Shift start/end line setup
In short
It appears in about 1 of every 100 lines studied.
When it appears, it takes on average about 57 % of the line's lost time. Reported by 1 of the 112 studies that could observe it (sparse evidence).
What happens
At the start of a shift the packaging line must be brought from a stopped or standby state to stable operating conditions, requiring warm-up, checks and fine adjustments before good units are produced; at the end of a shift the line is progressively run down, cleared and prepared for the next shift, which also consumes productive time without output. These transition periods occur independently of any product or format change and are tied purely to the shift schedule.
What is done about it
Standardize shift handover and start-up/shut-down procedures with checklists, pre-stage settings and materials before the shift begins, and use brief shift overlap so the line can keep running while responsibilities transfer. Apply quick-setup principles to shorten warm-up and shutdown sequences and track them as a distinct, monitored step in the shift schedule.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 0.5% [0.1–1.4%]
- Expected share of lost time
- 0.3% [0.1–0.8%]
- Share of lost time when present
- 57% [44–67%]
- Studies / units
- 112 / 155
- Evidence grade
- D
Grade D: 0 or 1 study; the estimate is driven by partial pooling and priors, and the wide interval is the result.
2Probability by segment
- Dairy products0.6% [0.1–2.2%]14 studies
- Soft drinks, bottled water and juices0.5% [0.1–1.6%]33 studies
- Brewing, wine and spirits0.6% [0.1–2.0%]14 studies
- Bakery and pasta0.6% [0.1–2.3%]6 studies
- Meat, poultry and seafood0.6% [0.1–2.4%]6 studies
- Fruit and vegetable processing0.6% [0.1–2.3%]4 studies
- Grain and oilseed milling0.6% [0.1–2.2%]4 studies
- Sugar and confectionery0.6% [0.1–2.3%]4 studies
- Snacks, coffee, tea and other foods0.6% [0.1–2.1%]8 studies
- Animal feed and pet food0.6% [0.1–2.2%]5 studies
- Food manufacturing (unspecified or mixed)0.9% [0.1–3.2%]14 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceAt the start of a shift the packaging line must be brought from a stopped or standby state to stable operating conditions, requiring warm-up, checks and fine adjustments before good units are produced; at the end of a shift the line is progressively run down, cleared and prepared for the next shift, which also consumes productive time without output. These transition periods occur independently of any product or format change and are tied purely to the shift schedule.
How it looks in SCADA data
Engineering guidanceMES/SCADA logs show recurring blocks of setup or non-running machine state aligned with the shift calendar at the start and end of each shift, with no accompanying product-change or recipe-change event. Output counters remain flat or show reduced partial counts during these intervals, and the pattern repeats consistently across shifts rather than correlating with specific SKUs.
Countermeasure
Engineering guidanceStandardize shift handover and start-up/shut-down procedures with checklists, pre-stage settings and materials before the shift begins, and use brief shift overlap so the line can keep running while responsibilities transfer. Apply quick-setup principles to shorten warm-up and shutdown sequences and track them as a distinct, monitored step in the shift schedule.
4Sources
- ANALISIS PERHITUNGAN OVERALL EQUIPMENT EFFECTIVENESS (OEE) PADA MESIN PACKING UNTUK MENINGKATKAN NILAI AVAILABILITY MESIN (2014)Open sourceLost time: 3,908 min · as reported: “Initial and end of shift setup”
Show verbatim quote
Setting awal dan akhir shift 3,908 35%