foratvise
Get Started
organizational external

Stoppage due to spare parts shortage

In short

It appears in about 1 of every 100 lines studied.

When it appears, it takes on average about 59 % of the line's lost time. Reported by 2 of the 127 studies that could observe it (limited evidence).

What happens

A failed component cannot be repaired or replaced immediately because the required spare part is not available in the plant stores, so the line or machine remains stopped while the part is requested, located or transported from an external supplier. The underlying cause is organizational, rooted in inventory policy, procurement lead times or utility service outages rather than in the equipment itself.

What is done about it

Establish a critical spare parts inventory based on criticality analysis, with minimum stock levels, reorder points and vendor-managed or consignment agreements for long lead time items. Complement this with preventive maintenance planning and service contracts to reduce exposure to utility outages that trigger the same waiting condition.

Practical guidance written from engineering knowledge; it is not a statistical estimate.

1Probability and evidence

Pooled over all segments. A wide interval is a result: it states how much the evidence allows us to know.
Probability of presence
0.8% [0.2–1.9%]
Expected share of lost time
0.4% [0.1–1.1%]
Share of lost time when present
59% [48–69%]
Studies / units
127 / 161
Evidence grade
C

Grade C: 2 to 4 studies, or an interval wider than 0.35.

2Probability by segment

Partially pooled estimates for each industry segment.
  • Dairy products
    0.9% [0.1–3.0%]13 studies
  • Soft drinks, bottled water and juices
    0.8% [0.1–2.4%]26 studies
  • Brewing, wine and spirits
    0.8% [0.1–3.0%]11 studies
  • Bakery and pasta
    0.8% [0.1–2.7%]24 studies
  • Meat, poultry and seafood
    0.9% [0.1–3.0%]9 studies
  • Fruit and vegetable processing
    0.9% [0.1–3.3%]7 studies
  • Grain and oilseed milling
    1.3% [0.2–4.6%]6 studies
  • Sugar and confectionery
    0.9% [0.1–3.0%]9 studies
  • Snacks, coffee, tea and other foods
    1.3% [0.2–4.6%]5 studies
  • Animal feed and pet food
    0.9% [0.1–3.2%]7 studies
  • Food manufacturing (unspecified or mixed)
    0.9% [0.1–3.0%]10 studies

3Mechanism, SCADA signature and countermeasure

Engineering guidance that helps recognise and address the cause; it is not part of the statistical estimate.

Mechanism

Engineering guidance

A failed component cannot be repaired or replaced immediately because the required spare part is not available in the plant stores, so the line or machine remains stopped while the part is requested, located or transported from an external supplier. The underlying cause is organizational, rooted in inventory policy, procurement lead times or utility service outages rather than in the equipment itself.

How it looks in SCADA data

Engineering guidance

SCADA/MES shows an extended stop state on the affected machine with no maintenance work order closure for a long interval, often flagged generically as waiting or unavailable rather than under a specific fault code. Downstream and upstream stations show starvation or blocking patterns consistent with a single bottleneck remaining idle for an unusually long, non-cyclical duration.

Countermeasure

Engineering guidance

Establish a critical spare parts inventory based on criticality analysis, with minimum stock levels, reorder points and vendor-managed or consignment agreements for long lead time items. Complement this with preventive maintenance planning and service contracts to reduce exposure to utility outages that trigger the same waiting condition.

4Sources

Every extracted datum with its study, value and verbatim quote.
  1. Lost time: 10.0 h · as reported: “Falla de servicios”
    Show verbatim quote
    Falla de servicios 10 961 1.0% 97.7%
  2. Share of lost time: 1.00 % · as reported: “Falla de servicios”
    Show verbatim quote
    Falla de servicios 10 961 1.0% 97.7%
  3. Share of planned time: 5.00 % · as reported: “stockouts of spare parts and maintenance materials”
    Show verbatim quote
    High downtime rate due to stockouts 5% 3.80% 1.24%
  4. Lost time: 84.0 h · as reported: “stockouts of spare parts and maintenance materials”
    Show verbatim quote
    stockouts of spare parts and maintenance materials were reduced by shortening supply lead times by 78.78%, from 84 hours to 17.82 hours
  5. Mean event duration: 45.0 minutes · as reported: “espera por repuestos”
    Show verbatim quote
    El tiempo promedio de espera por insumos descendió de 45 minutos a menos de 5 minutos diarios
  6. Number of events: 32.0 stops · as reported: “paros por falta de repuestos”
    Show verbatim quote
    la frecuencia de paros mensuales por falta de repuestos se redujo de 32 a 5 veces
  7. Mean event duration: 5.00 minutes · as reported: “espera por repuestos”
    Show verbatim quote
    El tiempo promedio de espera por insumos descendió de 45 minutos a menos de 5 minutos diarios
  8. Number of events: 5.00 stops · as reported: “paros por falta de repuestos”
    Show verbatim quote
    la frecuencia de paros mensuales por falta de repuestos se redujo de 32 a 5 veces