Included study
Analisis Produktivitas Mesin Filling Botol Dengan Metode Overal Equipment Effectiveness Dan Failure Mode And Effect Analysis
1Bibliographic record
- Authors
- Angga Prasetya Aji, Widya Setiafindari
- Year
- 2023
- Venue
- Jurnal TRINISTIK Jurnal Teknik Industri Bisnis Digital dan Teknik Logistik
- Country
- Indonesia
- Segment
- Soft drinks, bottled water and juices
- Process family
- Filling and packaging line
- Study type
- Single case study
- Extraction scope
- Abstract only
- Size
- 1 plants · 1 lines · 1 machines
- Observation period
- 365 days
- Data collection
- not_reported
- Intervention
Show the setting as described by the study
PDAM Tirta Binangun is located in Secang, Sendangsari, Pengasih, Kulon Progo. The problem faced by the company is that the production of 600 ml bottled drinking water has a product failure of 16,038 bottles in one year, from April 2021 to March 2022.
2Risk of bias
Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 8Moderate risk
| Item | Score |
|---|---|
| Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product or sector is given but the equipment or process is only partly described. | 1 / 2 |
| Is the observation period long enough and reported?Period reported and at least 30 days of production (or at least 100 recorded events). | 2 / 2 |
| How were loss data collected?Interviews, estimates, or method not reported. | 0 / 2 |
| Are OEE, loading time and the loss categories defined explicitly?No definition; metrics are reported as bare numbers. | 0 / 2 |
| Does the loss breakdown account for the total loss it claims to explain?Only the top causes are reported and the unexplained remainder can be computed. | 1 / 2 |
| Is there evidence of selective reporting of favourable results?Observational study, or intervention study that reports baseline and post-intervention data with the same method. | 2 / 2 |
| Are the reported numbers internally consistent?Small inconsistencies (2 to 10 percentage points) or values that cannot be cross-checked. | 1 / 2 |
| Could conflicts of interest or the source of the data bias the result?Authors are employees of the plant or of an equipment/software vendor; no declaration. | 1 / 2 |
3Extracted data
Each datum with its classification and the verbatim quote that states it.
| Reported cause | Loss category | Metric | Value | Extraction |
|---|---|---|---|---|
—filling machineShow verbatim quote (Abstract)The results of the OEE show that the average effectiveness of the filling machine is 87.48% so that the failure is still within tolerance and has a good value because it is greater than the OEE standard, which is 85%. | none | OEE | 87.5 % | Both extractors agreed |
Idle and Minor Stoppagefilling machineShow verbatim quote (Abstract)Reduce Speed Losses with an average proportion of 3.82% and a relative frequency of 39.01%, Downtime Losses with an average of 2.27% and a relative frequency of 28.31%, Defect Losses with an average of 1.58% and a relative frequency of 15.59%, Idle and Minor Stoppage with an average of 1.55% and a relative frequency of 15.85%. | Idling and minor stops (micro-stops) | Share of loss events | 15.9 % | Both extractors agreed |
Defect Lossesfilling machineShow verbatim quote (Abstract)Reduce Speed Losses with an average proportion of 3.82% and a relative frequency of 39.01%, Downtime Losses with an average of 2.27% and a relative frequency of 28.31%, Defect Losses with an average of 1.58% and a relative frequency of 15.59%, Idle and Minor Stoppage with an average of 1.55% and a relative frequency of 15.85%. | Process defects (scrap and rework) | Share of loss events | 15.6 % | Both extractors agreed |
Downtime Lossesfilling machineShow verbatim quote (Abstract)Reduce Speed Losses with an average proportion of 3.82% and a relative frequency of 39.01%, Downtime Losses with an average of 2.27% and a relative frequency of 28.31%, Defect Losses with an average of 1.58% and a relative frequency of 15.59%, Idle and Minor Stoppage with an average of 1.55% and a relative frequency of 15.85%. | Not classifiable from the report | Share of loss events | 28.3 % | Adjudicated |
Reduce Speed Lossesfilling machineShow verbatim quote (Abstract)Reduce Speed Losses with an average proportion of 3.82% and a relative frequency of 39.01%, Downtime Losses with an average of 2.27% and a relative frequency of 28.31%, Defect Losses with an average of 1.58% and a relative frequency of 15.59%, Idle and Minor Stoppage with an average of 1.55% and a relative frequency of 15.85%. | Reduced speed | Share of loss events | 39.0 % | Both extractors agreed |
Reduce Speed Lossesfilling machineShow verbatim quote (Abstract)Reduce Speed Losses with an average proportion of 3.82% and a relative frequency of 39.01%, Downtime Losses with an average of 2.27% and a relative frequency of 28.31%, Defect Losses with an average of 1.58% and a relative frequency of 15.59%, Idle and Minor Stoppage with an average of 1.55% and a relative frequency of 15.85%. | Reduced speed | Share of planned time | 3.82 % | Single extractor |
Downtime Lossesfilling machineShow verbatim quote (Abstract)Reduce Speed Losses with an average proportion of 3.82% and a relative frequency of 39.01%, Downtime Losses with an average of 2.27% and a relative frequency of 28.31%, Defect Losses with an average of 1.58% and a relative frequency of 15.59%, Idle and Minor Stoppage with an average of 1.55% and a relative frequency of 15.85%. | Not classifiable from the report | Share of planned time | 2.27 % | Single extractor |
Defect Lossesfilling machineShow verbatim quote (Abstract)Reduce Speed Losses with an average proportion of 3.82% and a relative frequency of 39.01%, Downtime Losses with an average of 2.27% and a relative frequency of 28.31%, Defect Losses with an average of 1.58% and a relative frequency of 15.59%, Idle and Minor Stoppage with an average of 1.55% and a relative frequency of 15.85%. | Process defects (scrap and rework) | Share of planned time | 1.58 % | Single extractor |
Idle and Minor Stoppagefilling machineShow verbatim quote (Abstract)Reduce Speed Losses with an average proportion of 3.82% and a relative frequency of 39.01%, Downtime Losses with an average of 2.27% and a relative frequency of 28.31%, Defect Losses with an average of 1.58% and a relative frequency of 15.59%, Idle and Minor Stoppage with an average of 1.55% and a relative frequency of 15.85%. | Idling and minor stops (micro-stops) | Share of planned time | 1.55 % | Single extractor |
—Show verbatim quote (Abstract)Reduce Speed Losses with an average proportion of 3.82% | Reduced speed | Share of lost time | 3.82 % | Single extractor |
—Show verbatim quote (Abstract)Downtime Losses with an average of 2.27% | Equipment failure (breakdowns) | Share of lost time | 2.27 % | Single extractor |
—Show verbatim quote (Abstract)Defect Losses with an average of 1.58% | Process defects (scrap and rework) | Share of lost time | 1.58 % | Single extractor |
—Show verbatim quote (Abstract)Idle and Minor Stoppage with an average of 1.55% | Idling and minor stops (micro-stops) | Share of lost time | 1.55 % | Single extractor |
—Show verbatim quote (Abstract)the production of 600 ml bottled drinking water has a product failure of 16,038 bottles in one year, from April 2021 to March 2022 | Process defects (scrap and rework) | Number of events | 16,038 bottles | Single extractor |
Observation units
- Filling machine · Filling · Baseline