Process defects (scrap and rework)

Rework of off-specification product

Process defects (scrap and rework)QualityWhole line or unspecified equipment

In short

It appears in about 2 of every 100 lines studied.

When it appears, it takes on average about 46 % of the line's lost time. Reported by 5 of the 127 studies that could observe it (good evidence).

What happens

Product or packages produced during stable running fail to meet weight, fill, seal, appearance or other quality specifications at first pass and must be diverted for reprocessing, re-filling, re-labeling or re-packing instead of being accepted as good output. The underlying root causes can be process drift, material variability or minor equipment misadjustment, but the loss itself is the material, time and capacity consumed in recovering the units rather than scrapping them.

What is done about it

Tighten process control (fill weight, seal temperature/pressure, closure torque) through SPC and automatic feedback loops to reduce the generation of off-spec units at the source, and standardize rework procedures with clear acceptance criteria to minimize the handling time per diverted unit. Root-cause the recurring defect types feeding rework and address them through equipment calibration, material qualification or operator training rather than relying on downstream recovery.

Practical guidance written from engineering knowledge; it is not a statistical estimate.

1Probability and evidence

Pooled over all segments. A wide interval is a result: it states how much the evidence allows us to know.
Probability of presence
1.5% [0.5–3.4%]
Expected share of lost time
0.7% [0.2–1.6%]
Share of lost time when present
46% [35–57%]
Studies / units
127 / 161
Evidence grade
B

Grade B: 5 to 9 studies, or an interval width between 0.20 and 0.35.

2Probability by segment

Partially pooled estimates for each industry segment.
  • Dairy products
    1.6% [0.3–4.9%]13 studies
  • Soft drinks, bottled water and juices
    1.8% [0.4–5.0%]26 studies
  • Brewing, wine and spirits
    4.3% [0.8–12.7%]11 studies
  • Bakery and pasta
    1.4% [0.2–3.8%]24 studies
  • Meat, poultry and seafood
    1.6% [0.2–5.2%]9 studies
  • Fruit and vegetable processing
    1.7% [0.2–5.4%]7 studies
  • Grain and oilseed milling
    1.7% [0.3–5.3%]6 studies
  • Sugar and confectionery
    2.2% [0.4–6.8%]9 studies
  • Snacks, coffee, tea and other foods
    1.7% [0.2–5.5%]5 studies
  • Animal feed and pet food
    1.6% [0.3–5.0%]7 studies
  • Food manufacturing (unspecified or mixed)
    1.6% [0.2–5.2%]10 studies

3Mechanism, SCADA signature and countermeasure

Engineering guidance that helps recognise and address the cause; it is not part of the statistical estimate.

Mechanism

Engineering guidance

Product or packages produced during stable running fail to meet weight, fill, seal, appearance or other quality specifications at first pass and must be diverted for reprocessing, re-filling, re-labeling or re-packing instead of being accepted as good output. The underlying root causes can be process drift, material variability or minor equipment misadjustment, but the loss itself is the material, time and capacity consumed in recovering the units rather than scrapping them.

How it looks in SCADA data

Engineering guidance

MES/quality modules show elevated counts of units flagged as rework or rejected-but-recoverable, often tied to a diversion or reject-lane actuator cycling, with a parallel rework or reprocessing line showing increased throughput and run time. Checkweigher, vision or seal-tester reject counters rise while overall line OEE availability stays largely unaffected, concentrating the loss in the quality/yield metric rather than in downtime.

Countermeasure

Engineering guidance

Tighten process control (fill weight, seal temperature/pressure, closure torque) through SPC and automatic feedback loops to reduce the generation of off-spec units at the source, and standardize rework procedures with clear acceptance criteria to minimize the handling time per diverted unit. Root-cause the recurring defect types feeding rework and address them through equipment calibration, material qualification or operator training rather than relying on downstream recovery.

4Sources

Every extracted datum with its study, value and verbatim quote.
  1. Share of planned time: 0 % · as reported: “Rework Losses”
    Show verbatim quote
    Rata-Rata 0,099271 9,29814 30,74813 0,00000 0,00000 0,13414
  2. Number of events: 4.00 Boxes x 12 · as reported: “Rework”
    Show verbatim quote
    Rework Average 7 4
  3. Number of events: 7.00 Boxes x 12 · as reported: “Rework”
    Show verbatim quote
    Rework Average 7 4
  4. Share of lost time: 14.0 % · as reported: “reprocessing”
    Show verbatim quote
    Among the main causes identified, errors in the conduct of operations accounted for 39.20%, reprocessing constituted 13.95%, and process shutdowns due to machine failures covered 46.85%.
  5. Share of lost time: 0 % · as reported: “Rework Losses”
    Show verbatim quote
    Rata-Rata 0,099271 9,29814 30,74813 0,00000 0,00000 0,13414
  6. Share of lost time: 14.0 % · as reported: “reprocessing”
    Show verbatim quote
    errors in the conduct of operations accounted for 39.20%, reprocessing constituted 13.95%, and process shutdowns due to machine failures covered 46.85%.
  7. Defect rate: 12.0 % · as reported: “reprocessing”
    Show verbatim quote
    The main issues concerning the product process include 25% of incorrectly labeled bottles, 18% of improperly sealed bottles, and 12% of reprocessing in the current alcoholic beverage production process.
  8. Share of lost time: 22.0 % · as reported: “Rework Losses”
    Show verbatim quote
    Rework Losses 8.890 29.095 22% 72%
  9. Lost time: 8,890 Minutes · as reported: “Rework Losses”
    Show verbatim quote
    Rework Losses 8.890 29.095 22% 72%
  10. Share of lost time: 19.0 % · as reported: “the necessity for product reprocessing”
    Show verbatim quote
    Detailed decomposition of the shortfall reveals that parasitic machine velocity losses exert a 47% share on ineffective output, protracted repair durations 34%, and the necessity for product reprocessing 19%.
  11. Defect rate: 19.0 % · as reported: “rework”
    Show verbatim quote
    In the initial process diagnosis, an inefficiency level of 19% was identified, reflecting high variability, rework, and bottlenecks.
  12. Defect rate: 13.0 % · as reported: “rework”
    Show verbatim quote
    With the validation of the pilot test, this value was reduced to 13%, representing a relative improvement of 32% compared to the initial condition.
  13. Defect rate: 25.0 % · as reported: “reprocessing”
    Show verbatim quote
    Reprocessing: 25% → 5%
  14. Defect rate: 5.00 % · as reported: “reprocessing”
    Show verbatim quote
    Reprocessing: 25% → 5%
  15. Lost time: 0 menit · as reported: “Rework Loss”
    Show verbatim quote
    Rework Loss 0 0% 100%
  16. Lost time: 0 menit · as reported: “Rework Loss”
    Show verbatim quote
    Rework Loss 0 0% 100%