In short
It appears in fewer than 1 of every 100 lines studied.
When it appears, it takes on average about 56 % of the line's lost time. Reported by 0 of the 120 studies that could observe it (sparse evidence).
What happens
Changeover tasks on the filler are performed largely as sequential, machine-stopped (internal) steps rather than being split into parallel or pre-staged (external) activities, and adjustments are not standardized across operators. This lack of structured methodology extends the time between the last good unit of one run and the first good unit of the next.
What is done about it
Apply SMED methodology: classify and separate internal versus external setup activities, convert as many internal steps as possible into external ones performed while the line still runs, standardize and simplify adjustments with quick-change fixtures and pre-staged tooling, and validate the new sequence through time-and-motion studies and operator training.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 0.3% [0.1–1.0%]
- Expected share of lost time
- 0.2% [0.0–0.6%]
- Share of lost time when present
- 56% [43–67%]
- Studies / units
- 120 / 162
- Evidence grade
- D
Grade D: 0 or 1 study; the estimate is driven by partial pooling and priors, and the wide interval is the result.
2Probability by segment
- Dairy products0.4% [0.0–1.4%]18 studies
- Soft drinks, bottled water and juices0.3% [0.0–1.2%]44 studies
- Brewing, wine and spirits0.4% [0.0–1.5%]16 studies
- Bakery and pasta0.4% [0.0–1.7%]0 studies
- Meat, poultry and seafood0.4% [0.0–1.6%]6 studies
- Fruit and vegetable processing0.4% [0.0–1.6%]4 studies
- Grain and oilseed milling0.4% [0.0–1.5%]6 studies
- Sugar and confectionery0.4% [0.0–1.7%]3 studies
- Snacks, coffee, tea and other foods0.4% [0.0–1.5%]6 studies
- Animal feed and pet food0.4% [0.0–1.6%]4 studies
- Food manufacturing (unspecified or mixed)0.4% [0.0–1.5%]13 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceChangeover tasks on the filler are performed largely as sequential, machine-stopped (internal) steps rather than being split into parallel or pre-staged (external) activities, and adjustments are not standardized across operators. This lack of structured methodology extends the time between the last good unit of one run and the first good unit of the next.
How it looks in SCADA data
Engineering guidanceMES/SCADA logs show an extended changeover or setup machine-state duration on the filler, with multiple sequential sub-states (teardown, tool change, adjustment, trial run) and manual confirmation events bridging the transition; the changeover time distribution shows a long tail not explained by format complexity alone, and neighboring stations remain idle or blocked during the stop.
Countermeasure
Engineering guidanceApply SMED methodology: classify and separate internal versus external setup activities, convert as many internal steps as possible into external ones performed while the line still runs, standardize and simplify adjustments with quick-change fixtures and pre-staged tooling, and validate the new sequence through time-and-motion studies and operator training.
4Sources
- Lost time: 16.0 min · as reported: “SMED and related improvements”
Show verbatim quote
Therefore,the total reduction in changeover time due to SMED and related improvements was 16 min.