Eingeschlossene Studie
CHANGEOVER TIME REDUCTION THROUGH LEAN TOOL “SMED” – A CASE STUDY FROM FOOD SECTOR
1Bibliografische Angaben
- Autoren
- Kateřina Gálová
- Jahr
- 2018
- Publikationsorgan
- International Bata Conference for Ph.D. Students and Young Researchers (DOKBAT)
- Land
- Czech Republic
- Segment
- Zucker und Süßwaren
- Prozessfamilie
- Formen, Backen und Garen
- Studientyp
- Vorher-nachher-Intervention
- Extraktionsumfang
- Volltext
- Umfang
- 1 Werke · 5 Linien · — Maschinen
- Beobachtungszeitraum
- 365 Tage
- Datenerhebung
- automatic_monitoring
- Intervention
Umfeld laut Studie anzeigen
The plant itself, in which the case study was processed, focuses on the production of chocolate and chocolate confectionery.
2Verzerrungsrisiko
Bewertet nach dem Schema des Protokolls: 2 geringe Bedenken, 1 einige Bedenken, 0 hohe Bedenken.
Gesamtpunktzahl 10Mittleres Risiko
| Kriterium | Punkte |
|---|---|
| Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product, process and equipment are all described. | 2 / 2 |
| Is the observation period long enough and reported?Period reported but shorter than 30 days, or only the number of shifts is given. | 1 / 2 |
| How were loss data collected?Manual logs or maintenance records with unknown completeness. | 1 / 2 |
| Are OEE, loading time and the loss categories defined explicitly?A standard definition is cited but its application is not shown. | 1 / 2 |
| Does the loss breakdown account for the total loss it claims to explain?Only the top causes are reported and the unexplained remainder can be computed. | 1 / 2 |
| Is there evidence of selective reporting of favourable results?Observational study, or intervention study that reports baseline and post-intervention data with the same method. | 2 / 2 |
| Are the reported numbers internally consistent?Small inconsistencies (2 to 10 percentage points) or values that cannot be cross-checked. | 1 / 2 |
| Could conflicts of interest or the source of the data bias the result?Authors are employees of the plant or of an equipment/software vendor; no declaration. | 1 / 2 |
3Extrahierte Daten
Jeder Datenpunkt mit seiner Einordnung und dem wörtlichen Zitat, das ihn belegt.
| Berichtete Ursache | Verlustkategorie | Kennzahl | Wert | Extraktion |
|---|---|---|---|---|
—Wörtliches Zitat anzeigen (Section 4.2 Actual impacts of the project, p.111)Savings in the form of released production were 21 tons / year. | none | Durchsatz | 21,0 tons/year | Beide Extraktionen übereinstimmend |
Internal activitiesWörtliches Zitat anzeigen (Section 4.2, Figure 9, p.111)Internal activities occupied 83% of the total time. | Rüsten und Einstellen | Anteil an der Verlustzeit | 83,0 % | Beide Extraktionen übereinstimmend |
changeover (selected type, average, long-run)Wörtliches Zitat anzeigen (Section 4.2 Actual impacts of the project, p.111)The new changeover time was even lower than the project goal, but in the long run, the time was 210 minutes. This time is kept without any major problems. | Rüsten und Einstellen | Mittlere Ereignisdauer | 210 min | Beide Extraktionen übereinstimmend |
changeover (selected type, annual frequency)Wörtliches Zitat anzeigen (Section 4.2, p.109)At a frequency of 58 changeovers per year and with a given number of operators and wage rates, the annual savings would be 91 thousand. CZK. | Rüsten und Einstellen | Anzahl der Ereignisse | 58,0 events/year | Beide Extraktionen übereinstimmend |
changeover (selected type, average)Wörtliches Zitat anzeigen (Section 4.2 Specification of the project objective, p.109)The project team decided on the main goal of the project, which was to reduce the time of the selected sort by 10% of the average changeover time, from 244 minutes to 220 minutes. | Rüsten und Einstellen | Mittlere Ereignisdauer | 244 min | Beide Extraktionen übereinstimmend |
Planned stoppagesWörtliches Zitat anzeigen (Section 4.1 / Figure 4, p.108)It is clear from the chart that the most important were planned stoppages with total time 10184 hours. | Geplanter Stillstand (geplante Instandhaltung, Pausen, keine Nachfrage) | Verlustzeit | 10.184 hours | Einfache Extraktion |
Planned stoppagesWörtliches Zitat anzeigen (Section 5 Conclusion, p.113)Plates fall into planned stoppages, accounting for 61% of all stoppages of the company. | Geplanter Stillstand (geplante Instandhaltung, Pausen, keine Nachfrage) | Anteil an der Verlustzeit | 61,0 % | Einfache Extraktion |
ChangeoversWörtliches Zitat anzeigen (Section 5 Conclusion, p.113)Changeovers on a particular selected line then account for a total of 77% of all planned stoppages on this line. | Rüsten und Einstellen | Anteil an der Verlustzeit | 77,0 % | Einfache Extraktion |
changeover (most frequent type)Wörtliches Zitat anzeigen (Section 4.1, Figure 8, p.109)Of these types of changeovers, the fourth longest changeover was the most frequent (which would take 185 minutes), but the longest and second most frequent type of changeover (240 minutes) was eventually chosen by project team for the next step. | Rüsten und Einstellen | Mittlere Ereignisdauer | 185 min | Einfache Extraktion |
changeover (selected type for SMED project)Wörtliches Zitat anzeigen (Section 4.1, Figure 8, p.109)Of these types of changeovers, the fourth longest changeover was the most frequent (which would take 185 minutes), but the longest and second most frequent type of changeover (240 minutes) was eventually chosen by project team for the next step. | Rüsten und Einstellen | Mittlere Ereignisdauer | 240 min | Einfache Extraktion |
External activitiesWörtliches Zitat anzeigen (Figure 9, p.111)internal; 83% external; 17% breakdown; 6% Figure 9 Internal vs external activities. Source: own | Rüsten und Einstellen | Anteil an der Verlustzeit | 17,0 % | Einfache Extraktion |
breakdown (within changeover)valveWörtliches Zitat anzeigen (Figure 9, p.111)internal; 83% external; 17% breakdown; 6% Figure 9 Internal vs external activities. Source: own | Anlagenausfall (Störungen) | Anteil an der Verlustzeit | 6,00 % | Einfache Extraktion |
changeover (selected type, average, first re-measurement)Wörtliches Zitat anzeigen (Section 4.2 Actual impacts of the project, p.111)The average throw time dropped from 244 minutes to 194 minutes (Figure 7) and the target was met. | Rüsten und Einstellen | Mittlere Ereignisdauer | 194 min | Einfache Extraktion |
Flushing massesWörtliches Zitat anzeigen (Table 6 (Changeover activities))Flushing masses: 0:39:00 | Rüsten und Einstellen | Mittlere Ereignisdauer | 39,0 min | Einfache Extraktion |
Dismantling the dividerWörtliches Zitat anzeigen (Table 6 (Changeover activities))Dismantling the divider: 0:28:00 | Rüsten und Einstellen | Mittlere Ereignisdauer | 28,0 min | Einfache Extraktion |
Assembly of dividersWörtliches Zitat anzeigen (Table 6 (Changeover activities))Assembly of dividers: 0:22:00 | Rüsten und Einstellen | Mittlere Ereignisdauer | 22,0 min | Einfache Extraktion |
Valve failureWörtliches Zitat anzeigen (Table 6 (Changeover activities))Valve failure: 0:13:00 | Rüsten und Einstellen | Mittlere Ereignisdauer | 13,0 min | Einfache Extraktion |
Flush with butterWörtliches Zitat anzeigen (Table 6 (Changeover activities))Flush with butter: 0:06:00 | Rüsten und Einstellen | Mittlere Ereignisdauer | 6,00 min | Einfache Extraktion |
Exchange of moldsWörtliches Zitat anzeigen (Table 6 (Changeover activities))Exchange of molds: 0:04:00 | Rüsten und Einstellen | Mittlere Ereignisdauer | 4,00 min | Einfache Extraktion |
Forming of moldsWörtliches Zitat anzeigen (Table 6 (Changeover activities))Forming of molds: 0:07:00 | Rüsten und Einstellen | Mittlere Ereignisdauer | 7,00 min | Einfache Extraktion |
Blowing the front of the bassWörtliches Zitat anzeigen (Table 6 (Changeover activities))Blowing the front of the bass: 0:06:00 | Rüsten und Einstellen | Mittlere Ereignisdauer | 6,00 min | Einfache Extraktion |
Start of productionWörtliches Zitat anzeigen (Table 6 (Changeover activities))Start of production: 0:03:00 | Rüsten und Einstellen | Mittlere Ereignisdauer | 3,00 min | Einfache Extraktion |
First good formWörtliches Zitat anzeigen (Table 6 (Changeover activities))First good form: 0:03:00 | Rüsten und Einstellen | Mittlere Ereignisdauer | 3,00 min | Einfache Extraktion |
First good productWörtliches Zitat anzeigen (Table 6 (Changeover activities))First good product: 0:27:00 | Rüsten und Einstellen | Mittlere Ereignisdauer | 27,0 min | Einfache Extraktion |
—Wörtliches Zitat anzeigen (Section 4.2, Table 8 (Financial impact of the project))At a frequency of 58 changeovers per year and with a given number of operators and wage rates, the annual savings would be 91 thousand. CZK. | Rüsten und Einstellen | Anzahl der Ereignisse | 58,0 events | Einfache Extraktion |
Beobachtungseinheiten
- D1 line · Formen, Gießen und Dosieren · Nach der Intervention
- D1 line · Formen, Gießen und Dosieren · Ausgangslage
- Whole plant · Gesamte Linie oder nicht spezifizierte Anlage · Ausgangslage