It appears in about 1 of every 100 lines studied.
When it appears, it takes on average about 59 % of the line's lost time. Reported by 2 of the 127 studies that could observe it (limited evidence).
What happens
A failed component cannot be repaired or replaced immediately because the required spare part is not available in the plant stores, so the line or machine remains stopped while the part is requested, located or transported from an external supplier. The underlying cause is organizational, rooted in inventory policy, procurement lead times or utility service outages rather than in the equipment itself.
What is done about it
Establish a critical spare parts inventory based on criticality analysis, with minimum stock levels, reorder points and vendor-managed or consignment agreements for long lead time items. Complement this with preventive maintenance planning and service contracts to reduce exposure to utility outages that trigger the same waiting condition.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 0.8% [0.2–1.9%]
- Expected share of lost time
- 0.4% [0.1–1.1%]
- Share of lost time when present
- 59% [48–69%]
- Studies / units
- 127 / 161
- Evidence grade
- C
Grade C: 2 to 4 studies, or an interval wider than 0.35.
2Probability by segment
- Dairy products0.9% [0.1–3.0%]13 studies
- Soft drinks, bottled water and juices0.8% [0.1–2.4%]26 studies
- Brewing, wine and spirits0.8% [0.1–3.0%]11 studies
- Bakery and pasta0.8% [0.1–2.7%]24 studies
- Meat, poultry and seafood0.9% [0.1–3.0%]9 studies
- Fruit and vegetable processing0.9% [0.1–3.3%]7 studies
- Grain and oilseed milling1.3% [0.2–4.6%]6 studies
- Sugar and confectionery0.9% [0.1–3.0%]9 studies
- Snacks, coffee, tea and other foods1.3% [0.2–4.6%]5 studies
- Animal feed and pet food0.9% [0.1–3.2%]7 studies
- Food manufacturing (unspecified or mixed)0.9% [0.1–3.0%]10 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceA failed component cannot be repaired or replaced immediately because the required spare part is not available in the plant stores, so the line or machine remains stopped while the part is requested, located or transported from an external supplier. The underlying cause is organizational, rooted in inventory policy, procurement lead times or utility service outages rather than in the equipment itself.
How it looks in SCADA data
Engineering guidanceSCADA/MES shows an extended stop state on the affected machine with no maintenance work order closure for a long interval, often flagged generically as waiting or unavailable rather than under a specific fault code. Downstream and upstream stations show starvation or blocking patterns consistent with a single bottleneck remaining idle for an unusually long, non-cyclical duration.
Countermeasure
Engineering guidanceEstablish a critical spare parts inventory based on criticality analysis, with minimum stock levels, reorder points and vendor-managed or consignment agreements for long lead time items. Complement this with preventive maintenance planning and service contracts to reduce exposure to utility outages that trigger the same waiting condition.
4Sources
- Lost time: 10.0 h · as reported: “Falla de servicios”
Show verbatim quote
Falla de servicios 10 961 1.0% 97.7%
- Share of lost time: 1.00 % · as reported: “Falla de servicios”
Show verbatim quote
Falla de servicios 10 961 1.0% 97.7%
- Innovation in Smart Maintenance: An IoT-Based Strategy to Improve Packaging Machine Availability in a SME (2025)Open sourceShare of planned time: 5.00 % · as reported: “stockouts of spare parts and maintenance materials”
Show verbatim quote
High downtime rate due to stockouts 5% 3.80% 1.24%
- Innovation in Smart Maintenance: An IoT-Based Strategy to Improve Packaging Machine Availability in a SME (2025)Open sourceLost time: 84.0 h · as reported: “stockouts of spare parts and maintenance materials”
Show verbatim quote
stockouts of spare parts and maintenance materials were reduced by shortening supply lead times by 78.78%, from 84 hours to 17.82 hours
- Sinergia lean-industria 4.0: un modelo de eficiencia operativa para mypes del sector alimentario (2026)Open sourceMean event duration: 45.0 minutes · as reported: “espera por repuestos”
Show verbatim quote
El tiempo promedio de espera por insumos descendió de 45 minutos a menos de 5 minutos diarios
- Sinergia lean-industria 4.0: un modelo de eficiencia operativa para mypes del sector alimentario (2026)Open sourceNumber of events: 32.0 stops · as reported: “paros por falta de repuestos”
Show verbatim quote
la frecuencia de paros mensuales por falta de repuestos se redujo de 32 a 5 veces
- Sinergia lean-industria 4.0: un modelo de eficiencia operativa para mypes del sector alimentario (2026)Open sourceMean event duration: 5.00 minutes · as reported: “espera por repuestos”
Show verbatim quote
El tiempo promedio de espera por insumos descendió de 45 minutos a menos de 5 minutos diarios
- Sinergia lean-industria 4.0: un modelo de eficiencia operativa para mypes del sector alimentario (2026)Open sourceNumber of events: 5.00 stops · as reported: “paros por falta de repuestos”
Show verbatim quote
la frecuencia de paros mensuales por falta de repuestos se redujo de 32 a 5 veces