Planned schedule shutdown

In short

It appears in about 1 of every 100 lines studied.

When it appears, it takes on average about 57 % of the line's lost time. Reported by 2 of the 127 studies that could observe it (limited evidence).

What happens

The line is deliberately stopped as part of the production schedule, for example during periods of no demand, holidays, shift gaps or planned maintenance windows, with no equipment malfunction involved. The stop is anticipated and built into the operating calendar rather than triggered by a process event.

What is done about it

Ensure the stop is correctly flagged as planned downtime in the scheduling and MES systems so it is excluded from availability loss calculations, and use the window efficiently for maintenance, cleaning or changeover preparation to minimize its impact on subsequent startup.

Practical guidance written from engineering knowledge; it is not a statistical estimate.

1Probability and evidence

Pooled over all segments. A wide interval is a result: it states how much the evidence allows us to know.
Probability of presence
0.8% [0.2–1.9%]
Expected share of lost time
0.4% [0.1–1.1%]
Share of lost time when present
57% [45–68%]
Studies / units
127 / 161
Evidence grade
C

Grade C: 2 to 4 studies, or an interval wider than 0.35.

2Probability by segment

Partially pooled estimates for each industry segment.
  • Dairy products
    0.8% [0.1–2.8%]13 studies
  • Soft drinks, bottled water and juices
    1.0% [0.2–3.1%]26 studies
  • Brewing, wine and spirits
    0.8% [0.1–2.9%]11 studies
  • Bakery and pasta
    0.8% [0.1–2.5%]24 studies
  • Meat, poultry and seafood
    0.8% [0.1–2.9%]9 studies
  • Fruit and vegetable processing
    0.9% [0.1–3.1%]7 studies
  • Grain and oilseed milling
    0.9% [0.1–3.0%]6 studies
  • Sugar and confectionery
    1.2% [0.2–4.3%]9 studies
  • Snacks, coffee, tea and other foods
    0.8% [0.1–3.0%]5 studies
  • Animal feed and pet food
    0.9% [0.1–3.2%]7 studies
  • Food manufacturing (unspecified or mixed)
    0.9% [0.1–3.1%]10 studies

3Mechanism, SCADA signature and countermeasure

Engineering guidance that helps recognise and address the cause; it is not part of the statistical estimate.

Mechanism

Engineering guidance

The line is deliberately stopped as part of the production schedule, for example during periods of no demand, holidays, shift gaps or planned maintenance windows, with no equipment malfunction involved. The stop is anticipated and built into the operating calendar rather than triggered by a process event.

How it looks in SCADA data

Engineering guidance

MES/SCADA shows a long machine-off or idle state that coincides with the planned production calendar, with no preceding fault alarms, no fault codes logged, and no material or utility shortage flags; the stop start and end times typically align with shift boundaries or scheduled maintenance entries.

Countermeasure

Engineering guidance

Ensure the stop is correctly flagged as planned downtime in the scheduling and MES systems so it is excluded from availability loss calculations, and use the window efficiently for maintenance, cleaning or changeover preparation to minimize its impact on subsequent startup.

4Sources

Every extracted datum with its study, value and verbatim quote.
  1. Lost time: 2,171 menit · as reported: “Schedule Shutdown”
    Show verbatim quote
    Juni 992 2.171 6.164
  2. Lost time: 6,341 menit · as reported: “Schedule Shutdown”
    Show verbatim quote
    Mei 980 6.341 4.452
  3. Lost time: 8,680 menit · as reported: “Schedule Shutdown”
    Show verbatim quote
    April 1.599 8.680 5.376
  4. Lost time: 14,278 menit · as reported: “Schedule Shutdown”
    Show verbatim quote
    Maret 1.957 14.278 1.707
  5. Lost time: 10,424 menit · as reported: “Schedule Shutdown”
    Show verbatim quote
    Februari 2.051 10.424 1.098
  6. Lost time: 13,731 menit · as reported: “Schedule Shutdown”
    Show verbatim quote
    Januari 1.278 13.731 929
  7. Lost time: 9,274 menit · as reported: “Schedule Shutdown”
    Show verbatim quote
    Desember 986 9.274 9.307
  8. Lost time: 8,213 menit · as reported: “Schedule Shutdown”
    Show verbatim quote
    Oktober 1.687 8.213 15.131
  9. Lost time: 6,057 menit · as reported: “Schedule Shutdown”
    Show verbatim quote
    Agustus 1.120 6.057 16.715
  10. Lost time: 8,963 menit · as reported: “Schedule Shutdown”
    Show verbatim quote
    Juli 1.025 8.963 14.174
  11. Lost time: 12,412 menit · as reported: “Schedule Shutdown”
    Show verbatim quote
    September 1.768 12.412 9.943
  12. Lost time: 12,512 menit · as reported: “Schedule Shutdown”
    Show verbatim quote
    November 788 12.512 9.670
  13. Lost time: 4,320 menit · as reported: “Planned Shutdown”
    Show verbatim quote
    2017 223.200,00 4.320,00 218.880,00 193.089,50 3.675,62