Syrup batching changeover and setup time
In short
It appears in about 1 of every 100 lines studied.
When it appears, it takes on average about 57 % of the line's lost time. Reported by 2 of the 31 studies that could observe it (limited evidence).
What happens
Between successive syrup batches the mixing tank must be emptied, cleaned if required, recharged with water and ingredients, and brought to the target concentration, temperature and homogeneity before the batch is released to the filling line. This preparation sequence, together with recipe selection and verification, consumes time during which no usable syrup is produced.
What is done about it
Standardize and pre-stage ingredient quantities, automate recipe loading and parameter checks in the batch control system, and overlap tank cleaning or charging with upstream or downstream line activities so that the preparation sequence runs in parallel rather than in series with filling demand.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 1.3% [0.3–3.8%]
- Expected share of lost time
- 0.7% [0.1–2.1%]
- Share of lost time when present
- 57% [45–67%]
- Studies / units
- 31 / 40
- Evidence grade
- C
Grade C: 2 to 4 studies, or an interval wider than 0.35.
2Probability by segment
- Dairy products1.5% [0.1–5.7%]6 studies
- Soft drinks, bottled water and juices2.2% [0.2–7.8%]2 studies
- Brewing, wine and spirits1.5% [0.2–5.7%]0 studies
- Bakery and pasta2.1% [0.2–7.3%]2 studies
- Meat, poultry and seafood1.6% [0.1–5.9%]1 study
- Fruit and vegetable processing1.5% [0.1–6.0%]2 studies
- Grain and oilseed milling1.6% [0.1–6.1%]0 studies
- Sugar and confectionery1.5% [0.1–5.8%]3 studies
- Snacks, coffee, tea and other foods1.5% [0.1–5.1%]3 studies
- Animal feed and pet food1.4% [0.2–5.3%]5 studies
- Food manufacturing (unspecified or mixed)1.5% [0.1–5.4%]7 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceBetween successive syrup batches the mixing tank must be emptied, cleaned if required, recharged with water and ingredients, and brought to the target concentration, temperature and homogeneity before the batch is released to the filling line. This preparation sequence, together with recipe selection and verification, consumes time during which no usable syrup is produced.
How it looks in SCADA data
Engineering guidanceMES/SCADA shows an extended batch or setup state between the end of discharge of the previous batch and the start of stable mixing, with recipe-load and ingredient-charging events clustered in this window; total batch lead time recorded by the system is dominated by this non-productive segment rather than by active mixing time.
Countermeasure
Engineering guidanceStandardize and pre-stage ingredient quantities, automate recipe loading and parameter checks in the batch control system, and overlap tank cleaning or charging with upstream or downstream line activities so that the preparation sequence runs in parallel rather than in series with filling demand.
4Sources
- An implementation of lean technology to improve the lead time of syrup batching process and reduce hot fill line downtime (2023)Open sourceLost time: 140 min · as reported: “total leading time of syrup batching process”
Show verbatim quote
Total leading time of recently batching syrup process for new product is 140 minutes.
- An implementation of lean technology to improve the lead time of syrup batching process and reduce hot fill line downtime (2023)Open sourceLost time: 98.0 min · as reported: “total leading time of syrup batching process”
Show verbatim quote
The project results obtained that the total time in the syrup batching process was reduced from 140 minutes to 98 minutes - a dramatic decrease of 42 minutes (equivalent to a 30% reduction) as shown on Figure 11.
- Productivity Improvement in a Bakery and Pastry Premix Company by Applying Preventive Maintenance, SMED and 5´S (2026)Open sourceMean event duration: 27.3 min · as reported: “Total Time”
Show verbatim quote
Total Time 27.25 18.22 9.04
- Productivity Improvement in a Bakery and Pastry Premix Company by Applying Preventive Maintenance, SMED and 5´S (2026)Open sourceMean event duration: 18.2 min · as reported: “Total Time”
Show verbatim quote
Total Time 27.25 18.22 9.04