Unspecified availability loss (OEE component, cause not detailed)
In short
It appears in about 1 of every 100 lines studied.
When it appears, it takes on average about 56 % of the line's lost time. Reported by 3 of the 127 studies that could observe it (limited evidence).
What happens
These labels report the availability (and sometimes performance/quality) component of the OEE calculation at an aggregate level, lumping planned and unplanned stoppages without attributing them to a specific equipment failure, changeover, or organizational cause. The loss is therefore a reporting-level figure rather than a description of a physical or organizational mechanism.
What is done about it
Implement or enforce detailed downtime and stop-reason coding at the machine level (equipment tag, start/end timestamps, reason category) so that aggregate availability figures can be decomposed into specific equipment, changeover, or organizational causes for targeted improvement.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 1.0% [0.3–2.3%]
- Expected share of lost time
- 0.5% [0.2–1.3%]
- Share of lost time when present
- 56% [44–66%]
- Studies / units
- 127 / 161
- Evidence grade
- C
Grade C: 2 to 4 studies, or an interval wider than 0.35.
2Probability by segment
- Dairy products1.1% [0.2–3.4%]13 studies
- Soft drinks, bottled water and juices1.3% [0.2–3.7%]26 studies
- Brewing, wine and spirits1.5% [0.2–5.1%]11 studies
- Bakery and pasta1.0% [0.2–3.0%]24 studies
- Meat, poultry and seafood1.1% [0.1–3.7%]9 studies
- Fruit and vegetable processing1.1% [0.1–3.6%]7 studies
- Grain and oilseed milling1.7% [0.2–6.0%]6 studies
- Sugar and confectionery1.1% [0.2–3.6%]9 studies
- Snacks, coffee, tea and other foods1.1% [0.2–3.7%]5 studies
- Animal feed and pet food1.1% [0.1–3.6%]7 studies
- Food manufacturing (unspecified or mixed)1.1% [0.1–3.9%]10 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceThese labels report the availability (and sometimes performance/quality) component of the OEE calculation at an aggregate level, lumping planned and unplanned stoppages without attributing them to a specific equipment failure, changeover, or organizational cause. The loss is therefore a reporting-level figure rather than a description of a physical or organizational mechanism.
How it looks in SCADA data
Engineering guidanceIn SCADA/MES this appears as a single aggregated downtime total or an availability percentage tag/KPI with no associated stop-reason code, equipment tag, or event breakdown, so the underlying machine states cannot be isolated from the record itself.
Countermeasure
Engineering guidanceImplement or enforce detailed downtime and stop-reason coding at the machine level (equipment tag, start/end timestamps, reason category) so that aggregate availability figures can be decomposed into specific equipment, changeover, or organizational causes for targeted improvement.
4Sources
- Análise da aplicação de indicadores alternativos ao Overall Equipment Effectiveness (OEE) na gestão do desempenho global de uma fábricaOpen sourceShare of lost time: 29.0 % · as reported: “Perdas de disponibilidade (g2,g3), desempenho e qualidade”
Show verbatim quote
as causas que afetavam o OEEL como aquelas que geram perdas de disponibilidade (g2, g3), desempenho e qualidade representavam 29% do tempo total de paradas
- Análise da aplicação de indicadores alternativos ao Overall Equipment Effectiveness (OEE) na gestão do desempenho global de uma fábricaOpen sourceLost time: 42.6 h · as reported: “Perdas de disponibilidade, desempenho e qualidade”
Show verbatim quote
o volume de produção perdido devido às perdas de disponibilidade, desempenho e qualidade baixou de uma média de 153 t por semana (42,6 horas perdidas por semana), na fase 1, para uma média de 104 t por semana (28,8 horas perdidas por semana) na fase 2.
- Análise da aplicação de indicadores alternativos ao Overall Equipment Effectiveness (OEE) na gestão do desempenho global de uma fábricaOpen sourceLost time: 28.8 h · as reported: “Perdas de disponibilidade, desempenho e qualidade”
Show verbatim quote
o volume de produção perdido devido às perdas de disponibilidade, desempenho e qualidade baixou de uma média de 153 t por semana (42,6 horas perdidas por semana), na fase 1, para uma média de 104 t por semana (28,8 horas perdidas por semana) na fase 2.
- Availability: 92.1 % · as reported: “Disponibilidade Planejada”
Show verbatim quote
Disponibilidade P (Dp) 92,14%
- Availability: 90.3 % · as reported: “Disponibilidade Não Planejada”
Show verbatim quote
Disponibilidade Np (Dnp) 90,30%
- Share of lost time: 18.0 % · as reported: “Disponibilidade (total)”
Show verbatim quote
verificou-se que cerca de 18% das perdas em relação ao tempo total são referentes a disponibilidade
- Share of lost time: 8.00 % · as reported: “Disponibilidade P”
Show verbatim quote
Disponibilidade P 8%
- Share of lost time: 10.0 % · as reported: “Disponibilidade de NP”
Show verbatim quote
Disponibilidade de NP 10%
- Share of planned time: 8.00 % · as reported: “Planned availability losses”
Show verbatim quote
Disponibilidade P 8%
- Share of planned time: 10.0 % · as reported: “Unplanned availability losses”
Show verbatim quote
Disponibilidade de NP 10%
- Lost time: 160 min · as reported: “Planned losses”
Show verbatim quote
Planned losses (min) 0 160 0 0 0 160 7
- Share of lost time: 7.00 % · as reported: “Planned losses”
Show verbatim quote
Planned losses (min) 0 160 0 0 0 160 7