Delay in upstream supply or support process
In short
It appears in about 1 of every 100 lines studied.
When it appears, it takes on average about 56 % of the line's lost time. Reported by 2 of the 127 studies that could observe it (limited evidence).
What happens
The line is starved because a support activity located upstream of the process (washing of containers/trays, batch formulation, feeding of raw materials onto the line, or receipt of external deliveries) does not deliver its output in time. The stoppage does not originate in the line equipment itself but in the scheduling or execution of an upstream task on which the line depends.
What is done about it
Synchronize the schedule of the upstream support process with the production plan of the line, add buffer stock or intermediate storage of washed containers, formulated batches or incoming materials, and set up early warning or kanban signals so the upstream area anticipates the line's demand and deliveries are coordinated in advance.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 0.8% [0.2–1.9%]
- Expected share of lost time
- 0.4% [0.1–1.1%]
- Share of lost time when present
- 56% [45–66%]
- Studies / units
- 127 / 161
- Evidence grade
- C
Grade C: 2 to 4 studies, or an interval wider than 0.35.
2Probability by segment
- Dairy products0.9% [0.1–2.9%]13 studies
- Soft drinks, bottled water and juices0.8% [0.1–2.5%]26 studies
- Brewing, wine and spirits0.8% [0.1–2.8%]11 studies
- Bakery and pasta1.1% [0.2–3.4%]24 studies
- Meat, poultry and seafood0.9% [0.1–3.0%]9 studies
- Fruit and vegetable processing0.9% [0.1–2.9%]7 studies
- Grain and oilseed milling0.9% [0.1–3.3%]6 studies
- Sugar and confectionery0.9% [0.1–3.0%]9 studies
- Snacks, coffee, tea and other foods0.9% [0.1–3.1%]5 studies
- Animal feed and pet food0.9% [0.1–3.0%]7 studies
- Food manufacturing (unspecified or mixed)1.3% [0.2–4.4%]10 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceThe line is starved because a support activity located upstream of the process (washing of containers/trays, batch formulation, feeding of raw materials onto the line, or receipt of external deliveries) does not deliver its output in time. The stoppage does not originate in the line equipment itself but in the scheduling or execution of an upstream task on which the line depends.
How it looks in SCADA data
Engineering guidanceLine or station shows an extended idle/waiting state with no equipment fault code active, often logged as waiting for material or waiting for input; counters for infeed accumulation drop to zero while the rest of the line remains available, and the event correlates in time with records or logs of the upstream washing, formulation or logistics area rather than with any machine alarm.
Countermeasure
Engineering guidanceSynchronize the schedule of the upstream support process with the production plan of the line, add buffer stock or intermediate storage of washed containers, formulated batches or incoming materials, and set up early warning or kanban signals so the upstream area anticipates the line's demand and deliveries are coordinated in advance.
4Sources
- Lost time: 5.00 h · as reported: “Demora en formulación”
Show verbatim quote
Demora en formulación 5 980 0.5% 99.7%
- Share of lost time: 0.500 % · as reported: “Demora en formulación”
Show verbatim quote
Demora en formulación 5 980 0.5% 99.7%
- Proposal to improve efficiency in pre-baked bread production lines in a Peruvian SME, using SMED and TPM (2025)Open sourceLost time: 54.1 h · as reported: “Demora en el lavado de bandejas”
Show verbatim quote
Demora en el lavado de bandejas 54.09 53%
- Proposal to improve efficiency in pre-baked bread production lines in a Peruvian SME, using SMED and TPM (2025)Open sourceShare of lost time: 53.0 % · as reported: “Demora en el lavado de bandejas”
Show verbatim quote
Demora en el lavado de bandejas 54.09 53%
- Proposal to improve efficiency in pre-baked bread production lines in a Peruvian SME, using SMED and TPM (2025)Open sourceLost time: 14.4 h · as reported: “Demora en el lavado de bandejas”
Show verbatim quote
se concluye que el tiempo de parada por la demora en el lavado de bandejas representa el 53% del total de horas del motivo 3 y presentó su máximo de horas de paradas en el enero del 2023, con 14.4 horas.
- Proposal to improve efficiency in pre-baked bread production lines in a Peruvian SME, using SMED and TPM (2025)Open sourceLost time: 17.0 h · as reported: “Demora en la alimentación de la línea”
Show verbatim quote
Demora en la alimentación de la línea 16.97 16%
- Proposal to improve efficiency in pre-baked bread production lines in a Peruvian SME, using SMED and TPM (2025)Open sourceShare of lost time: 16.0 % · as reported: “Demora en la alimentación de la línea”
Show verbatim quote
Demora en la alimentación de la línea 16.97 16%
- Implementation of TPM total productive maintenance methodology to improve productivity in a frozen food company (2023)Open sourceShare of loss events: 34.0 % · as reported: “Demora en Entregas”
Show verbatim quote
En los primeros 9 meses del año 2022 se registró un total de 167 incidencias en todo el proceso de producción, ocasionando un 34% en demoras en las entregas finales a los clientes y un 66% en retrasos de procesos.