Included study
EVALUATIONOF TOTAL PRODUCTIVE MAINTENANCE SYSTEM INA BEVERAGES BOTTLING PLANT
1Bibliographic record
- Authors
- Sreenivasulu Reddy Allampati, Sivaramakrishna Reddy. S
- Year
- 2017
- Venue
- International Journal of Engineering Researches and Management Studies
- DOI
- —
- Country
- India
- Segment
- Soft drinks, bottled water and juices
- Process family
- Filling and packaging line
- Study type
- Before/after intervention
- Extraction scope
- Full text
- Size
- 1 plants · 1 lines · 5 machines
- Observation period
- 20 days
- Data collection
- not_reported
- Intervention
Show the setting as described by the study
This line is 200 Bottles per Minute (BPM) PET line and was started in the year 2004. Pack size machines in CSD PET line consists of Blower, Filler, Labeller, Caser and Palletizer.
2Risk of bias
Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 9Moderate risk
| Item | Score |
|---|---|
| Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product, process and equipment are all described. | 2 / 2 |
| Is the observation period long enough and reported?Period reported but shorter than 30 days, or only the number of shifts is given. | 1 / 2 |
| How were loss data collected?Interviews, estimates, or method not reported. | 0 / 2 |
| Are OEE, loading time and the loss categories defined explicitly?A standard definition is cited but its application is not shown. | 1 / 2 |
| Does the loss breakdown account for the total loss it claims to explain?Only the top causes are reported and the unexplained remainder can be computed. | 1 / 2 |
| Is there evidence of selective reporting of favourable results?Intervention study in which baseline and post-intervention periods differ in length or method. | 1 / 2 |
| Are the reported numbers internally consistent?Small inconsistencies (2 to 10 percentage points) or values that cannot be cross-checked. | 1 / 2 |
| Could conflicts of interest or the source of the data bias the result?Academic or independent study, or conflicts declared and unrelated to the result. | 2 / 2 |
3Extracted data
Each datum with its classification and the verbatim quote that states it.
| Reported cause | Loss category | Metric | Value | Extraction |
|---|---|---|---|---|
—Show verbatim quote (Table-1, Day 1)OEE (%) 63 76 54 80 65 46 33 57 26 78 | none | OEE | 63.0 % | Single extractor |
—Show verbatim quote (Table-1, Day 2)OEE (%) 63 76 54 80 65 46 33 57 26 78 | none | OEE | 76.0 % | Single extractor |
—Show verbatim quote (Table-1, Day 3)OEE (%) 63 76 54 80 65 46 33 57 26 78 | none | OEE | 54.0 % | Single extractor |
—Show verbatim quote (Table-1, Day 4)OEE (%) 63 76 54 80 65 46 33 57 26 78 | none | OEE | 80.0 % | Single extractor |
—Show verbatim quote (Table-1, Day 5)OEE (%) 63 76 54 80 65 46 33 57 26 78 | none | OEE | 65.0 % | Single extractor |
—Show verbatim quote (Table-1, Day 6)OEE (%) 63 76 54 80 65 46 33 57 26 78 | none | OEE | 46.0 % | Single extractor |
—Show verbatim quote (Table-1, Day 7)OEE (%) 63 76 54 80 65 46 33 57 26 78 | none | OEE | 33.0 % | Single extractor |
—Show verbatim quote (Table-1, Day 8)OEE (%) 63 76 54 80 65 46 33 57 26 78 | none | OEE | 57.0 % | Single extractor |
—Show verbatim quote (Table-1, Day 9)OEE (%) 63 76 54 80 65 46 33 57 26 78 | none | OEE | 26.0 % | Single extractor |
—Show verbatim quote (Table-1, Day 10)OEE (%) 63 76 54 80 65 46 33 57 26 78 | none | OEE | 78.0 % | Single extractor |
—Show verbatim quote (Table-1, Day 1 (ME))ME (%) 63 76 62 80 65 46 33 57 26 78 | none | Availability | 63.0 % | Single extractor |
—Show verbatim quote (Table-1, Day 2 (ME))ME (%) 63 76 62 80 65 46 33 57 26 78 | none | Availability | 76.0 % | Single extractor |
—Show verbatim quote (Table-1, Day 3 (ME))ME (%) 63 76 62 80 65 46 33 57 26 78 | none | Availability | 62.0 % | Single extractor |
—Show verbatim quote (Table-1, Day 4 (ME))ME (%) 63 76 62 80 65 46 33 57 26 78 | none | Availability | 80.0 % | Single extractor |
—Show verbatim quote (Table-1, Day 5 (ME))ME (%) 63 76 62 80 65 46 33 57 26 78 | none | Availability | 65.0 % | Single extractor |
—Show verbatim quote (Table-1, Day 6 (ME))ME (%) 63 76 62 80 65 46 33 57 26 78 | none | Availability | 46.0 % | Single extractor |
—Show verbatim quote (Table-1, Day 7 (ME))ME (%) 63 76 62 80 65 46 33 57 26 78 | none | Availability | 33.0 % | Single extractor |
—Show verbatim quote (Table-1, Day 8 (ME))ME (%) 63 76 62 80 65 46 33 57 26 78 | none | Availability | 57.0 % | Single extractor |
—Show verbatim quote (Table-1, Day 9 (ME))ME (%) 63 76 62 80 65 46 33 57 26 78 | none | Availability | 26.0 % | Single extractor |
—Show verbatim quote (Table-1, Day 10 (ME))ME (%) 63 76 62 80 65 46 33 57 26 78 | none | Availability | 78.0 % | Single extractor |
Planned lossesShow verbatim quote (Table-4)Planned losses (min) 0 160 0 0 0 160 7 | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 160 min | Single extractor |
Planned lossesShow verbatim quote (Table-4)Planned losses (min) 0 160 0 0 0 160 7 | Planned downtime (scheduled maintenance, breaks, no demand) | Share of lost time | 7.00 % | Single extractor |
Operational lossesShow verbatim quote (Table-4)Operational losses (min) 278 494 106 53 157 1088 48 | Not classifiable from the report | Lost time | 1,088 min | Single extractor |
Operational lossesShow verbatim quote (Table-4)Operational losses (min) 278 494 106 53 157 1088 48 | Not classifiable from the report | Share of lost time | 48.0 % | Single extractor |
Equipment lossesShow verbatim quote (Table-4)Equipment losses (min) 420 364 24 55 152 1015 44.8 | Equipment failure (breakdowns) | Lost time | 1,015 min | Single extractor |
Equipment lossesShow verbatim quote (Table-4)Equipment losses (min) 420 364 24 55 152 1015 44.8 | Equipment failure (breakdowns) | Share of lost time | 44.8 % | Single extractor |
Total LossesShow verbatim quote (Table-5)Total Losses(min) 698 1018 130 108 309 2263 | Not classifiable from the report | Lost time | 2,263 min | Single extractor |
—Show verbatim quote (Table-6, January 2004 (before TPM))January 55 September 76 | none | OEE | 55.0 % | Single extractor |
—Show verbatim quote (Table-6, September 2015 (after TPM))January 55 September 76 | none | OEE | 76.0 % | Single extractor |
—Show verbatim quote (Table-6, October 2015 (after TPM))February 46 October 80 | none | OEE | 80.0 % | Single extractor |
—Show verbatim quote (Table-6, November 2015 (after TPM))March 54 November 83 | none | OEE | 83.0 % | Single extractor |
Planned lossesBlowerShow verbatim quote (Table-4)Planned losses (min) 0 160 0 0 0 160 7 | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 0 min | Single extractor |
Operational lossesBlowerShow verbatim quote (Table-4)Operational losses (min) 278 494 106 53 157 1088 48 | Not classifiable from the report | Lost time | 278 min | Single extractor |
Equipment lossesBlowerShow verbatim quote (Table-4)Equipment losses (min) 420 364 24 55 152 1015 44.8 | Equipment failure (breakdowns) | Lost time | 420 min | Single extractor |
Total LossesBlowerShow verbatim quote (Table-5)Total Losses(min) 698 1018 130 108 309 2263 | Not classifiable from the report | Lost time | 698 min | Single extractor |
Total LossesBlowerShow verbatim quote (Table-5)% of Losses 30.8 45 5.8 4.8 13.7 | Not classifiable from the report | Share of lost time | 30.8 % | Single extractor |
Planned lossesFillerShow verbatim quote (Table-4)Planned losses (min) 0 160 0 0 0 160 7 | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 160 min | Single extractor |
Operational lossesFillerShow verbatim quote (Table-4)Operational losses (min) 278 494 106 53 157 1088 48 | Not classifiable from the report | Lost time | 494 min | Single extractor |
Equipment lossesFillerShow verbatim quote (Table-4)Equipment losses (min) 420 364 24 55 152 1015 44.8 | Equipment failure (breakdowns) | Lost time | 364 min | Single extractor |
Total LossesFillerShow verbatim quote (Table-5)Total Losses(min) 698 1018 130 108 309 2263 | Not classifiable from the report | Lost time | 1,018 min | Single extractor |
Total LossesFillerShow verbatim quote (Table-5)% of Losses 30.8 45 5.8 4.8 13.7 | Not classifiable from the report | Share of lost time | 45.0 % | Single extractor |
Planned lossesLabellerShow verbatim quote (Table-4)Planned losses (min) 0 160 0 0 0 160 7 | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 0 min | Single extractor |
Operational lossesLabellerShow verbatim quote (Table-4)Operational losses (min) 278 494 106 53 157 1088 48 | Not classifiable from the report | Lost time | 106 min | Single extractor |
Equipment lossesLabellerShow verbatim quote (Table-4)Equipment losses (min) 420 364 24 55 152 1015 44.8 | Equipment failure (breakdowns) | Lost time | 24.0 min | Single extractor |
Total LossesLabellerShow verbatim quote (Table-5)Total Losses(min) 698 1018 130 108 309 2263 | Not classifiable from the report | Lost time | 130 min | Single extractor |
Total LossesLabellerShow verbatim quote (Table-5)% of Losses 30.8 45 5.8 4.8 13.7 | Not classifiable from the report | Share of lost time | 5.80 % | Single extractor |
Planned lossesCaserShow verbatim quote (Table-4)Planned losses (min) 0 160 0 0 0 160 7 | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 0 min | Single extractor |
Operational lossesCaserShow verbatim quote (Table-4)Operational losses (min) 278 494 106 53 157 1088 48 | Not classifiable from the report | Lost time | 53.0 min | Single extractor |
Equipment lossesCaserShow verbatim quote (Table-4)Equipment losses (min) 420 364 24 55 152 1015 44.8 | Equipment failure (breakdowns) | Lost time | 55.0 min | Single extractor |
Total LossesCaserShow verbatim quote (Table-5)Total Losses(min) 698 1018 130 108 309 2263 | Not classifiable from the report | Lost time | 108 min | Single extractor |
Total LossesCaserShow verbatim quote (Table-5)% of Losses 30.8 45 5.8 4.8 13.7 | Not classifiable from the report | Share of lost time | 4.80 % | Single extractor |
Planned lossesPalletizerShow verbatim quote (Table-4)Planned losses (min) 0 160 0 0 0 160 7 | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 0 min | Single extractor |
Operational lossesPalletizerShow verbatim quote (Table-4)Operational losses (min) 278 494 106 53 157 1088 48 | Not classifiable from the report | Lost time | 157 min | Single extractor |
Equipment lossesPalletizerShow verbatim quote (Table-4)Equipment losses (min) 420 364 24 55 152 1015 44.8 | Equipment failure (breakdowns) | Lost time | 152 min | Single extractor |
Total LossesPalletizerShow verbatim quote (Table-5)Total Losses(min) 698 1018 130 108 309 2263 | Not classifiable from the report | Lost time | 309 min | Single extractor |
Total LossesPalletizerShow verbatim quote (Table-5)% of Losses 30.8 45 5.8 4.8 13.7 | Not classifiable from the report | Share of lost time | 13.7 % | Single extractor |
—Show verbatim quote (Table-4)Planned losses (min) | 0 | 160 | 0 | 0 | 0 | 160 | 7 | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 160 min | Single extractor |
FillerFillerShow verbatim quote (Table-4)Planned losses (min) | 0 | 160 | 0 | 0 | 0 | 160 | 7 | Planned downtime (scheduled maintenance, breaks, no demand) | Lost time | 160 min | Single extractor |
—Show verbatim quote (Table-4)Operational losses (min) | 278 | 494 | 106 | 53 | 157 | 1088 | 48 | Idling and minor stops (micro-stops) | Lost time | 1,088 min | Single extractor |
BlowerBlowerShow verbatim quote (Table-4)Operational losses (min) | 278 | 494 | 106 | 53 | 157 | 1088 | 48 | Idling and minor stops (micro-stops) | Lost time | 278 min | Single extractor |
FillerFillerShow verbatim quote (Table-4)Operational losses (min) | 278 | 494 | 106 | 53 | 157 | 1088 | 48 | Idling and minor stops (micro-stops) | Lost time | 494 min | Single extractor |
LabellerLabellerShow verbatim quote (Table-4)Operational losses (min) | 278 | 494 | 106 | 53 | 157 | 1088 | 48 | Idling and minor stops (micro-stops) | Lost time | 106 min | Single extractor |
CaserCaserShow verbatim quote (Table-4)Operational losses (min) | 278 | 494 | 106 | 53 | 157 | 1088 | 48 | Idling and minor stops (micro-stops) | Lost time | 53.0 min | Single extractor |
PalletizerPalletizerShow verbatim quote (Table-4)Operational losses (min) | 278 | 494 | 106 | 53 | 157 | 1088 | 48 | Idling and minor stops (micro-stops) | Lost time | 157 min | Single extractor |
—Show verbatim quote (Table-4)Equipment losses (min) | 420 | 364 | 24 | 55 | 152 | 1015 | 44.8 | Equipment failure (breakdowns) | Lost time | 1,015 min | Single extractor |
BlowerBlowerShow verbatim quote (Table-4)Equipment losses (min) | 420 | 364 | 24 | 55 | 152 | 1015 | 44.8 | Equipment failure (breakdowns) | Lost time | 420 min | Single extractor |
FillerFillerShow verbatim quote (Table-4)Equipment losses (min) | 420 | 364 | 24 | 55 | 152 | 1015 | 44.8 | Equipment failure (breakdowns) | Lost time | 364 min | Single extractor |
LabellerLabellerShow verbatim quote (Table-4)Equipment losses (min) | 420 | 364 | 24 | 55 | 152 | 1015 | 44.8 | Equipment failure (breakdowns) | Lost time | 24.0 min | Single extractor |
CaserCaserShow verbatim quote (Table-4)Equipment losses (min) | 420 | 364 | 24 | 55 | 152 | 1015 | 44.8 | Equipment failure (breakdowns) | Lost time | 55.0 min | Single extractor |
PalletizerPalletizerShow verbatim quote (Table-4)Equipment losses (min) | 420 | 364 | 24 | 55 | 152 | 1015 | 44.8 | Equipment failure (breakdowns) | Lost time | 152 min | Single extractor |
Observation units
- CSD PET line · Whole line or unspecified equipment · Baseline
- CSD PET line · Whole line or unspecified equipment · After intervention
- Blower · Forming, moulding and depositing · Baseline
- Filler · Filling · Baseline
- Labeller · Labeling and coding · Baseline
- Caser · Packaging (forming, sealing, wrapping, case packing, palletizing) · Baseline
- Palletizer · Packaging (forming, sealing, wrapping, case packing, palletizing) · Baseline