Analisis Efisiensi Mesin Produksi Forming Machine Pada Cv. Agrindo Supra Food Menggunakan Metode OEE

Open source

1Bibliographic record

Authors
Dedi Setiawan, Ari Zaqi Al-Faritsy
Year
2026
Venue
JURNAL ILMIAH RESEARCH STUDENT
DOI
—
Country
Indonesia
Segment
Fruit and vegetable processing
Process family
Forming, baking and cooking
Study type
Single case study
Extraction scope
Full text
Size
1 plants · 1 lines · 1 machines
Observation period
92 days
Data collection
manual_logs
Intervention
Show the setting as described by the study
CV. Agrindo Supra Food merupakan perusahaan agroindustri di Bantul, Yogyakarta, yang memproduksi nata de coco.

2Risk of bias

Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 11Moderate risk
ItemScore
Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product or sector is given but the equipment or process is only partly described.1 / 2
Is the observation period long enough and reported?Period reported and at least 30 days of production (or at least 100 recorded events).2 / 2
How were loss data collected?Manual logs or maintenance records with unknown completeness.1 / 2
Are OEE, loading time and the loss categories defined explicitly?A standard definition is cited but its application is not shown.1 / 2
Does the loss breakdown account for the total loss it claims to explain?The reported causes or categories sum to at least 90% of the stated total, or an explicit "other" class closes the balance.2 / 2
Is there evidence of selective reporting of favourable results?Observational study, or intervention study that reports baseline and post-intervention data with the same method.2 / 2
Are the reported numbers internally consistent?Inconsistencies above 10 percentage points, or OEE factors above 100%.0 / 2
Could conflicts of interest or the source of the data bias the result?Academic or independent study, or conflicts declared and unrelated to the result.2 / 2

3Extracted data

Each datum with its classification and the verbatim quote that states it.
Reported causeLoss categoryMetricValueExtraction
—Forming Machine
Show verbatim quote (Conclusion / Table 6)
Hasil perhitungan menunjukkan rata-rata Availability Rate sebesar 65,05%, Performance Rate sebesar 98,87%, dan Quality Rate sebesar 75,94%, sehingga diperoleh nilai rata-rata Overall Equipment Effectiveness (OEE) sebesar 42%.
noneAvailability65.1 %Single extractor
—Forming Machine
Show verbatim quote (Conclusion / Table 8)
Hasil perhitungan menunjukkan rata-rata Availability Rate sebesar 65,05%, Performance Rate sebesar 98,87%, dan Quality Rate sebesar 75,94%, sehingga diperoleh nilai rata-rata Overall Equipment Effectiveness (OEE) sebesar 42%.
nonePerformance98.9 %Single extractor
—Forming Machine
Show verbatim quote (Conclusion / Table 9)
Hasil perhitungan menunjukkan rata-rata Availability Rate sebesar 65,05%, Performance Rate sebesar 98,87%, dan Quality Rate sebesar 75,94%, sehingga diperoleh nilai rata-rata Overall Equipment Effectiveness (OEE) sebesar 42%.
noneQuality75.9 %Single extractor
—Forming Machine
Show verbatim quote (Conclusion / Table 11)
Hasil perhitungan menunjukkan rata-rata Availability Rate sebesar 65,05%, Performance Rate sebesar 98,87%, dan Quality Rate sebesar 75,94%, sehingga diperoleh nilai rata-rata Overall Equipment Effectiveness (OEE) sebesar 42%.
noneOEE42.0 %Single extractor
breakdownForming Machine
Show verbatim quote (Table 4 Data Downtime)
rata-rata 3.564 193,25 3.757,25
Equipment failure (breakdowns)Lost time3,564 menitSingle extractor
setupForming Machine
Show verbatim quote (Table 4 Data Downtime)
rata-rata 3.564 193,25 3.757,25
Setup and adjustmentsLost time193 menitSingle extractor
downtimeForming Machine
Show verbatim quote (Table 4 Data Downtime)
rata-rata 3.564 193,25 3.757,25
Not classifiable from the reportLost time3,757 menitSingle extractor
rantai putusForming Machine
Show verbatim quote (Latar Belakang (Introduction))
Dalam satu bulan, tercatat 2 hingga 3 kali kejadian rantai putus dengan rata-rata waktu penanganan sekitar 30 menit per kejadian, serta 10 hingga 15 kali kegiatan perawatan pada pir penggerak dengan rata-rata waktu perbaikan 15 menit.
Equipment failure (breakdowns)Mean event duration30.0 menitSingle extractor
pir penggerakForming Machine
Show verbatim quote (Latar Belakang (Introduction))
Dalam satu bulan, tercatat 2 hingga 3 kali kejadian rantai putus dengan rata-rata waktu penanganan sekitar 30 menit per kejadian, serta 10 hingga 15 kali kegiatan perawatan pada pir penggerak dengan rata-rata waktu perbaikan 15 menit.
Equipment failure (breakdowns)Mean event duration15.0 menitSingle extractor

Observation units

  • Forming Machine · Forming, moulding and depositing · Baseline