In short
It appears in about 1 of every 100 lines studied.
When it appears, it takes on average about 56 % of the line's lost time. Reported by 2 of the 120 studies that could observe it (limited evidence).
What happens
A product or format change on the filling machine requires removing and fitting the weight/format-specific tooling (nozzles, guides, change parts) before production can resume, with the task performed either by a single operator or split between two operators working in parallel. The mechanical disassembly, part swap, reassembly and verification steps keep the machine in a non-productive changeover state regardless of crew size, though staffing affects how long the state lasts.
What is done about it
Standardize the retooling procedure with quick-change/tool-less fittings, pre-kit the change parts, and apply parallel/split-task methods (SMED) with an additional operator to shorten the changeover window. Train crews on a documented sequence and verify setup with a go/no-go check before restart.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 0.7% [0.2–1.9%]
- Expected share of lost time
- 0.4% [0.1–1.1%]
- Share of lost time when present
- 56% [43–67%]
- Studies / units
- 120 / 162
- Evidence grade
- C
Grade C: 2 to 4 studies, or an interval wider than 0.35.
2Probability by segment
- Dairy products0.8% [0.1–2.7%]18 studies
- Soft drinks, bottled water and juices0.6% [0.1–1.9%]44 studies
- Brewing, wine and spirits0.8% [0.1–2.6%]16 studies
- Bakery and pasta0.9% [0.1–3.3%]0 studies
- Meat, poultry and seafood1.7% [0.2–5.9%]6 studies
- Fruit and vegetable processing0.8% [0.1–3.1%]4 studies
- Grain and oilseed milling0.8% [0.1–2.9%]6 studies
- Sugar and confectionery0.8% [0.1–3.2%]3 studies
- Snacks, coffee, tea and other foods0.8% [0.1–3.1%]6 studies
- Animal feed and pet food0.8% [0.1–3.1%]4 studies
- Food manufacturing (unspecified or mixed)0.8% [0.1–2.9%]13 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceA product or format change on the filling machine requires removing and fitting the weight/format-specific tooling (nozzles, guides, change parts) before production can resume, with the task performed either by a single operator or split between two operators working in parallel. The mechanical disassembly, part swap, reassembly and verification steps keep the machine in a non-productive changeover state regardless of crew size, though staffing affects how long the state lasts.
How it looks in SCADA data
Engineering guidanceMES/SCADA shows the filler in a changeover or setup machine-state between the last good unit of the previous run and the first good unit of the new run, with no cycle counts incrementing. Duration of this state varies with the number of operators logged against the changeover task, and downstream conveyors/accumulators show starvation during the whole window.
Countermeasure
Engineering guidanceStandardize the retooling procedure with quick-change/tool-less fittings, pre-kit the change parts, and apply parallel/split-task methods (SMED) with an additional operator to shorten the changeover window. Train crews on a documented sequence and verify setup with a go/no-go check before restart.
4Sources
- Mean event duration: 11.5 min · as reported: “retooling (two workers, parallel operations)”
Show verbatim quote
The time of retooling was reduced from 17.5 minutes to 11.5 minutes.
- Mean event duration: 17.5 min · as reported: “retooling (one worker)”
Show verbatim quote
The total time of retooling using one worker (Current state in Fig. 9) is 17.5 minutes involving 9 activities (A,B,C,D,E,F,G,H,I).
- Using Lean Manufacturing Approach for Improvement in Food Manufacturing: Case Study from Egypt (2024)Open sourceLost time: 2.00 min · as reported: “Transport die to the machine”
Show verbatim quote
Transport die to the machine 2 min 4 min External
- Using Lean Manufacturing Approach for Improvement in Food Manufacturing: Case Study from Egypt (2024)Open sourceLost time: 5.00 min · as reported: “Program the machine”
Show verbatim quote
Program the machine 5 min 15 min Internal
- Using Lean Manufacturing Approach for Improvement in Food Manufacturing: Case Study from Egypt (2024)Open sourceLost time: 6.00 min · as reported: “Change machine die”
Show verbatim quote
Change machine die 6 min 10 min Internal
- Using Lean Manufacturing Approach for Improvement in Food Manufacturing: Case Study from Egypt (2024)Open sourceShare of lost time: 33.0 % · as reported: “Change machine die”
Show verbatim quote
The total changeover time is 18 min and changing the die takes almost 33% of this time while programming the machine takes 27%.
- Using Lean Manufacturing Approach for Improvement in Food Manufacturing: Case Study from Egypt (2024)Open sourceShare of lost time: 27.0 % · as reported: “Program the machine”
Show verbatim quote
The total changeover time is 18 min and changing the die takes almost 33% of this time while programming the machine takes 27%.
- Using Lean Manufacturing Approach for Improvement in Food Manufacturing: Case Study from Egypt (2024)Open sourceLost time: 2.00 min · as reported: “Transport die to the machine”
Show verbatim quote
Transport die to the machine | 2 min | 4 min | External
- Using Lean Manufacturing Approach for Improvement in Food Manufacturing: Case Study from Egypt (2024)Open sourceLost time: 2.00 min · as reported: “Change machine die”
Show verbatim quote
Change machine die | 2 min | 6 min | Internal
- Using Lean Manufacturing Approach for Improvement in Food Manufacturing: Case Study from Egypt (2024)Open sourceLost time: 1.00 min · as reported: “Programming machine”
Show verbatim quote
Programming machine | 1 min | 8 min | Internal