Waiting for supervisor or maintenance instructions
In short
It appears in about 1 of every 100 lines studied.
When it appears, it takes on average about 55 % of the line's lost time. Reported by 1 of the 127 studies that could observe it (sparse evidence).
What happens
The line stands idle because operators lack authorization or technical direction to proceed, needing to wait for a supervisor, planner or maintenance technician to issue instructions or work orders before action can be taken. This reflects an organizational communication or decision-making bottleneck rather than a technical equipment fault.
What is done about it
Establish clear escalation protocols, decentralized decision authority and standing work instructions so operators can act without waiting for case-by-case approval, supported by radio or digital messaging systems for rapid dispatch of maintenance orders. Visual management boards and predefined response trees for common scenarios reduce dependency on real-time supervisor availability.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 0.5% [0.1–1.5%]
- Expected share of lost time
- 0.3% [0.1–0.9%]
- Share of lost time when present
- 55% [44–65%]
- Studies / units
- 127 / 161
- Evidence grade
- D
Grade D: 0 or 1 study; the estimate is driven by partial pooling and priors, and the wide interval is the result.
2Probability by segment
- Dairy products0.6% [0.1–2.4%]13 studies
- Soft drinks, bottled water and juices0.6% [0.1–2.0%]26 studies
- Brewing, wine and spirits0.6% [0.1–2.4%]11 studies
- Bakery and pasta0.6% [0.1–2.1%]24 studies
- Meat, poultry and seafood0.9% [0.1–3.5%]9 studies
- Fruit and vegetable processing0.6% [0.1–2.4%]7 studies
- Grain and oilseed milling0.7% [0.1–2.5%]6 studies
- Sugar and confectionery0.6% [0.1–2.3%]9 studies
- Snacks, coffee, tea and other foods0.6% [0.1–2.5%]5 studies
- Animal feed and pet food0.6% [0.1–2.3%]7 studies
- Food manufacturing (unspecified or mixed)0.6% [0.1–2.3%]10 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceThe line stands idle because operators lack authorization or technical direction to proceed, needing to wait for a supervisor, planner or maintenance technician to issue instructions or work orders before action can be taken. This reflects an organizational communication or decision-making bottleneck rather than a technical equipment fault.
How it looks in SCADA data
Engineering guidanceSCADA/MES shows the line or station in an idle or standby state with no active alarm and no material movement, often logged under a generic downtime reason code awaiting manual operator classification. Duration tends to be irregular and not correlated with any sensor fault, and the stop typically ends abruptly once a manual command or mode change is entered by an operator.
Countermeasure
Engineering guidanceEstablish clear escalation protocols, decentralized decision authority and standing work instructions so operators can act without waiting for case-by-case approval, supported by radio or digital messaging systems for rapid dispatch of maintenance orders. Visual management boards and predefined response trees for common scenarios reduce dependency on real-time supervisor availability.
4Sources
- Maintenance Performance Evaluation and Downtime Analysis of Manufacturing Equipment in a Food Manufacturing Company (2021)Open sourceLost time: 5,153 min · as reported: “Waiting for maintenance instruction and orders”
Show verbatim quote
Waiting for maintenance instruction and orders 5153 4.92 98.22
- Maintenance Performance Evaluation and Downtime Analysis of Manufacturing Equipment in a Food Manufacturing Company (2021)Open sourceShare of lost time: 4.92 % · as reported: “Waiting for maintenance instruction and orders”
Show verbatim quote
Waiting for maintenance instruction and orders 5153 4.92 98.22
- Lost time: 7.00 min/day · as reported: “clarification of the shift task”
Show verbatim quote
The development and implementation of the printed form of the shift task have helped to eliminate the daily time spent (7 minutes) for its clarification and have also eliminated the loss of information by the work performers
- The implementation of an integrated Lean Management-HACCP model: application in the food industry in Casablanca,Morocco (2025)Open sourceLost time: 10.0 min · as reported: “waiting for instructions from superiors”
Show verbatim quote
10 minutes of waiting for instructions from superiors to start the day's production.
- The implementation of an integrated Lean Management-HACCP model: application in the food industry in Casablanca,Morocco (2025)Open sourceLost time: 5.00 min · as reported: “waiting for instructions from superiors”
Show verbatim quote
Waiting times reduced from 20 min to 10 min and from 10 min to 5 min which represents 50% completion