustment.
What is done about it
Maintain buffer stock or intermediate storage of the material feeding the filler, improve coordination and scheduling with upstream suppliers or processes, and implement standardized restart procedures with pre-set parameters to shorten the readjustment time after a supply break.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 0.6% [0.1–1.6%]
- Expected share of lost time
- 0.3% [0.1–0.9%]
- Share of lost time when present
- 57% [45–67%]
- Studies / units
- 120 / 162
- Evidence grade
- D
Grade D: 0 or 1 study; the estimate is driven by partial pooling and priors, and the wide interval is the result.
2Probability by segment
- Dairy products0.6% [0.1–2.3%]18 studies
- Soft drinks, bottled water and juices0.5% [0.1–1.8%]44 studies
- Brewing, wine and spirits0.6% [0.1–2.3%]16 studies
- Bakery and pasta0.7% [0.1–2.8%]0 studies
- Meat, poultry and seafood1.0% [0.1–3.7%]6 studies
- Fruit and vegetable processing0.7% [0.1–2.6%]4 studies
- Grain and oilseed milling0.7% [0.1–2.5%]6 studies
- Sugar and confectionery0.7% [0.1–2.5%]3 studies
- Snacks, coffee, tea and other foods0.7% [0.1–2.5%]6 studies
- Animal feed and pet food0.7% [0.1–2.6%]4 studies
- Food manufacturing (unspecified or mixed)0.6% [0.1–2.4%]13 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceAn upstream break or shortfall in the flow of product to be filled (raw material, bulk product, or component) halts the vacuum filler; once supply resumes, the equipment has to be readjusted (vacuum level, dosing parameters, nozzle timing) before stable filling can continue. The stoppage itself originates outside the filler, but the recovery requires a manual equipment adjustment.
How it looks in SCADA data
Engineering guidanceUpstream flow or level sensors show loss of material feed while the filler state transitions to idle or starved; the stop is followed by an extended non-production interval during which setpoints are modified and the machine cycles through manual or adjustment mode before returning to automatic run. Repeated short runs with parameter changes logged around each restart are typical.
Countermeasure
Engineering guidanceMaintain buffer stock or intermediate storage of the material feeding the filler, improve coordination and scheduling with upstream suppliers or processes, and implement standardized restart procedures with pre-set parameters to shorten the readjustment time after a supply break.
4Sources
- Lost time: 82.0 min · as reported: “Readjustment of equipment; Interruptions in the supply of raw materials”
Show verbatim quote
Downtime (Dt) – ПР = 82 min.: Readjustment of equipment; Interruptions in the supply of raw materials.