1Bibliographic record
- Authors
- Malek Miguel Maalouf, Magdalena Zaduminska
- Year
- 2019
- Venue
- Management and Production Engineering Review
- Country
- Denmark
- Segment
- Meat, poultry and seafood
- Process family
- Filling and packaging line
- Study type
- Single case study
- Extraction scope
- Full text
- Size
- 1 plants · 1 lines · 1 machines
- Observation period
- 365 days
- Data collection
- manual_logs
- Intervention
Show the setting as described by the study
Line 1 produces a family of products called “herring salad” in jars and plastic buckets, of two ˛ avors and di´erent sizes.
2Risk of bias
Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 11Moderate risk
| Item | Score |
|---|---|
| Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product, process and equipment are all described. | 2 / 2 |
| Is the observation period long enough and reported?Period reported and at least 30 days of production (or at least 100 recorded events). | 2 / 2 |
| How were loss data collected?Manual logs or maintenance records with unknown completeness. | 1 / 2 |
| Are OEE, loading time and the loss categories defined explicitly?No definition; metrics are reported as bare numbers. | 0 / 2 |
| Does the loss breakdown account for the total loss it claims to explain?The reported causes or categories sum to at least 90% of the stated total, or an explicit "other" class closes the balance. | 2 / 2 |
| Is there evidence of selective reporting of favourable results?Intervention study in which baseline and post-intervention periods differ in length or method. | 1 / 2 |
| Are the reported numbers internally consistent?Recomputed totals, shares and OEE factors agree with the reported values within 2 percentage points. | 2 / 2 |
| Could conflicts of interest or the source of the data bias the result?Authors are employees of the plant or of an equipment/software vendor; no declaration. | 1 / 2 |
3Extracted data
Each datum with its classification and the verbatim quote that states it.
| Reported cause | Loss category | Metric | Value | Extraction |
|---|---|---|---|---|
retooling (two workers, parallel operations)Multi-Weight machineShow verbatim quote (Outcomes of SMED implementation section / Fig. 9)The time of retooling was reduced from 17.5 minutes to 11.5 minutes. | Setup and adjustments | Mean event duration | 11.5 min | Both extractors agreed |
retooling (one worker)Multi-Weight machineShow verbatim quote (Implementation (future state) section / Fig. 9)The total time of retooling using one worker (Current state in Fig. 9) is 17.5 minutes involving 9 activities (A,B,C,D,E,F,G,H,I). | Setup and adjustments | Mean event duration | 17.5 min | Both extractors agreed |
machine breakdownsShow verbatim quote (Changeover data analysis section / Fig. 5)Changeovers consumed 536 hours (28%), while machine breakdowns totalled 485 hours (25%). | Equipment failure (breakdowns) | Share of planned time | 25.0 % | Both extractors agreed |
machine breakdownsShow verbatim quote (Changeover data analysis section / Fig. 5)Changeovers consumed 536 hours (28%), while machine breakdowns totalled 485 hours (25%). | Equipment failure (breakdowns) | Lost time | 485 h | Both extractors agreed |
changeoversShow verbatim quote (Changeover data analysis section / Fig. 5)Changeovers consumed 536 hours (28%), while machine breakdowns totalled 485 hours (25%). | Setup and adjustments | Share of planned time | 28.0 % | Both extractors agreed |
changeoversShow verbatim quote (Changeover data analysis section / Fig. 5)Changeovers consumed 536 hours (28%), while machine breakdowns totalled 485 hours (25%). | Setup and adjustments | Lost time | 536 h | Both extractors agreed |
retoolingShow verbatim quote (Changeover data analysis section / Fig. 6)A look at Fig. 6 revelas that retooling consumed up to 23% of the overall working hours adding up to 5602 hours in 2014. | Setup and adjustments | Lost time | 5,602 h | Both extractors agreed |
—Show verbatim quote (Changeover data analysis section / Fig. 5)In 2014, out of a total of 1928 hours available in the year, the real production time of line L1 was 907 hours (47%). | none | Availability | 47.0 % | Single extractor |
retoolingShow verbatim quote (Changeover data analysis section / Fig. 6)A look at Fig. 6 revelas that retooling consumed up to 23% of the overall working hours adding up to 5602 hours in 2014. | Setup and adjustments | Share of planned time | 23.0 % | Single extractor |
—Show verbatim quote (Page 6, Outcomes of SMED implementation section)The reduction of changeover time of Line 1 (producing 84% of total production) generated increase of ca. 11% of the production capacity (kg/h) of the L1 in 2016 (Fig. 10). | none | Throughput | 11.0 % | Single extractor |
Observation units
- Multi-Weight machine · Filling · After intervention
- Multi-Weight machine · Filling · Baseline
- Line L1 · Whole line or unspecified equipment · Baseline
- Line 1 · Whole line or unspecified equipment · After intervention