Sterilizer Reliability Analysis Using Reliability Block Diagram Based on Failure Identification Through Fault Tree Analysis
1Bibliographic record
- Authors
- Syamsul Bahri, Fatimah Fatimah, Saifuddin Muhammad Jalil, Amri Amri, Muhammad Ilham
- Year
- 2021
- Venue
- International Journal of Engineering Science and Information Technology
- Country
- Indonesia
- Segment
- Grain and oilseed milling
- Process family
- Slaughter, cutting and primary processing
- Study type
- Reliability analysis
- Extraction scope
- Full text
- Size
- 1 plants · — lines · 1 machines
- Observation period
- 365 days
- Data collection
- maintenance_records
- Intervention
Show the setting as described by the study
PT. X is a company engaged in the processing of fresh fruit bunches (FFB) into Crude Palm Oil and Palm Kernel.
2Risk of bias
Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 12Moderate risk
| Item | Score |
|---|---|
| Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product, process and equipment are all described. | 2 / 2 |
| Is the observation period long enough and reported?Period reported and at least 30 days of production (or at least 100 recorded events). | 2 / 2 |
| How were loss data collected?Manual logs or maintenance records with unknown completeness. | 1 / 2 |
| Are OEE, loading time and the loss categories defined explicitly?A standard definition is cited but its application is not shown. | 1 / 2 |
| Does the loss breakdown account for the total loss it claims to explain?Only the top causes are reported and the unexplained remainder can be computed. | 1 / 2 |
| Is there evidence of selective reporting of favourable results?Observational study, or intervention study that reports baseline and post-intervention data with the same method. | 2 / 2 |
| Are the reported numbers internally consistent?Small inconsistencies (2 to 10 percentage points) or values that cannot be cross-checked. | 1 / 2 |
| Could conflicts of interest or the source of the data bias the result?Academic or independent study, or conflicts declared and unrelated to the result. | 2 / 2 |
3Extracted data
Each datum with its classification and the verbatim quote that states it.
| Reported cause | Loss category | Metric | Value | Extraction |
|---|---|---|---|---|
Packing doorPacking doorShow verbatim quote (Table 3)Packing door 11 | Equipment failure (breakdowns) | Number of events | 11.0 events | Single extractor |
Flange PipeFlange PipeShow verbatim quote (Table 3)Flange Pipe 4 | Equipment failure (breakdowns) | Number of events | 4.00 events | Single extractor |
Ball ValveBall ValveShow verbatim quote (Table 3)Ball Valve 2 | Equipment failure (breakdowns) | Number of events | 2.00 events | Single extractor |
Nozzle CondensatNozzle CondensatShow verbatim quote (Table 3)Nozzle Condensat 2 | Equipment failure (breakdowns) | Number of events | 2.00 events | Single extractor |
ActuatorActuatorShow verbatim quote (Table 3)Actuator 2 | Equipment failure (breakdowns) | Number of events | 2.00 events | Single extractor |
Valve ExhaustValve ExhaustShow verbatim quote (Table 3)Valve Exhaust 2 | Equipment failure (breakdowns) | Number of events | 2.00 events | Single extractor |
Valve CondensatValve CondensatShow verbatim quote (Table 3)Valve Condensat 1 | Equipment failure (breakdowns) | Number of events | 1.00 events | Single extractor |
Streiner ValveStreiner ValveShow verbatim quote (Table 3)Streiner Valve 1 | Equipment failure (breakdowns) | Number of events | 1.00 events | Single extractor |
Packing FlangePacking FlangeShow verbatim quote (Table 3)Packing Flange 1 | Equipment failure (breakdowns) | Number of events | 1.00 events | Single extractor |
Packing doorPacking doorShow verbatim quote (Table 4)Packing door 11 185,49 | Equipment failure (breakdowns) | Time between events | 185 hours | Single extractor |
ElbowElbowShow verbatim quote (Table 4)Elbow 4 510,1 | Equipment failure (breakdowns) | Time between events | 510 hours | Single extractor |
Flange PipeFlange PipeShow verbatim quote (Table 4)Flange Pipe 4 510,1 | Equipment failure (breakdowns) | Time between events | 510 hours | Single extractor |
PipePipeShow verbatim quote (Table 4)Pipe 3 680,13 | Equipment failure (breakdowns) | Time between events | 680 hours | Single extractor |
Ball ValveBall ValveShow verbatim quote (Table 4)Ball Valve 2 1020,2 | Equipment failure (breakdowns) | Time between events | 1,020 hours | Single extractor |
Nozzle CondensatNozzle CondensatShow verbatim quote (Table 4)Nozzle Condensat 2 1020,2 | Equipment failure (breakdowns) | Time between events | 1,020 hours | Single extractor |
LinerLinerShow verbatim quote (Table 4)Liner 2 1020,2 | Equipment failure (breakdowns) | Time between events | 1,020 hours | Single extractor |
ActuatorActuatorShow verbatim quote (Table 4)Actuator 2 1020,2 | Equipment failure (breakdowns) | Time between events | 1,020 hours | Single extractor |
Valve ExhaustValve ExhaustShow verbatim quote (Table 4)Valve Exhaust 2 1020,2 | Equipment failure (breakdowns) | Time between events | 1,020 hours | Single extractor |
Valve CondensatValve CondensatShow verbatim quote (Table 4)Valve Condensat 1 2040 | Equipment failure (breakdowns) | Time between events | 2,040 hours | Single extractor |
Streiner ValveStreiner ValveShow verbatim quote (Table 4)Streiner Valve 1 2040 | Equipment failure (breakdowns) | Time between events | 2,040 hours | Single extractor |
Packing FlangePacking FlangeShow verbatim quote (Table 4)Packing Flange 1 2040 | Equipment failure (breakdowns) | Time between events | 2,040 hours | Single extractor |
—Show verbatim quote (Table 2)July 2020 20 | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 20.0 h | Single extractor |
—Show verbatim quote (Table 2)August 2020 15 | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 15.0 h | Single extractor |
Observation units
- Horizontal Sterilizer · Sterilization (retort, UHT) · Baseline