Format/mould changeover on forming equipment
In short
It appears in about 1 of every 100 lines studied.
When it appears, it takes on average about 58 % of the line's lost time. Reported by 3 of the 76 studies that could observe it (limited evidence).
What happens
Switching the forming machine from one product or package format to another requires stopping production to remove and refit moulds, tooling or forming parts, reset dimensional and process parameters, and verify the first good units before resuming the run. The elapsed time between the last good unit of the previous format and the first good unit of the new one is lost to production.
What is done about it
Apply SMED methodology to separate internal from external setup activities, standardize and pre-stage tooling, use quick-change fixtures and locating features, and document a repeatable sequence so the forming machine can be reset with minimal stopped time.
Practical guidance written from engineering knowledge; it is not a statistical estimate.
1Probability and evidence
- Probability of presence
- 1.3% [0.3–3.2%]
- Expected share of lost time
- 0.7% [0.2–1.9%]
- Share of lost time when present
- 58% [46–68%]
- Studies / units
- 76 / 96
- Evidence grade
- C
Grade C: 2 to 4 studies, or an interval wider than 0.35.
2Probability by segment
- Dairy products2.1% [0.3–7.4%]5 studies
- Soft drinks, bottled water and juices1.3% [0.2–4.5%]11 studies
- Brewing, wine and spirits1.6% [0.2–6.0%]0 studies
- Bakery and pasta1.6% [0.3–4.7%]25 studies
- Meat, poultry and seafood1.5% [0.2–5.2%]3 studies
- Fruit and vegetable processing1.5% [0.2–5.1%]3 studies
- Grain and oilseed milling1.5% [0.2–5.2%]0 studies
- Sugar and confectionery1.9% [0.3–6.4%]8 studies
- Snacks, coffee, tea and other foods1.4% [0.2–4.6%]7 studies
- Animal feed and pet food1.4% [0.2–4.7%]6 studies
- Food manufacturing (unspecified or mixed)1.4% [0.2–4.6%]8 studies
3Mechanism, SCADA signature and countermeasure
Mechanism
Engineering guidanceSwitching the forming machine from one product or package format to another requires stopping production to remove and refit moulds, tooling or forming parts, reset dimensional and process parameters, and verify the first good units before resuming the run. The elapsed time between the last good unit of the previous format and the first good unit of the new one is lost to production.
How it looks in SCADA data
Engineering guidanceSCADA/MES shows a sustained non-running machine state tagged as changeover or setup, bracketed by the end of the prior production order and the start of the new one, with no fault alarms active; associated counters for mould or tooling changes and operator login events to the changeover procedure typically coincide with the stop.
Countermeasure
Engineering guidanceApply SMED methodology to separate internal from external setup activities, standardize and pre-stage tooling, use quick-change fixtures and locating features, and document a repeatable sequence so the forming machine can be reset with minimal stopped time.
4Sources
- CHANGEOVER TIME REDUCTION THROUGH LEAN TOOL “SMED” – A CASE STUDY FROM FOOD SECTOR (2018)Open sourceMean event duration: 210 min · as reported: “changeover (selected type, average, long-run)”
Show verbatim quote
The new changeover time was even lower than the project goal, but in the long run, the time was 210 minutes. This time is kept without any major problems.
- CHANGEOVER TIME REDUCTION THROUGH LEAN TOOL “SMED” – A CASE STUDY FROM FOOD SECTOR (2018)Open sourceNumber of events: 58.0 events/year · as reported: “changeover (selected type, annual frequency)”
Show verbatim quote
At a frequency of 58 changeovers per year and with a given number of operators and wage rates, the annual savings would be 91 thousand. CZK.
- CHANGEOVER TIME REDUCTION THROUGH LEAN TOOL “SMED” – A CASE STUDY FROM FOOD SECTOR (2018)Open sourceMean event duration: 244 min · as reported: “changeover (selected type, average)”
Show verbatim quote
The project team decided on the main goal of the project, which was to reduce the time of the selected sort by 10% of the average changeover time, from 244 minutes to 220 minutes.
- CHANGEOVER TIME REDUCTION THROUGH LEAN TOOL “SMED” – A CASE STUDY FROM FOOD SECTOR (2018)Open sourceMean event duration: 185 min · as reported: “changeover (most frequent type)”
Show verbatim quote
Of these types of changeovers, the fourth longest changeover was the most frequent (which would take 185 minutes), but the longest and second most frequent type of changeover (240 minutes) was eventually chosen by project team for the next step.
- CHANGEOVER TIME REDUCTION THROUGH LEAN TOOL “SMED” – A CASE STUDY FROM FOOD SECTOR (2018)Open sourceMean event duration: 240 min · as reported: “changeover (selected type for SMED project)”
Show verbatim quote
Of these types of changeovers, the fourth longest changeover was the most frequent (which would take 185 minutes), but the longest and second most frequent type of changeover (240 minutes) was eventually chosen by project team for the next step.
- CHANGEOVER TIME REDUCTION THROUGH LEAN TOOL “SMED” – A CASE STUDY FROM FOOD SECTOR (2018)Open sourceMean event duration: 194 min · as reported: “changeover (selected type, average, first re-measurement)”
Show verbatim quote
The average throw time dropped from 244 minutes to 194 minutes (Figure 7) and the target was met.
- CHANGEOVER TIME REDUCTION THROUGH LEAN TOOL “SMED” – A CASE STUDY FROM FOOD SECTOR (2018)Open sourceMean event duration: 4.00 min · as reported: “Exchange of molds”
Show verbatim quote
Exchange of molds: 0:04:00
- CHANGEOVER TIME REDUCTION THROUGH LEAN TOOL “SMED” – A CASE STUDY FROM FOOD SECTOR (2018)Open sourceMean event duration: 7.00 min · as reported: “Forming of molds”
Show verbatim quote
Forming of molds: 0:07:00
- Application of Lean-Total Productive Maintenance Tools to Reduce Setup Times and Machine Stoppages on the Molding Line of an SME in the Food Industry (2023)Open sourceLost time: 280 min · as reported: “Total duration of mold change”
Show verbatim quote
From the data collection of the total duration of mold change times, a total of 280 minutes on average was obtained, and the times of internal activities, 254 min, and external activities, 26 min.
- Improvement Model for the Production Area to increase Labor Productivity through Lean Manufacturing tools in a bakery company (2026)Open sourceLost time: 82.0 min · as reported: “format changeovers (changing from circular to rectangular cookies)”
Show verbatim quote
It was documented that the setup time averages 1.37 hours per day (82 minutes), consuming a significant portion of the available shift time.
- Improving Production Efficiency in a Chocolate SME through Continuous Flow, SMED and Poka-Yoke (2026)Open sourceNumber of events: 10.0 events/week · as reported: “operational interruptions during mold changeover”
Show verbatim quote
As-Is interruptions: 10 per week → 1 per week
- Improving Production Efficiency in a Chocolate SME through Continuous Flow, SMED and Poka-Yoke (2026)Open sourceNumber of events: 1.00 events/week · as reported: “operational interruptions during mold changeover”
Show verbatim quote
Week 5: 1 interruption
- Improving Production Efficiency in a Chocolate SME through Continuous Flow, SMED and Poka-Yoke (2026)Open sourceNumber of events: 5.00 events/week · as reported: “operational interruptions during mold changeover”
Show verbatim quote
Week 1: 5 interruptions
- Improving Production Efficiency in a Chocolate SME through Continuous Flow, SMED and Poka-Yoke (2026)Open sourceNumber of events: 3.00 events/week · as reported: “operational interruptions during mold changeover”
Show verbatim quote
Weeks 2, 3, and 4 stabilized at three interruptions each, showing improved workflow continuity and reduced operational stops.