Changeover delay due to searching for and fetching tools/utensils
In short
It appears in fewer than 1 of every 100 lines studied.
When it appears, it takes on average about 57 % of the line's lost time. Reported by 1 of the 127 studies that could observe it (sparse evidence).
What happens
During a changeover the operator discovers that the tools, spare parts or utensils needed are not at the workstation and must walk to a storeroom or another area to find and bring them back, adding non-productive time before the line can be reassembled and restarted. This typically happens when there is no standardized kit or shadow board for the format being set up and tool location is not controlled.
What is done about it
Apply SMED principles: pre-stage a dedicated changeover kit or shadow board with every tool and utensil needed for each format at the point of use, and separate internal from external setup activities so retrieval happens before the line stops. Assign a changeover checklist and, where volume justifies it, a dedicated setup technician to eliminate walking and searching time.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 0.5% [0.1–1.3%]
- Expected share of lost time
- 0.3% [0.1–0.8%]
- Share of lost time when present
- 57% [45–67%]
- Studies / units
- 127 / 161
- Evidence grade
- D
Grade D: 0 or 1 study; the estimate is driven by partial pooling and priors, and the wide interval is the result.
2Probability by segment
- Dairy products0.6% [0.1–2.1%]13 studies
- Soft drinks, bottled water and juices0.5% [0.1–1.8%]26 studies
- Brewing, wine and spirits0.6% [0.1–1.9%]11 studies
- Bakery and pasta0.5% [0.1–1.8%]24 studies
- Meat, poultry and seafood0.6% [0.1–2.0%]9 studies
- Fruit and vegetable processing0.6% [0.1–2.0%]7 studies
- Grain and oilseed milling0.6% [0.1–2.2%]6 studies
- Sugar and confectionery0.6% [0.1–2.0%]9 studies
- Snacks, coffee, tea and other foods0.6% [0.1–2.0%]5 studies
- Animal feed and pet food0.9% [0.1–3.3%]7 studies
- Food manufacturing (unspecified or mixed)0.6% [0.1–2.1%]10 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceDuring a changeover the operator discovers that the tools, spare parts or utensils needed are not at the workstation and must walk to a storeroom or another area to find and bring them back, adding non-productive time before the line can be reassembled and restarted. This typically happens when there is no standardized kit or shadow board for the format being set up and tool location is not controlled.
How it looks in SCADA data
Engineering guidanceThe equipment state log shows an extended changeover/setup state with no machine motion or energy consumption, often with the operator badge or HMI left idle, and the gap does not correlate with any mechanical adjustment step recorded elsewhere on the line. MES changeover timers exceed the standard changeover duration without any fault or jam code being raised.
Countermeasure
Engineering guidanceApply SMED principles: pre-stage a dedicated changeover kit or shadow board with every tool and utensil needed for each format at the point of use, and separate internal from external setup activities so retrieval happens before the line stops. Assign a changeover checklist and, where volume justifies it, a dedicated setup technician to eliminate walking and searching time.
4Sources
- Production Management Model Based on Lean Manufacturing Tools and SLP to Increase Productivity in a Meatball (BARF) Plant (2026)Open sourceMean event duration: 2.81 min · as reported: “Search and transfer utensils to the area”
Show verbatim quote
Search and transfer utensils to the area 2.81 Internal External
- Production Management Model Based on Lean Manufacturing Tools and SLP to Increase Productivity in a Meatball (BARF) Plant (2026)Open sourceLost time: 2.81 min · as reported: “Search and transfer utensils to the area”
Show verbatim quote
Search and transfer utensils to the area 2.81