Product Loss in Transfer Lines
In short
It appears in about 1 of every 100 lines studied.
When it appears, it takes on average about 48 % of the line's lost time. Reported by 3 of the 127 studies that could observe it (limited evidence).
What happens
Liquid product such as syrup or chocolate is lost as it moves between process stages because of the geometry and length of the transfer lines, residual holdup in pipes, hoses and buffer tanks, or inefficient manual handling during transfer. The product that clings to walls, remains in dead legs, or is spilled during manual pouring never reaches the downstream process as usable material.
What is done about it
Redesign transfer lines to minimize length, dead legs and holdup volume, add pigging or scraping systems to recover residual product, and automate manual transfer steps with closed piping and pumps instead of open pouring. Track and reconcile mass balances per transfer event to quantify and target the largest contributors.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 0.9% [0.2–2.1%]
- Expected share of lost time
- 0.4% [0.1–1.1%]
- Share of lost time when present
- 48% [29–66%]
- Studies / units
- 127 / 161
- Evidence grade
- C
Grade C: 2 to 4 studies, or an interval wider than 0.35.
2Probability by segment
- Dairy products0.9% [0.1–3.1%]13 studies
- Soft drinks, bottled water and juices1.1% [0.2–3.5%]26 studies
- Brewing, wine and spirits1.0% [0.1–3.4%]11 studies
- Bakery and pasta1.2% [0.2–3.5%]24 studies
- Meat, poultry and seafood1.0% [0.1–3.2%]9 studies
- Fruit and vegetable processing1.0% [0.1–3.5%]7 studies
- Grain and oilseed milling1.0% [0.1–3.6%]6 studies
- Sugar and confectionery1.4% [0.2–4.8%]9 studies
- Snacks, coffee, tea and other foods1.0% [0.1–3.4%]5 studies
- Animal feed and pet food1.0% [0.1–3.4%]7 studies
- Food manufacturing (unspecified or mixed)0.9% [0.1–3.2%]10 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceLiquid product such as syrup or chocolate is lost as it moves between process stages because of the geometry and length of the transfer lines, residual holdup in pipes, hoses and buffer tanks, or inefficient manual handling during transfer. The product that clings to walls, remains in dead legs, or is spilled during manual pouring never reaches the downstream process as usable material.
How it looks in SCADA data
Engineering guidanceThere is no single dedicated alarm; the loss typically appears as a mass or volume balance discrepancy between the source tank/line and the receiving tank, as short unclassified stop events logged at transfer points without a maintenance code, or as manual operator actions recorded in MES during product transfer that correlate with downstream yield shortfalls.
Countermeasure
Engineering guidanceRedesign transfer lines to minimize length, dead legs and holdup volume, add pigging or scraping systems to recover residual product, and automate manual transfer steps with closed piping and pumps instead of open pouring. Track and reconcile mass balances per transfer event to quantify and target the largest contributors.
4Sources
- An Example Application On Comparison Of Six Sigma And Kaizen From Total Quality Managment Techniquies (2018)Open sourceLost time: 20,000 litre · as reported: “Transfer hattı dizaynına bağlı şurup kaybı”
Show verbatim quote
Böylece 1 yıllık süreç içersinde 20.000 litre şurup kaybının engellenmesi sağlanmıştır.
- An Example Application On Comparison Of Six Sigma And Kaizen From Total Quality Managment Techniquies (2018)Open sourceLost time: 57,000 litre · as reported: “Şurup transferi ve ürün hazırlamadaki kayıplar”
Show verbatim quote
Belirlenen bu kök nedenin yarattığı kayıp miktarı 57.000 litre olup genel kayıpların %20 sini oluşturduğu belirlenmiştir.
- An Example Application On Comparison Of Six Sigma And Kaizen From Total Quality Managment Techniquies (2018)Open sourceShare of lost time: 20.0 % · as reported: “Şurup transferi ve ürün hazırlamadaki kayıplar”
Show verbatim quote
Belirlenen bu kök nedenin yarattığı kayıp miktarı 57.000 litre olup genel kayıpların %20 sini oluşturduğu belirlenmiştir.
- An Example Application On Comparison Of Six Sigma And Kaizen From Total Quality Managment Techniquies (2018)Open sourceLost time: 27.5 litre · as reported: “Transfer hattı dizaynına bağlı şurup kaybı”
Show verbatim quote
Şurup transfer hatlarından bir tanesinde her üretim başlangıç ve bitişinde transfer hattı dizaynına bağlı olarak ortalama 87.5 litrelik şurup kaybı olduğu belirlenmiş yapılan iyileştirmeler ile kayıp %69 oranında azaltılarak 27.5 litre seviyesine indirilmiştir.
- Productivity Improvement in a Bakery and Pastry Premix Company by Applying Preventive Maintenance, SMED and 5´S (2026)Open sourceMean event duration: 3.02 min · as reported: “Transfer”
Show verbatim quote
Transfer 3.02 2.96 2%
- Productivity Improvement in a Bakery and Pastry Premix Company by Applying Preventive Maintenance, SMED and 5´S (2026)Open sourceMean event duration: 2.96 min · as reported: “Transfer”
Show verbatim quote
Transfer 3.02 2.96 2%
- Improving Production Efficiency in a Chocolate SME through Continuous Flow, SMED and Poka-Yoke (2026)Open sourceLost time: 180 min · as reported: “manual chocolate transfer”
Show verbatim quote
Problem addressed: 180-minute manual transfer, temperature fluctuations, risk of spills, and WIP accumulation.