Filling
Rotary isobaric (counter-pressure) gravity filling of beverages into bottles
In short
Filling can use at most 99 of every 100 planned hours. The rest goes to limits no plant can avoid.
- 99usable at most
- 1are a physical limit
The three limits that set it
Running time: up to 99 %
The rest are stops imposed by physics or by regulation: cleaning, changeovers, defrosting.
Speed: up to 100 %
How close to its maximum speed it can run without damaging the product or the equipment.
Good product: up to 100 %
Some product falls outside specification even with the process well under control.
Technical detail
Uncertainty intervals, physical models per station and sources, for anyone who wants to check each figure.
1Scenario
A carbonated soft drink is filled into 0.5 L PET bottles on a rotary filler with N valves. At each valve the bottle is pressed against the valve, pressurised with CO2 from the bowl head-space, filled by gravity while the displaced gas returns to the bowl, and decompressed to atmosphere through a snift orifice before it leaves the carousel. The fill volume is set by the level of the return-gas tube (level filling). With zero carbonation the same model describes a still liquid filled by gravity at atmospheric pressure.
2Results
- Tolerable negative error (tolerable deficiency) T for the nominal quantity15.0 mL
- Minimum target mean fill that satisfies the prepackage rules502.6 [501.4–505.1] mL
- Give-away per bottle (target mean minus nominal quantity)2.58 [1.38–5.05] mL
- Give-away as a share of the nominal quantity0.00515 [0.00277–0.01010]
- Capability index of the fill volume against the lower limit Qn - T2.93 [1.49–5.65]
- Largest fill standard deviation for which the average requirement alone binds (T / z for the T1 share)7.65 mL
- Share of bottles with a T1 error at the target mean7.61 × 10⁻¹⁹ [1.17 × 10⁻⁶⁴–4.03 × 10⁻⁶]
- Share of bottles rejected for a T2 error (below Qn - 2T)6.00 × 10⁻⁶⁰ [2.77 × 10⁻²⁰⁸–2.93 × 10⁻¹⁷]
- TheoreticalMaximum yield: nominal volume sold per volume filled (give-away and T2 rejects)0.9949 [0.9900–0.9972]
- Best documentedYield including the documented product loss per changeover of a traditional filling operation0.9948 [0.9899–0.9971]
- TheoreticalMaximum OEE quality factor (bottles without a T2 error)1.00
- Equilibrium CO2 pressure of the product at the filling temperature (Henry's law)2.46 [1.70–3.26] bar
- Counter-pressure (absolute) used for filling3.46 [2.54–4.83] bar
- Minimum work to lift the liquid to the filler bowl0.0196 [0.0105–0.0385] kJ/kg
- Minimum (isothermal) work to compress the counter-pressure gas vented at the snift0.0223 [0.0104–0.0447] kJ/kg
- TheoreticalThermodynamic minimum work of filling (lift + vented counter-pressure gas)0.0419 [0.0269–0.0746] kJ/kg
- Free liquid area of the neck (bore minus gas-return tube)342 [292–375] mm²
- Minimum pressurisation time of the bottle (ideal nozzle, adiabatic charging)0.0817 [0.0465–0.1781] s
- Minimum liquid fill time (Torricelli discharge, discharge coefficient 1)0.525 [0.417–0.699] s
- Minimum snift (head-space blowdown) time through the snift orifice0.267 [0.093–0.784] s
- TheoreticalMinimum valve process time (pressurise + fill + snift)0.874 [0.651–1.438] s
- TypicalValve process time with throttled liquid flow, real nozzles, controlled snift and valve actuation (declared scenario)3.10 [2.28–5.03] s
- Maximum bottles per hour per valve (physics minimum times)3,089 [1,837–4,287] 1/h
- TheoreticalMaximum bottles per hour of the rotary filler (physics minimum times)222,435 [132,241–308,691] 1/h
- TypicalBottles per hour of the rotary filler with the declared typical valve times62,649 [37,444–86,980] 1/h
- Availability with declared changeovers (minimum CIP plus product changeovers)0.974 [0.922–0.991]
- TypicalAvailability with a typical CIP programme (no changeovers)0.972 [0.916–0.989]
- TheoreticalMaximum availability (minimum filler CIP)0.995 [0.986–0.998]
- TheoreticalPerformance factor against the physics-limited rate1.00
- TheoreticalPhysics-bounded OEE0.995 [0.986–0.998]
- OEE with declared changeovers0.974 [0.922–0.991]
3Ceilings per dimension
- Theoretical
- Best available technique
- Best documented
- Typical
- TheoreticalMaximum yield: nominal volume sold per volume filled (give-away and T2 rejects)0.9949 [0.9900–0.9972]
- Best documentedYield including the documented product loss per changeover of a traditional filling operation0.9948 [0.9899–0.9971]
- TheoreticalMaximum OEE quality factor (bottles without a T2 error)1.00
- TheoreticalThermodynamic minimum work of filling (lift + vented counter-pressure gas)0.0419 [0.0269–0.0746] kJ/kg
- Best available techniqueDOE bandwidth study, state-of-the-art on-site energy intensity of fluid milk packaging (whole packaging step: filling, container handling and closing; wider boundary than the filler) · Benchmark27.9 kJ/kg
- TypicalDOE bandwidth study, current typical on-site energy intensity of fluid milk packaging (whole packaging step) · Benchmark34.9 kJ/kg
- TheoreticalMinimum valve process time (pressurise + fill + snift)0.874 [0.651–1.438] s
- TypicalValve process time with throttled liquid flow, real nozzles, controlled snift and valve actuation (declared scenario)3.10 [2.28–5.03] s
- TheoreticalMaximum bottles per hour of the rotary filler (physics minimum times)222,435 [132,241–308,691] 1/h
- TypicalBottles per hour of the rotary filler with the declared typical valve times62,649 [37,444–86,980] 1/h
- TheoreticalMaximum availability (minimum filler CIP)0.995 [0.986–0.998]
- TypicalAvailability with a typical CIP programme (no changeovers)0.972 [0.916–0.989]
- TheoreticalPerformance factor against the physics-limited rate1.00
- TheoreticalPhysics-bounded OEE0.995 [0.986–0.998]
4Loss cascade
- TheoreticalTypicalCycle or residence time0.874 [0.651–1.438] s → 3.10 [2.28–5.03] s (gap 2.23 s)
The theoretical valve time adds three ideal steps: adiabatic charging of the bottle through a loss-free nozzle, frictionless Torricelli discharge of the liquid through the full free annulus of the neck, and an unrestricted blowdown of the head-space. In operation the liquid flow is throttled on purpose: a carbonated product released at high velocity entrains gas, nucleates bubbles on the wall and foams, so the effective discharge coefficient is a fraction of one. The snift is not a free blowdown either: when the head-space pressure drops below the equilibrium CO2 pressure the product is supersaturated and degasses violently, so decompression is stepped and lasts about a second instead of a few hundredths. Valve actuation, the calming time before the snift and real gas-path losses add the rest.
- TheoreticalTypicalThroughput222,435 [132,241–308,691] 1/h → 62,649 [37,444–86,980] 1/h (gap 159,786 1/h)
The machine rate is the number of valves times the share of the revolution available for the process divided by the valve time. The gap between the theoretical and the typical rate is therefore the inverse of the time gap above (foaming-limited liquid flow, controlled snift, actuation), at equal number of valves and equal angular share.
- TheoreticalBest documentedYield0.9949 [0.9900–0.9972] → 0.9948 [0.9899–0.9971] (gap 1.02 × 10⁻⁴)
The theoretical yield already contains the give-away imposed by the prepackage rules for the declared fill dispersion and the drift of the lot mean, plus the bottles with a T2 error. The documented yield adds the product pushed out and rinsed away at each changeover in a traditional filling operation (75–100 L per changeover in the BAT reference document); techniques such as product recovery pigs, shorter product paths and late product diversification close this gap.
- TheoreticalBest available techniqueEnergy per unit of product
The thermodynamic minimum work of filling is tiny: lifting the liquid a couple of metres and compressing the few tens of millilitres of CO2 that are vented at the snift cost a few hundredths of a kilojoule per kilogram. The state-of-the-art and typical energy intensities of a packaging step are three orders of magnitude larger because they include drives of the carousel, conveyors, closing and labelling, compressed air, container rinsing and losses of motors and pneumatics; the energy of filling is set by machinery, not by the physics of the liquid.
5Physics-bounded OEE
- Loading time (ideal)1.000
- Availabilityfactor 0.995 [0.986–0.998]0.995 (−0.005)
- Performancefactor 1.000.995 (−0.000)
- Qualityfactor 1.000.995 (−0.000)
- Physics-bounded OEE0.995 [0.986–0.998]
6Full derivation
Scope. A carbonated soft drink filled into 0.5 L PET bottles on a rotary level filler with valves, by isobaric (counter-pressure) gravity filling. With zero carbonation the same equations describe a still liquid filled by gravity at atmospheric pressure. Symbols and their values, units, uncertainty distributions and sources are listed in the parameter table generated from config/physics/filling.yaml. Numbers quoted in this text are point values; the output table gives the Monte Carlo intervals.
1. Mass balance — maximum yield
Filling neither creates nor destroys product: every millilitre that leaves the bowl ends up in a bottle. The losses of a filler are therefore not physical but legal and statistical. A prepackage must carry at least its nominal quantity on average, and only a small share of packages may fall short by more than a tolerance. Because the individual fill volume scatters, the filler must aim above the nominal quantity, and the product filled above the nominal is given away: it is sold without being paid for. Bottles that fall short beyond twice the tolerance cannot be sold at all and are rejected.
The legal rules. For a nominal quantity the EU Directive 76/211/EEC (Annex I, point 2.4) and OIML R 87 (Table 1) fix the tolerable negative error (OIML: tolerable deficiency) ; for from 500 to 1 000 mL it is mL. Three requirements follow:
- Average requirement — the mean actual content of the lot is at least (OIML R 87, 3.2; Directive, Annex I, 1.1).
- T1 errors — at most of the packages may hold less than (OIML R 87, 3.3.2). The Directive states the same rule as a proportion "sufficiently small" to pass its reference sampling test.
- T2 errors — no package may hold less than , with (Directive, Annex I, 1.3; OIML R 87, 3.3.3).
NIST Handbook 133 (US) expresses the individual limit differently, as a "Maximum Allowable Variation" (MAV) beyond which a deficiency is an unreasonable minus error; it is cited for context and not modelled.
Fill-volume distribution. In a level filler the volume in each bottle is the brim-full capacity of the bottle minus the head-space left above the end of the return-gas tube. Both vary from bottle to bottle, so the individual fill volume is modelled as , where is the target mean and the standard deviation of individual fills (a declared scenario value, 2 mL, range 1–4 mL). Between control checks the mean itself drifts (temperature of the product, change of bottle lot, wear of valves); this drift is described by the standard deviation of the lot mean .
Minimum target mean. Each rule sets a lower bound on :
Here is the offset of the average requirement (the mean may not be below the nominal), is the one-sided 99.5% safety factor the operator applies so that each lot, not just the long-run average, meets the average requirement, and is the standard normal distribution function. is the mean at which exactly 2.5% of the bottles would carry a T1 error. The T1 rule binds only when ; the output sigma_legal_max mL shows the dispersion beyond which the individual rule, not the average rule, sets the mean. With the scenario values the average rule binds: mL.
Give-away, rejects and yield.
is the give-away per bottle (2.6 mL, 0.52% of the nominal), the share of bottles with a T2 error, which are rejected at the filler and whose content is lost, and the ratio of the nominal volume sold to the volume filled. is the theoretical yield ceiling for the declared capability: it falls only when the dispersion grows (more give-away, more rejects).
Capability index. The fill is compared with the lower legal limit through
A capable filler ( well above 1) has negligible rejects; its yield loss is entirely the give-away imposed by the average rule and the drift of the mean.
Documented ceiling. At each product changeover the previous product is pushed out of bowl, valves and product line and the system is rinsed. The BAT reference document reports that "Normally, 75–100 litres" are lost per changeover in a traditional filling operation (liquid dairy). With litres lost per changeover and litres filled between two changeovers,
2. Energy balance — minimum work per unit of product
A filler changes neither the temperature nor the composition of the product; the only energy it must supply is mechanical.
Lifting. The liquid is raised from the buffer tank to the bowl, a height . The reversible work per kilogram is ( = 9.81 m/s²): 0.020 kJ/kg for 2 m. The fall from the bowl into the bottle is driven by this potential energy and needs no further work.
Counter-pressure gas. In isobaric filling the bottle is first pressurised with CO2 from the bowl head-space to the filling pressure ; while the liquid flows in, the displaced gas returns to the bowl through the vent tube, so it is not consumed. What is consumed is the gas left in the head-space (brim-full capacity minus fill), which is vented to atmosphere at the snift. Replacing it requires compressing that amount of gas from atmospheric pressure to ; the least work is the reversible isothermal compression
where is the mass of product in the bottle: 0.022 kJ/kg at = 3.46 bar.
Thermodynamic minimum.
This is tiny — and it is meant to be shown as tiny. The dissolution of CO2 (carbonation) happens upstream in the carbonator and is outside the boundary; so is the refrigeration that keeps the product cold. The DOE bandwidth study sets the thermodynamic minimum of bottling to zero because it counts only chemical conversions; its boundary ignores mechanical work and is not comparable with . The documented energy intensities of a whole packaging step (DOE, fluid milk: 12 Btu/lb state of the art, 15 Btu/lb current typical, that is 28 and 35 kJ/kg) are three orders of magnitude above : they include drives, conveyors, closing, compressed air and motor losses, which belong to machinery, not to the physics of filling.
3. Rate-limiting step — minimum valve time and maximum throughput
Each valve performs three physical steps whose durations can be bounded: pressurisation of the bottle, liquid flow, and decompression (snift).
Minimum counter-pressure (Henry's law). The product must not release CO2 while it flows, so the filling pressure must exceed the equilibrium pressure of the dissolved gas. Carbonation is expressed in "volumes": volumes of gas at 0 °C and 1 atm per volume of liquid, i.e. a concentration mol/m³ ( = 8.314 J/(mol K), = 101 325 Pa, = 273.15 K), or mol/kg. The solubility of CO2 in water is given by the Weiss correlation
with in mol/(kg atm), in kelvin and , , (Weiss, 1974; = 0.034 mol/(kg atm) at 25 °C). Henry's law gives the equilibrium pressure : 2.46 bar for 3.5 volumes at 6 °C. The filler runs at , with a margin (scenario, 1 bar). For a still liquid and the gas steps vanish.
Pressurisation (compressible flow). Gas flows from the bowl at through the gas path of area (the vent tube, diameter ) into the bottle of volume . For an isentropic orifice the mass flow is
where , is the critical (choked) pressure ratio, the ratio of specific heats of CO2 (CoolProp), the specific gas constant, the gas temperature and the discharge coefficient (1 for an ideal nozzle). The energy balance of a rigid volume charged adiabatically from a reservoir at gives . Separating variables with :
integrated numerically up to , the pressure equalisation at which the liquid valve opens. Adiabatic charging requires less gas than isothermal charging (the gas heats on compression), so this is the shortest possible time: 0.082 s.
Liquid flow (Torricelli). With bowl and bottle at the same pressure, the driving force is the liquid head between the bowl level and the valve outlet. The ideal (frictionless) exit velocity is (Bernoulli). The liquid flows through the neck bore minus the return-gas tube :
With , = 342 mm² and = 0.40 m, the minimum fill time of 502.6 mL is 0.53 s. No publicly available drawing of the 28 mm PET neck finish could be retrieved, so is a declared scenario value (21.7 mm, range 20.5–22.5 mm).
Snift (head-space blowdown). After filling, the head-space at is vented through the snift orifice down to . For an adiabatic blowdown the gas temperature falls as and , which with gives
This gas-dynamic time is a strict lower bound. In practice the snift is longer and stepped: once the head-space pressure falls below the product is supersaturated by the ratio (about 2.4), CO2 nucleates on the bottle wall and the bottle foams over if decompression is fast. No physical law fixes that duration without knowledge of the nucleation sites, so the controlled snift time is a declared scenario value (1 s, range 0.5–2 s).
Valve time and machine rate.
where and are the discharge coefficients of gas and liquid paths in operation (the liquid one includes deliberate throttling against foaming), the controlled snift and the valve actuation and settling time. On a rotary filler each valve has the share of a revolution for its process (the rest is infeed and discharge of the bottle), so
With = 0.75 and = 72 valves: 3 090 bottles per hour per valve and 222 000 bottles per hour at the physical limit; 62 600 bottles per hour with the typical valve times.
4. Process capability — quality ceiling
The capability model is the one of Section 1. Bottles with a T2 error are the only quality loss counted by OEE (they cannot be marketed), so
At = 2.9 this is 1 to many decimals; falls visibly only when approaches the tolerance (for = 16 mL it is 0.998). Give-away is not an OEE quality loss — the bottle is good — but a yield loss, reported in .
5. Unavoidable stops — maximum availability
One stop cannot be avoided: cleaning-in-place of the filler (bowl, valves, gas paths) at the interval set by the hygiene plan (declared; no open source gives it for soft-drink fillers). Its minimum duration is taken through a parameter link from the cleaning model (output cip_time_min: the physical minimum of the kinetic and displacement phases plus declared hold times). That model is valid for the recirculated product pipes and valves; the spray cleaning of the bowl interior is outside its validity, so the linked duration is a lower bound:
Product changeovers (push-out and rinse, duration every ) are a decision of the product mix, not physics. They are reported separately as = 0.974 and enter only oee_scenario. The typical availability uses a declared typical CIP programme of 1.5–3 h: = 0.972.
6. Physics-bounded OEE
Scope of the bound. The theoretical label of means physics-bounded under the declared scenario: the ceiling follows from the physics of the operation for the declared product, equipment and schedule, and it is a bound only conditional on those declarations. It follows the common definition of all models: counts only stops required by regulation or forced by a physical mechanism, at their physical minimum duration, plus the start-up they force; is the ratio of the physics-limited ideal cycle to the cycle of the capable process; is the share of conforming units, and mass losses of conforming product are reported only as yield.
refers to the physics-limited rate of Section 3: a machine running at the rate set by its own minimum valve times has no performance loss by definition. The gap between the theoretical and the typical rate (a factor of about 3.5) is a loss of the installed technology against physics, reported as the rate cascade. The result is = 0.995, set by the minimum cleaning stop; with the declared changeovers, oee_scenario = = 0.974.
7. Assumptions and validity
See the assumption and validity lists generated from the configuration file. The most influential inputs (sensitivity table) are the cleaning and changeover intervals and durations for OEE; the drift of the lot mean and its safety factor for yield; and the liquid discharge coefficient and controlled snift time for the typical rate.
References
- Council Directive 76/211/EEC on the making-up by weight or by volume of certain prepackaged products, consolidated text of 11.04.2009. Publications Office of the European Union.
- International Organization of Legal Metrology. OIML R 87 Quantity of product in prepackages, Edition 2016.
- National Institute of Standards and Technology. NIST Handbook 133, Checking the Net Contents of Packaged Goods, 2026 Edition. doi:10.6028/NIST.HB.133-2026
- European Commission, Joint Research Centre. Best Available Techniques (BAT) Reference Document for the Food, Drink and Milk Industries, 2019.
- U.S. Department of Energy. Bandwidth Study on Energy Use and Potential Energy Saving Opportunities in U.S. Food and Beverage Manufacturing, 2017.
- Weiss, R. F. (1974). Carbon dioxide in water and seawater: the solubility of a non-ideal gas. Marine Chemistry, 2, 203–215. doi:10.1016/0304-4203(74)90015-2
- Bell, I. H., Wronski, J., Quoilin, S., Lemort, V. (2014). Pure and pseudo-pure fluid thermophysical property evaluation and the open-source thermophysical property library CoolProp. Industrial & Engineering Chemistry Research, 53, 2498–2508. doi:10.1021/ie4033999
7Parameters and provenance
- 500 mL
Nominal quantity stated on the bottle
Scenario · Fixed
Declared assumption0.5 L bottle of the scenario.
- 15 mL
Tolerable negative error (tolerable deficiency) for nominal quantities from 500 to 1 000 mL
Regulatory · Fixed
Verified quoteShow verbatim quote
from 500 to 1 000 — 15 from 1 000 to 10 000 1.5Council Directive 76/211/EEC of 20 January 1976 on the approximation of the laws of the Member States relating to the making-up by weight or by volume of certain prepackaged products (consolidated text of 11.04.2009) (opens in a new tab). Publications Office of the European Union, 2009. p. 5. CELEX 01976L0211-20090411
- 2
Multiple of the tolerable negative error beyond which no prepackage may be marketed (T2 error)
Regulatory · Fixed
Verified quoteShow verbatim quote
no prepackage having a negative error greater than twice the tolerable negative error given in the table in 2.4 may bear the EEC signCouncil Directive 76/211/EEC of 20 January 1976 on the approximation of the laws of the Member States relating to the making-up by weight or by volume of certain prepackaged products (consolidated text of 11.04.2009) (opens in a new tab). Publications Office of the European Union, 2009. p. 5. CELEX 01976L0211-20090411
- 2.5 %
Maximum share of prepackages with a T1 error in a homogeneous group
Regulatory · Fixed
Verified quoteShow verbatim quote
A homogenous group of prepackages shall contain no more than 2.5 % of packages having T1 errors.OIML R 87 Quantity of product in prepackages, Edition 2016 (E) (opens in a new tab). International Organization of Legal Metrology (OIML), 2016. p. 13. OIML R 87:2016 (E)
- 0 mL
Average requirement: the mean content may not be below the nominal quantity (offset zero)
Regulatory · Fixed
Verified quoteShow verbatim quote
The average actual quantity of product in prepackages shall be at least equal to the nominal quantity.OIML R 87 Quantity of product in prepackages, Edition 2016 (E) (opens in a new tab). International Organization of Legal Metrology (OIML), 2016. p. 13. OIML R 87:2016 (E)
- 2 mL
Standard deviation of the individual fill volume (bottle capacity spread plus level-setting spread of the valves)
Scenario · Uniform 1 to 4 mL
Declared assumptionProcess-capability assumption; no open source with measured fill-volume dispersion of PET level fillers was found. Replace with the measured value of the line.
- 1 mL
Standard deviation of the lot mean between control checks (temperature, bottle lot, level drift)
Scenario · Uniform 0.5 to 2 mL
Declared assumptionDeclared assumption for the drift of the controlled mean.
- 2.576
Safety factor on the lot mean so that each lot meets the average requirement (one-sided 99.5 %)
Scenario · Fixed
Declared assumptionOperating choice: Phi^-1(0.995). A larger factor raises give-away linearly.
- 1,040 kg/m³
Density of the sweetened carbonated soft drink
Scenario · Uniform 1,000 to 1,050 kg/m³
Declared assumptionRange from water (diet product) to a regular sweetened drink; declared assumption.
- 2 m
Height from the product buffer tank level to the liquid level of the filler bowl
Scenario · Uniform 1 to 4 m
Declared assumption - 3.5
Dissolved CO2 expressed as volumes of gas at 0 °C and 1 atm per volume of liquid (0 for still liquids)
Scenario · Uniform 2.5 to 4
Declared assumptionCarbonation level of the product; no open source with a regulated or reference value was used.
- 6 °C
Product temperature at the filler
Scenario · Uniform 2 to 12 °C
Declared assumption - -58.0931
Constant A1 of the Weiss correlation for the solubility of CO2 in pure water, K0 in mol/(kg atm)
Property · Fixed
Reference onlyLiterature constant (closed-access source, cited as reference only): Weiss (1974), ln K0 = A1 + A2 (100/T) + A3 ln(T/100); gives K0 = 0.0340 mol/(kg atm) at 25 °C. Derivation in physics_docs/filling.en.md, section 3.
- 90.5069
Constant A2 of the Weiss correlation
Property · Fixed
Reference onlyLiterature constant (closed-access source, cited as reference only): Weiss (1974).
- 22.294
Constant A3 of the Weiss correlation
Property · Fixed
Reference onlyLiterature constant (closed-access source, cited as reference only): Weiss (1974).
- 1 bar
Counter-pressure margin above the equilibrium CO2 pressure (keeps the gas in solution while filling)
Scenario · Uniform 0.5 to 2 bar
Declared assumptionOperating choice of the filler; declared assumption.
- 101,325 Pa
Atmospheric pressure
Property · Fixed
ComputedStandard atmosphere.
- 0.53 L
Brim-full (overflow) capacity of the 0.5 L PET bottle
Scenario · Uniform 0.52 to 0.54 L
Declared assumptionNo open bottle drawing was used; declared assumption.
- 1.3
Ratio of specific heats of CO2 (ideal gas at the filling temperature)
Property · Fixed
ComputedCoolProp: cp0 = 823.8 J/(kg K) at 279 K; kappa = cp0/(cp0 - R/M) = 1.298.
- 0.0440098 kg/mol
Molar mass of CO2
Property · Fixed
ComputedCoolProp PropsSI('M','CO2').
- 21.7 mm
Inner diameter (bore) of the 28 mm PET neck finish
Scenario · Uniform 20.5 to 22.5 mm
Declared assumptionNo publicly available neck-finish drawing could be retrieved (the standard drawings are distributed to members and suppliers); declared assumption with a range.
- 6 mm
Outer diameter of the return-gas (vent) tube inside the neck; also the gas path for pressurisation
Scenario · Uniform 4 to 8 mm
Declared assumption - 1 mm
Diameter of the snift (decompression) orifice
Scenario · Uniform 0.6 to 1.5 mm
Declared assumption - 0.4 m
Liquid head from the bowl level to the valve outlet (driving head with equalised pressures)
Scenario · Uniform 0.25 to 0.6 m
Declared assumption - 0.99
Pressure ratio bottle/bowl at which the liquid valve opens (pressure equalised)
Scenario · Fixed
Declared assumptionModel choice: equalisation within 1 %.
- 0.01
Residual over-pressure (fraction of atmospheric pressure) at the end of the snift
Scenario · Fixed
Declared assumptionModel choice: decompression to within 1 % of atmospheric pressure.
- 0.35
Effective discharge coefficient of the liquid path in operation (valve losses plus deliberate throttling against foaming of carbonated products)
Scenario · Uniform 0.2 to 0.6
Declared assumptionNo open source with measured fill rates per valve was found; declared assumption.
- 0.8
Discharge coefficient of the gas paths (pressurisation and snift)
Scenario · Uniform 0.6 to 0.9
Declared assumption - 1 s
Duration of the controlled (stepped) snift used to avoid foam-over of the supersaturated product
Scenario · Uniform 0.5 to 2 s
Declared assumptionNot bounded by an open source; the gas-dynamic minimum is computed, the controlled duration is declared.
- 0.5 s
Valve actuation and settling times per cycle (lift, opening, closing, calming before snift)
Scenario · Uniform 0.3 to 1 s
Declared assumption - 0.75
Share of a carousel revolution available for the valve process (the rest is infeed and discharge)
Scenario · Uniform 0.65 to 0.85
Declared assumption - 72
Number of filling valves of the rotary filler
Scenario · Fixed
Declared assumption - 72 h
Calendar interval between two cleanings-in-place of the filler
Scenario · Uniform 24 to 168 h
Declared assumptionNo open source states a cleaning frequency for soft-drink fillers; the frequency is set by the plant's hygiene plan. Declared assumption.
- 0.374294 h
Minimum duration of the filler CIP: physical minimum of the kinetic and displacement phases plus declared hold times (output cip_time_min of the cleaning model)
Property · Triangular 0.242184, 0.374294, 0.536161 h
ComputedOutput `cip_time_min` of the cleaning model: 22.46 min [14.53, 32.17].
- 2 h
Duration of a typical filler CIP programme (rinse
Scenario · Uniform 1.5 to 3 h
Declared assumptionDeclared typical programme, used for the typical availability.
- 24 h
Calendar interval between two product (flavour) changeovers
Scenario · Uniform 8 to 72 h
Declared assumption - 0.5 h
Duration of a product changeover (product push-out and water rinse of bowl and valves)
Scenario · Uniform 0.25 to 1 h
Declared assumption - 75 L
Product lost per changeover in a traditional filling operation (lower documented value
Benchmark · Uniform 75 to 100 L
Verified quoteShow verbatim quote
Normally, 75–100 litres of milk can easily be lost because of the changeover of production in a traditional filling operation.Best Available Techniques (BAT) Reference Document for the Food, Drink and Milk Industries (opens in a new tab). European Commission, Joint Research Centre; Publications Office of the European Union, 2019. p. 422. EUR 29978 EN; JRC118627; doi:10.2760/243911
8Benchmarks
| Benchmark | Ceiling | Value | Provenance |
|---|---|---|---|
DOE bandwidth study, state-of-the-art on-site energy intensity of fluid milk packaging (whole packaging step: filling, container handling and closing; wider boundary than the filler)Show verbatim quotePackaging 15 12 12 0 2.9 2.3 2.3 0Bandwidth Study on Energy Use and Potential Energy Savings Opportunities in U.S. Food and Beverage Manufacturing (opens in a new tab). U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy, Advanced Manufacturing Office, 2017. p. 56. DOE/EE-1571; OSTI ID 1512366 | Best available technique | 12 Btu/lb | Verified quote |
DOE bandwidth study, current typical on-site energy intensity of fluid milk packaging (whole packaging step)Show verbatim quotePackaging 15 12 12 0 2.9 2.3 2.3 0Bandwidth Study on Energy Use and Potential Energy Savings Opportunities in U.S. Food and Beverage Manufacturing (opens in a new tab). U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy, Advanced Manufacturing Office, 2017. p. 56. DOE/EE-1571; OSTI ID 1512366 | Typical | 15 Btu/lb | Verified quote |
DOE bandwidth study sets the thermodynamic minimum of bottling to zero because no chemical conversion takes place; its boundary ignores mechanical work, so it is not comparable with the lift and gas-compression work computed hereShow verbatim quoteBottling, storage and delivery Set to zero due to minimal chemical conversionsBandwidth Study on Energy Use and Potential Energy Savings Opportunities in U.S. Food and Beverage Manufacturing (opens in a new tab). U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy, Advanced Manufacturing Office, 2017. p. 65. DOE/EE-1571; OSTI ID 1512366 | Theoretical | 0 Btu/lb | Verified quote |
Product lost per changeover in a traditional filling operation, litres (BAT reference document, dairy)Show verbatim quoteNormally, 75–100 litres of milk can easily be lost because of the changeover of production in a traditional filling operation.Best Available Techniques (BAT) Reference Document for the Food, Drink and Milk Industries (opens in a new tab). European Commission, Joint Research Centre; Publications Office of the European Union, 2019. p. 422. EUR 29978 EN; JRC118627; doi:10.2760/243911 | Best documented | 75 L | Verified quote |
9Unavoidable stops
- Cleaning-in-place of the fillerDeclared assumption
Product residues in bowl, valves and gas paths support microbial growth; the hygiene plan of the plant fixes the interval. Duration and interval are declared scenario values.
- Product (flavour) changeover (scenario stop: availability_scenario only)Verified quote
A new product requires pushing out the previous one and rinsing the bowl and valves; the BAT reference document documents the product lost in a traditional filling changeover.
Show verbatim quote
Normally, 75–100 litres of milk can easily be lost because of the changeover of production in a traditional filling operation.Best Available Techniques (BAT) Reference Document for the Food, Drink and Milk Industries (opens in a new tab). European Commission, Joint Research Centre; Publications Office of the European Union, 2019. p. 422. EUR 29978 EN; JRC118627; doi:10.2760/243911
10Assumptions
- Individual fill volumes are normally distributed around the target mean; the lot mean drifts with the declared standard deviation between control checks.
- Bottles with a T2 error are rejected at the filler and their content is lost; bottles with a T1 error are legal up to the 2.5 % share and are sold.
- Isobaric filling: bowl and bottle are at the same pressure while the liquid flows, so the driving force is the liquid head only; the displaced gas returns to the bowl and is not consumed.
- Gas flows are isentropic orifice flows (choked below the critical pressure ratio); the bottle is charged and the head-space is discharged adiabatically, which gives the shortest times (lower bounds).
- CO2 dissolution (carbonation) happens upstream in the carbonator and is outside the boundary; the solubility is that of CO2 in pure water (Weiss correlation), the effect of dissolved sugar on solubility is neglected.
- Availability: the filler CIP is the only physically required stop; its minimum duration comes from the cleaning model, valid for the recirculated product pipes and valves; the spray cleaning of the bowl interior is outside that validity, so the linked duration is a lower bound. Product changeovers are a product-mix decision, not physics: they enter only availability_scenario and oee_scenario. The typical availability uses the declared typical CIP programme.
- Bottle rigidity: the PET bottle volume does not change during pressurisation (the expansion of the bottle under pressure is neglected).
11Range of validity
- Level (vent-tube) gravity fillers for liquids of water-like viscosity, carbonated or still, in rigid or semi-rigid bottles of 0.2 to 2 L.
- Prepackage rules of the EU Directive 76/211/EEC and OIML R 87; NIST Handbook 133 uses a different (maximum allowable variation) scheme that is not modelled here.
12Sensitivity
- Calendar interval between two cleanings-in-place of the fillerelasticity +0.005Spearman ρ +0.94
- Minimum duration of the filler CIP: physical minimum of the kinetic and displacement phases plus declared hold times (output cip_time_min of the cleaning model)elasticity -0.005Spearman ρ -0.31
- Output rises with the parameter
- Output falls with the parameter
13Validation checks
- Dimensional analysis31 outputs converted to their declared unitsPassed
- Every cited value verified against its source10 verified, 0 failedPassed
- No documented value beats the theoretical limitPassed
- Ceilings in physical orderPassed
- Fractions within 0 and 1Passed
14Causes of loss in this operation
- Filler equipment breakdown (unspecified failure mode)Equipment failure (breakdowns)3.7% [1.4–7.5%]A120 studies
- Filler changeover and adjustmentSetup and adjustments3.6% [1.5–7.1%]A120 studies
- Unspecified minor stoppage on filling lineIdling and minor stops (micro-stops)1.5% [0.5–3.3%]B120 studies
- Unspecified filler loss (unclassified cause)not classifiable1.4% [0.4–3.3%]B120 studies
- Filling process quality defectsProcess defects (scrap and rework)1.3% [0.4–3.1%]B120 studies
- Filler running below rated speedReduced speed1.1% [0.3–2.7%]C120 studies
- Crown cap feed, strip and alignment malfunction at the crownerEquipment failure (breakdowns)0.9% [0.2–2.3%]C120 studies
- CIP (Clean-in-Place) cleaning cycleSetup and adjustments0.9% [0.2–2.2%]C120 studies
- Filler dosing/valve fault causing overfillingProcess defects (scrap and rework)0.9% [0.2–2.1%]C120 studies
- Filler inlet guide jam/failureEquipment failure (breakdowns)0.8% [0.2–1.9%]C120 studies
- Electrical fault in filling/weighing equipmentEquipment failure (breakdowns)0.8% [0.2–1.8%]C120 studies
- Fill content or contamination defectProcess defects (scrap and rework)0.7% [0.2–2.0%]C120 studies
- Infeed screw/worm malfunction or jamEquipment failure (breakdowns)0.7% [0.2–2.0%]C120 studies
- Aseptic carton filler subsystem failureEquipment failure (breakdowns)0.7% [0.2–1.8%]C120 studies
- Filler discharge jam or backupEquipment failure (breakdowns)0.7% [0.2–1.9%]C120 studies
- Filling valve malfunctionEquipment failure (breakdowns)0.7% [0.2–1.8%]C120 studies
- Changeover retooling on fillerSetup and adjustments0.7% [0.2–1.9%]C120 studies
- Control panel failureEquipment failure (breakdowns)0.6% [0.1–1.7%]D120 studies
- Fastener or bolt breakageEquipment failure (breakdowns)0.6% [0.1–1.6%]D120 studies
- Planned downtime (scheduled stop)planned downtime0.6% [0.1–1.6%]D120 studies
- Filler timing worm/synchronization faultEquipment failure (breakdowns)0.6% [0.1–1.6%]D120 studies
- Filling nozzle component failureEquipment failure (breakdowns)0.6% [0.1–1.6%]D120 studies
- Scheduled short breaksplanned downtime0.6% [0.1–1.5%]D120 studies
- Raw material supply interruption causing filler readjustmentorganizational external0.6% [0.1–1.6%]D120 studies
- Dosing/lobe pump jamming failureEquipment failure (breakdowns)0.6% [0.1–1.6%]D120 studies
- Dosing hose cloggingEquipment failure (breakdowns)0.6% [0.1–1.5%]D120 studies
- Bag Fill Weight and Seal DefectsProcess defects (scrap and rework)0.6% [0.1–1.6%]D120 studies
- Scheduled cleaning, inspection and lubrication of the fillerplanned downtime0.6% [0.1–1.5%]D120 studies
- Container Body or Seal DefectProcess defects (scrap and rework)0.6% [0.1–1.5%]D120 studies
- Weighing scale failure (electrical or mechanical)Equipment failure (breakdowns)0.6% [0.1–1.5%]D120 studies
- Vent tube bent or looseEquipment failure (breakdowns)0.6% [0.1–1.5%]D120 studies
- Minor mechanical adjustment stop on fillerEquipment failure (breakdowns)0.5% [0.1–1.4%]D120 studies
- Metal detector malfunctionEquipment failure (breakdowns)0.5% [0.1–1.5%]D120 studies
- Filling and closure defects (underfill, uncrowned, contamination)Process defects (scrap and rework)0.5% [0.1–1.5%]D120 studies
- Sanitation-in-place (SIP) cycle on fillerIdling and minor stops (micro-stops)0.5% [0.1–1.4%]D120 studies
- Changeover material staging/fetching delaySetup and adjustments0.5% [0.1–1.4%]D120 studies
- Die or tooling retrieval delay during changeoverSetup and adjustments0.5% [0.1–1.4%]D120 studies
- Container jam at bottle divider/lane splitterIdling and minor stops (micro-stops)0.5% [0.1–1.4%]D120 studies
- Stamp/cap jam on applicator trackIdling and minor stops (micro-stops)0.5% [0.1–1.4%]D120 studies
- Changeover documentation and paperwork delaySetup and adjustments0.5% [0.1–1.4%]D120 studies
- Mixed and undifferentiated filler losses (changeover, breakdown, stoppage, defects)Setup and adjustments0.5% [0.1–1.4%]D120 studies
- Nylon washer/seal wear and failureEquipment failure (breakdowns)0.4% [0.1–1.1%]D120 studies
- Filler Sealing Pad Wear/FailureEquipment failure (breakdowns)0.4% [0.1–1.2%]D120 studies
- Crown cap sorter sensor malfunctionEquipment failure (breakdowns)0.4% [0.1–1.1%]D120 studies
- Jam/blockage at coding or sealing stationEquipment failure (breakdowns)0.4% [0.1–1.1%]D120 studies
- Pneumatic Component Failure (Air Hose / Solenoid Valve)Equipment failure (breakdowns)0.4% [0.1–1.2%]D120 studies
- Filler centering bell fault/tripEquipment failure (breakdowns)0.4% [0.1–1.2%]D120 studies
- Filler support/bracket mechanical failureEquipment failure (breakdowns)0.4% [0.1–1.1%]D120 studies
- Bag loading/opening mechanism failureEquipment failure (breakdowns)0.4% [0.1–1.1%]D120 studies
- Gripper FailureEquipment failure (breakdowns)0.4% [0.1–1.2%]D120 studies
- Filler product bowl malfunctionEquipment failure (breakdowns)0.4% [0.1–1.1%]D120 studies
- Filling sensor failure (electrical/photoelectric)Equipment failure (breakdowns)0.4% [0.1–1.1%]D120 studies
- Star wheel / transfer wheel timing faultEquipment failure (breakdowns)0.4% [0.1–1.1%]D120 studies
- Filler piston wear or failureEquipment failure (breakdowns)0.4% [0.1–1.0%]D120 studies
- Empty container supply shortageorganizational external0.4% [0.1–1.1%]D120 studies
- Staff meetings and briefingsorganizational external0.4% [0.1–1.1%]D120 studies
- Manual filling/weighing variationProcess defects (scrap and rework)0.4% [0.1–1.1%]D120 studies
- Excessive Product Foaming During FillingProcess defects (scrap and rework)0.4% [0.1–1.1%]D120 studies
- Manual rework due to packaging sealing defectsProcess defects (scrap and rework)0.4% [0.1–1.1%]D120 studies
- Thermal variability during tempering affecting fill accuracyProcess defects (scrap and rework)0.4% [0.1–1.1%]D120 studies
- Defective incoming pouch from supplierProcess defects (scrap and rework)0.4% [0.1–1.1%]D120 studies
- Doser calibration driftProcess defects (scrap and rework)0.4% [0.1–1.0%]D120 studies
- Bottle jam or fall on conveyorIdling and minor stops (micro-stops)0.3% [0.1–1.1%]D120 studies
- Tilting mechanism jamIdling and minor stops (micro-stops)0.3% [0.1–1.0%]D120 studies
- Bottle jam on spiral infeed screwIdling and minor stops (micro-stops)0.3% [0.1–1.0%]D120 studies
- Non-optimized changeover procedureSetup and adjustments0.3% [0.1–1.0%]D120 studies
- CIP conductivity/temperature transmitter malfunctionSetup and adjustments0.3% [0.1–1.0%]D120 studies
- Pallet Supply DepletionIdling and minor stops (micro-stops)0.3% [0.1–1.0%]D120 studies
- Shift handover documentation updateSetup and adjustments0.3% [0.1–1.0%]D120 studies
- Manual ingredient loading into filling tankSetup and adjustments0.3% [0.1–1.0%]D120 studies
- Changeover tooling disorganization (lack of 5S)Setup and adjustments0.3% [0.1–1.0%]D120 studies
- Cut-open rework of filled packages at changeoverSetup and adjustments0.3% [0.1–1.0%]D120 studies
- Changeover to new plastic package formatSetup and adjustments0.3% [0.1–1.0%]D120 studies
- Waiting for empty container supplySetup and adjustments0.3% [0.1–1.0%]D120 studies
- Buffer/Bright Tank Changeover DelaySetup and adjustments0.3% [0.1–1.0%]D120 studies
- First-piece inspection after changeoverSetup and adjustments0.3% [0.1–1.0%]D120 studies
- Fill volume setpoint adjustmentSetup and adjustments0.3% [0.1–1.0%]D120 studies
- Commissioning of new inline density/gravity sensorSetup and adjustments0.3% [0.1–0.9%]D120 studies
- Filler start-up yield lossStart-up losses (reduced yield)0.3% [0.0–1.0%]D120 studies
15References
- Council Directive 76/211/EEC of 20 January 1976 on the approximation of the laws of the Member States relating to the making-up by weight or by volume of certain prepackaged products (consolidated text of 11.04.2009) (opens in a new tab). Publications Office of the European Union, 2009. p. 5. CELEX 01976L0211-20090411
- OIML R 87 Quantity of product in prepackages, Edition 2016 (E) (opens in a new tab). International Organization of Legal Metrology (OIML), 2016. p. 13. OIML R 87:2016 (E)
- nist_hb133_2026
- Best Available Techniques (BAT) Reference Document for the Food, Drink and Milk Industries (opens in a new tab). European Commission, Joint Research Centre; Publications Office of the European Union, 2019. p. 422. EUR 29978 EN; JRC118627; doi:10.2760/243911
- Bandwidth Study on Energy Use and Potential Energy Savings Opportunities in U.S. Food and Beverage Manufacturing (opens in a new tab). U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy, Advanced Manufacturing Office, 2017. p. 56. DOE/EE-1571; OSTI ID 1512366
- doi:10.1016/0304-4203(74)90015-2 — Solubility of CO2 in water (Weiss correlation).
- doi:10.1021/ie4033999 — Thermophysical property library (CoolProp).