Enhancing Operational Effectiveness in a Beverage Bottling SME through SMED, 5S, and TPM Maintenance Practices

Open source

1Bibliographic record

Authors
Diana Stella Rossi-Huamán, Billy Manfred Tecse-Villacorta, Richard Nicholas Meza-Ortiz
Year
2025
Venue
International Journal of Industrial Engineering
Country
Peru
Segment
Soft drinks, bottled water and juices
Process family
Filling and packaging line
Study type
Before/after intervention
Extraction scope
Full text
Size
1 plants · 1 lines · — machines
Observation period
120 days
Data collection
not_reported
Intervention
Show the setting as described by the study
The company specializes in the production and commercialization of carbonated and energy drinks, sustaining more than twelve years of market presence.

2Risk of bias

Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 11Moderate risk
ItemScore
Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product, process and equipment are all described.2 / 2
Is the observation period long enough and reported?Period reported and at least 30 days of production (or at least 100 recorded events).2 / 2
How were loss data collected?Interviews, estimates, or method not reported.0 / 2
Are OEE, loading time and the loss categories defined explicitly?No definition; metrics are reported as bare numbers.0 / 2
Does the loss breakdown account for the total loss it claims to explain?The reported causes or categories sum to at least 90% of the stated total, or an explicit "other" class closes the balance.2 / 2
Is there evidence of selective reporting of favourable results?Observational study, or intervention study that reports baseline and post-intervention data with the same method.2 / 2
Are the reported numbers internally consistent?Small inconsistencies (2 to 10 percentage points) or values that cannot be cross-checked.1 / 2
Could conflicts of interest or the source of the data bias the result?Academic or independent study, or conflicts declared and unrelated to the result.2 / 2

3Extracted data

Each datum with its classification and the verbatim quote that states it.
Reported causeLoss categoryMetricValueExtraction
—
Show verbatim quote (Section 4.3.4 TPM: Enhancing Reliability through Preventive and Autonomous Maintenance)
Overall Equipment Effectiveness (OEE) rose from 61% to 79%, and the defect rate experienced a 22% contraction.
noneOEE79.0 %Both extractors agreed
—
Show verbatim quote (Section 4.3.4 TPM: Enhancing Reliability through Preventive and Autonomous Maintenance)
Overall Equipment Effectiveness (OEE) rose from 61% to 79%, and the defect rate experienced a 22% contraction.
noneOEE61.0 %Both extractors agreed
the necessity for product reprocessing
Show verbatim quote (Section 4.2 Initial Diagnosis)
Detailed decomposition of the shortfall reveals that parasitic machine velocity losses exert a 47% share on ineffective output, protracted repair durations 34%, and the necessity for product reprocessing 19%.
Process defects (scrap and rework)Share of lost time19.0 %Both extractors agreed
protracted repair durations
Show verbatim quote (Section 4.2 Initial Diagnosis)
Detailed decomposition of the shortfall reveals that parasitic machine velocity losses exert a 47% share on ineffective output, protracted repair durations 34%, and the necessity for product reprocessing 19%.
Equipment failure (breakdowns)Share of lost time34.0 %Both extractors agreed
parasitic machine velocity losses
Show verbatim quote (Section 4.2 Initial Diagnosis)
Detailed decomposition of the shortfall reveals that parasitic machine velocity losses exert a 47% share on ineffective output, protracted repair durations 34%, and the necessity for product reprocessing 19%.
Reduced speedShare of lost time47.0 %Both extractors agreed
—
Show verbatim quote (Table 2. Validation Results of the Lean-TPM Maintenance Model)
Effectiveness % 68% 95% 90% 32.35%
nonePerformance68.0 %Single extractor
—
Show verbatim quote (Table 2. Validation Results of the Lean-TPM Maintenance Model)
Effectiveness % 68% 95% 90% 32.35%
nonePerformance90.0 %Single extractor
—
Show verbatim quote (Section 4.3.4)
The Mean Time Between Failures (MTBF) increased by 31%
Equipment failure (breakdowns)Time between events31.0 %Single extractor
—
Show verbatim quote (Section 4.3.4)
The Mean Time to Repair (MTTR) decreased by 25%
Equipment failure (breakdowns)Mean event duration-25.0 %Single extractor
—
Show verbatim quote (Section 4.3.4)
The incidence of breakdowns decreased by 68%
Equipment failure (breakdowns)Number of events-68.0 %Single extractor
—
Show verbatim quote (Section 4.3.4)
the defect rate experienced a 22% contraction
Process defects (scrap and rework)Defect rate-22.0 %Single extractor

Observation units

  • SME bottling line · Whole line or unspecified equipment · After intervention
  • SME bottling line · Whole line or unspecified equipment · Baseline
  • Bottling line · Whole line or unspecified equipment · After intervention