Line Startup Delay
In short
It appears in about 1 of every 100 lines studied.
When it appears, it takes on average about 57 % of the line's lost time. Reported by 3 of the 127 studies that could observe it (limited evidence).
What happens
Bringing the line from a stopped, format-change or shift-change condition back to stable running requires sequential warm-up, synchronization and fine-tuning of each station (filler, former, capper, conveyors), and this transition period produces no good output or only unstable, low-quality output. The same elapsed time also appears when switching between product lines, since downstream equipment and controls must re-stabilize before steady production is reached.
What is done about it
Standardize and document startup and line-crossover sequences, use checklists and pre-staged setpoints recipes, pre-heat or pre-condition critical equipment before the scheduled start, and apply quick-changeover (SMED) principles with parallelized preparation tasks to shorten the transition window.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 0.9% [0.3–2.2%]
- Expected share of lost time
- 0.5% [0.1–1.3%]
- Share of lost time when present
- 57% [45–67%]
- Studies / units
- 127 / 161
- Evidence grade
- C
Grade C: 2 to 4 studies, or an interval wider than 0.35.
2Probability by segment
- Dairy products2.1% [0.3–6.7%]13 studies
- Soft drinks, bottled water and juices0.9% [0.1–2.7%]26 studies
- Brewing, wine and spirits1.0% [0.1–3.2%]11 studies
- Bakery and pasta1.3% [0.2–4.0%]24 studies
- Meat, poultry and seafood1.0% [0.1–3.3%]9 studies
- Fruit and vegetable processing1.1% [0.1–3.7%]7 studies
- Grain and oilseed milling1.1% [0.1–3.9%]6 studies
- Sugar and confectionery1.0% [0.1–3.6%]9 studies
- Snacks, coffee, tea and other foods1.0% [0.1–3.4%]5 studies
- Animal feed and pet food1.0% [0.1–3.4%]7 studies
- Food manufacturing (unspecified or mixed)1.0% [0.1–3.8%]10 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceBringing the line from a stopped, format-change or shift-change condition back to stable running requires sequential warm-up, synchronization and fine-tuning of each station (filler, former, capper, conveyors), and this transition period produces no good output or only unstable, low-quality output. The same elapsed time also appears when switching between product lines, since downstream equipment and controls must re-stabilize before steady production is reached.
How it looks in SCADA data
Engineering guidanceMES/SCADA shows an extended machine-state segment labeled startup, warm-up or changeover, with speed and output ramping gradually from zero to target, delayed timestamp of first good unit, and frequent micro-adjustments to setpoints during that window; neighboring stations remain starved or idle until the sequence completes.
Countermeasure
Engineering guidanceStandardize and document startup and line-crossover sequences, use checklists and pre-staged setpoints recipes, pre-heat or pre-condition critical equipment before the scheduled start, and apply quick-changeover (SMED) principles with parallelized preparation tasks to shorten the transition window.
4Sources
- Share of lost time: 12.0 % · as reported: “Demora en arranque de líneas”
Show verbatim quote
Demora en arranque de líneas 118 784 12.0% 79.7%
- Lost time: 118 h · as reported: “Demora en arranque de líneas”
Show verbatim quote
Demora en arranque de líneas 118 784 12.0% 79.7%
- Lost time: 49.0 h · as reported: “Demora en cruce de líneas”
Show verbatim quote
Demora en cruce de líneas 49 902 5.0% 91.7%
- Share of lost time: 5.00 % · as reported: “Demora en cruce de líneas”
Show verbatim quote
Demora en cruce de líneas 49 902 5.0% 91.7%
- Implantación de Herramientas Industriales para la Optimización del Proceso Industrial Lácteo-Fermentado (2019)Open sourceLost time: 38.6 Ton · as reported: “Arranque de Línea”
Show verbatim quote
pasando así de 57.9 toneladas de mema en el primer trimestre por 38.6 toneladas para el tercer trimestre del 2013, lo que representa un beneficio significativo del 34.6%
- Implantación de Herramientas Industriales para la Optimización del Proceso Industrial Lácteo-Fermentado (2019)Open sourceLost time: 57.9 Ton · as reported: “Arranque de Línea”
Show verbatim quote
pasando así de 57.9 toneladas de mema en el primer trimestre por 38.6 toneladas para el tercer trimestre del 2013, lo que representa un beneficio significativo del 34.6%
- Proposal to improve efficiency in pre-baked bread production lines in a Peruvian SME, using SMED and TPM (2025)Open sourceMean event duration: 24.6 min · as reported: “Tiempo de arranque de línea”
Show verbatim quote
la línea Laminadora, de 24.59 min a 15.69 min.
- Proposal to improve efficiency in pre-baked bread production lines in a Peruvian SME, using SMED and TPM (2025)Open sourceMean event duration: 28.8 min · as reported: “Tiempo de arranque de línea”
Show verbatim quote
Respecto a los tiempos de arranque, la línea Boleadora disminuyó de 28.83 a 19.63 min y la línea Laminadora, de 24.59 min a 15.69 min.
- Lost time: 85.0 min · as reported: “Arranque de linha”
Show verbatim quote
Arranque de linha 2 100 98,64 € 85
- Number of events: 2.00 events · as reported: “Arranque de linha”
Show verbatim quote
Arranque de linha 2 100 98,64 € 85