Manual raw material weighing and transfer to mixing stage
In short
It appears in about 1 of every 100 lines studied.
When it appears, it takes on average about 56 % of the line's lost time. Reported by 1 of the 31 studies that could observe it (sparse evidence).
What happens
Before a mixing batch can start, operators must manually weigh out the raw materials according to the formulation and physically carry or hoist them to the level or hopper where the mixer is charged. This preparatory handling is sequential with respect to the mixer and adds non-productive time to the changeover or batch-start window, especially when materials must be moved between floors or storage areas.
What is done about it
Pre-weigh and stage raw materials in advance during the running time of the previous batch, and use automated or semi-automated dosing/batching systems with pneumatic or mechanical conveying to the mixing level to eliminate manual carrying. Kitting of materials and parallel preparation activities reduce the sequential dependency and shorten the changeover or batch-start interval.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 0.8% [0.1–2.7%]
- Expected share of lost time
- 0.5% [0.1–1.5%]
- Share of lost time when present
- 56% [43–68%]
- Studies / units
- 31 / 40
- Evidence grade
- D
Grade D: 0 or 1 study; the estimate is driven by partial pooling and priors, and the wide interval is the result.
2Probability by segment
- Dairy products1.0% [0.1–3.9%]6 studies
- Soft drinks, bottled water and juices1.0% [0.1–3.8%]2 studies
- Brewing, wine and spirits1.0% [0.1–4.0%]0 studies
- Bakery and pasta1.4% [0.1–5.5%]2 studies
- Meat, poultry and seafood1.0% [0.1–4.1%]1 study
- Fruit and vegetable processing1.0% [0.1–3.9%]2 studies
- Grain and oilseed milling1.0% [0.1–4.4%]0 studies
- Sugar and confectionery1.0% [0.1–4.1%]3 studies
- Snacks, coffee, tea and other foods0.9% [0.1–3.5%]3 studies
- Animal feed and pet food1.0% [0.1–3.6%]5 studies
- Food manufacturing (unspecified or mixed)1.0% [0.1–3.9%]7 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceBefore a mixing batch can start, operators must manually weigh out the raw materials according to the formulation and physically carry or hoist them to the level or hopper where the mixer is charged. This preparatory handling is sequential with respect to the mixer and adds non-productive time to the changeover or batch-start window, especially when materials must be moved between floors or storage areas.
How it looks in SCADA data
Engineering guidanceThe mixer remains in an idle or waiting-for-material state with no agitation or feed signal active, preceded by a gap in which no weighing or charging event is logged in the MES/batch record. Operator or material-handling activity (weighing station use, hoist or elevator cycles) is recorded outside the mixer's run-state log, creating a visible dead time between end of previous batch and start of mixing.
Countermeasure
Engineering guidancePre-weigh and stage raw materials in advance during the running time of the previous batch, and use automated or semi-automated dosing/batching systems with pneumatic or mechanical conveying to the mixing level to eliminate manual carrying. Kitting of materials and parallel preparation activities reduce the sequential dependency and shorten the changeover or batch-start interval.
4Sources
- Productivity Improvement in a Bakery and Pastry Premix Company by Applying Preventive Maintenance, SMED and 5´S (2026)Open sourceMean event duration: 0.960 min · as reported: “Weigh raw materials”
Show verbatim quote
Weigh raw materials Weighing operators Weighing operators External External 0.96 0.96
- Productivity Improvement in a Bakery and Pastry Premix Company by Applying Preventive Maintenance, SMED and 5´S (2026)Open sourceMean event duration: 2.30 min · as reported: “Move raw material from weighing to 3rd level”
Show verbatim quote
Move raw material from weighing to 3rd level Operator 2 DRY / Weighing operators Operator 2 DRY / Weighing operators Internal External 2.30 3.00
- Productivity Improvement in a Bakery and Pastry Premix Company by Applying Preventive Maintenance, SMED and 5´S (2026)Open sourceMean event duration: 0.960 min · as reported: “Weigh raw materials”
Show verbatim quote
Weigh raw materials Weighing operators Weighing operators External External 0.96 0.96
- Productivity Improvement in a Bakery and Pastry Premix Company by Applying Preventive Maintenance, SMED and 5´S (2026)Open sourceMean event duration: 3.00 min · as reported: “Move raw material from weighing to 3rd level”
Show verbatim quote
Move raw material from weighing to 3rd level Operator 2 DRY / Weighing operators Operator 2 DRY / Weighing operators Internal External 2.30 3.00