Setup and adjustments

Changeover disassembly, cleaning and reassembly of machine parts

Setup and adjustmentsAvailabilityWhole line or unspecified equipment

In short

It appears in about 1 of every 100 lines studied.

When it appears, it takes on average about 57 % of the line's lost time. Reported by 2 of the 127 studies that could observe it (limited evidence).

What happens

At a product or format changeover the line must be stopped so that contact parts and tooling can be unbolted, taken off the machine, cleaned or sanitised to remove residual product and allergens, and then refitted and aligned before the next run can start. This manual, sequential work occupies the whole changeover window and keeps the line in a non-productive setup state until the first good unit is produced.

What is done about it

Apply SMED principles to convert internal tasks into external ones prepared in advance, standardise and pre-stage clean tooling sets, use quick-release fasteners and modular contact parts, and sequence or parallelise disassembly, cleaning and reassembly steps with trained changeover crews to shorten the non-productive window.

Practical guidance written from engineering knowledge; it is not a statistical estimate.

1Probability and evidence

Pooled over all segments. A wide interval is a result: it states how much the evidence allows us to know.
Probability of presence
0.7% [0.2–1.8%]
Expected share of lost time
0.4% [0.1–1.0%]
Share of lost time when present
57% [46–67%]
Studies / units
127 / 161
Evidence grade
C

Grade C: 2 to 4 studies, or an interval wider than 0.35.

2Probability by segment

Partially pooled estimates for each industry segment.
  • Dairy products
    0.8% [0.1–2.8%]13 studies
  • Soft drinks, bottled water and juices
    0.7% [0.1–2.2%]26 studies
  • Brewing, wine and spirits
    0.8% [0.1–2.7%]11 studies
  • Bakery and pasta
    0.7% [0.1–2.3%]24 studies
  • Meat, poultry and seafood
    0.8% [0.1–2.6%]9 studies
  • Fruit and vegetable processing
    0.8% [0.1–2.9%]7 studies
  • Grain and oilseed milling
    0.8% [0.1–2.9%]6 studies
  • Sugar and confectionery
    0.8% [0.1–2.8%]9 studies
  • Snacks, coffee, tea and other foods
    1.2% [0.2–4.1%]5 studies
  • Animal feed and pet food
    1.2% [0.1–3.7%]7 studies
  • Food manufacturing (unspecified or mixed)
    0.8% [0.1–2.9%]10 studies

3Mechanism, SCADA signature and countermeasure

Engineering guidance that helps recognise and address the cause; it is not part of the statistical estimate.

Mechanism

Engineering guidance

At a product or format changeover the line must be stopped so that contact parts and tooling can be unbolted, taken off the machine, cleaned or sanitised to remove residual product and allergens, and then refitted and aligned before the next run can start. This manual, sequential work occupies the whole changeover window and keeps the line in a non-productive setup state until the first good unit is produced.

How it looks in SCADA data

Engineering guidance

MES/SCADA shows an extended machine-state period classified as changeover or setup, bounded by the last good unit of the previous order and the first good unit of the next, with no production counts advancing; operators log manual start/stop events for disassembly, cleaning and reassembly steps, and the duration correlates with format or recipe change events rather than with fault alarms.

Countermeasure

Engineering guidance

Apply SMED principles to convert internal tasks into external ones prepared in advance, standardise and pre-stage clean tooling sets, use quick-release fasteners and modular contact parts, and sequence or parallelise disassembly, cleaning and reassembly steps with trained changeover crews to shorten the non-productive window.

4Sources

Every extracted datum with its study, value and verbatim quote.
  1. Lost time: 660 min · as reported: “Production machines dissembling, cleaning and assembling”
    Show verbatim quote
    Production machines dissembling, cleaning and assembling 660 minutes
  2. Mean event duration: 4.04 min · as reported: “Disassemble parts of inactive equipment”
    Show verbatim quote
    Disassemble parts of inactive equipment 4.04 Internal External
  3. Lost time: 4.04 min · as reported: “Disassemble parts of inactive equipment”
    Show verbatim quote
    Disassemble parts of inactive equipment 4.04