Included study
Production Model Based on Lean Manufacturing, MRP, MPS and TPM to Reduce Losses in a MSE in the Bakery Sector
1Bibliographic record
- Authors
- Marcela Garay -Rimarachin, Diego Eduardo Mejia -Espinoza
- Year
- 2023
- Venue
- International Conference on Industrial Engineering and Operations Management (IEOM)
- Country
- Peru
- Segment
- Bakery and pasta
- Process family
- Forming, baking and cooking
- Study type
- Before/after intervention
- Extraction scope
- Full text
- Size
- 1 plants · — lines · — machines
- Observation period
- 30 days
- Data collection
- questionnaire
- Intervention
Show the setting as described by the study
The present study is a case study since it is based on only one specific topic in the baking industry.
2Risk of bias
Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 6High risk
| Item | Score |
|---|---|
| Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product or sector is given but the equipment or process is only partly described. | 1 / 2 |
| Is the observation period long enough and reported?Period reported and at least 30 days of production (or at least 100 recorded events). | 2 / 2 |
| How were loss data collected?Interviews, estimates, or method not reported. | 0 / 2 |
| Are OEE, loading time and the loss categories defined explicitly?No definition; metrics are reported as bare numbers. | 0 / 2 |
| Does the loss breakdown account for the total loss it claims to explain?Only selected causes are reported and the total is unknown. | 0 / 2 |
| Is there evidence of selective reporting of favourable results?Intervention study in which baseline and post-intervention periods differ in length or method. | 1 / 2 |
| Are the reported numbers internally consistent?Small inconsistencies (2 to 10 percentage points) or values that cannot be cross-checked. | 1 / 2 |
| Could conflicts of interest or the source of the data bias the result?Authors are employees of the plant or of an equipment/software vendor; no declaration. | 1 / 2 |
3Extracted data
Each datum with its classification and the verbatim quote that states it.
| Reported cause | Loss category | Metric | Value | Extraction |
|---|---|---|---|---|
Downtime rateShow verbatim quote (Section 5.4 Validation)The downtime rate: This decreased from 35.26% to 10%, using the 5S methodology, this was reduced thanks to the implementation of cleanliness and order in the plant | Not classifiable from the report | Share of lost time | 35.3 % | Single extractor |
Stock breakShow verbatim quote (Section 5.4 Validation)Out of stock: This decreased thanks to the implementation of the MRP, down from 25% to 19%, with this indicator it was possible to know how much raw material is needed to be able to produce the final product. | Organizational or external stops (material or personnel shortage, utilities outage) | Share of lost time | 25.0 % | Single extractor |
Machine failureShow verbatim quote (Section 5.4 Validation)Machine failure: This indicator decreased from 48% to 15%, thanks to the implementation of the TPM, thanks to this the company was able to have better productivity. | Equipment failure (breakdowns) | Share of lost time | 48.0 % | Single extractor |
Defective products rateShow verbatim quote (Section 5.4 Validation)Defective product index: This indicator managed to drop from 10% to 5%, with this the company achieved better profitability and had fewer economic losses. | Process defects (scrap and rework) | Defect rate | 10.0 % | Single extractor |
Downtime rateShow verbatim quote (Section 5.4 Validation)The downtime rate: This decreased from 35.26% to 10%, using the 5S methodology, this was reduced thanks to the implementation of cleanliness and order in the plant | Not classifiable from the report | Share of lost time | 10.0 % | Single extractor |
Stock breakShow verbatim quote (Section 5.4 Validation)Out of stock: This decreased thanks to the implementation of the MRP, down from 25% to 19%, with this indicator it was possible to know how much raw material is needed to be able to produce the final product. | Organizational or external stops (material or personnel shortage, utilities outage) | Share of lost time | 19.0 % | Single extractor |
Machine failureShow verbatim quote (Section 5.4 Validation)Machine failure: This indicator decreased from 48% to 15%, thanks to the implementation of the TPM, thanks to this the company was able to have better productivity. | Equipment failure (breakdowns) | Share of lost time | 15.0 % | Single extractor |
Defective products rateShow verbatim quote (Section 5.4 Validation)Defective product index: This indicator managed to drop from 10% to 5%, with this the company achieved better profitability and had fewer economic losses. | Process defects (scrap and rework) | Defect rate | 5.00 % | Single extractor |
—Show verbatim quote (Table 1)Downtime rate | percentage | 35.26% | Not classifiable from the report | Share of planned time | 35.3 % | Single extractor |
—Show verbatim quote (Table 1)Machine failure | percentage | 48% | Equipment failure (breakdowns) | Share of lost time | 48.0 % | Single extractor |
—Show verbatim quote (Table 1)Stock break | percentage | 25% | Organizational or external stops (material or personnel shortage, utilities outage) | Share of lost time | 25.0 % | Single extractor |
—Show verbatim quote (Table 1)Defective products rate | percentage | 10% | Process defects (scrap and rework) | Defect rate | 10.0 % | Single extractor |
—Show verbatim quote (Table 1)Machine failure | percentage | 15% | Equipment failure (breakdowns) | Share of lost time | 15.0 % | Single extractor |
—Show verbatim quote (Table 1)Stock break | percentage | 19% | Organizational or external stops (material or personnel shortage, utilities outage) | Share of lost time | 19.0 % | Single extractor |
—Show verbatim quote (Table 1)Defective products rate | percentage | 5% | Process defects (scrap and rework) | Defect rate | 5.00 % | Single extractor |
Observation units
- Bakery MSE plant · Whole line or unspecified equipment · Baseline
- Bakery MSE plant · Whole line or unspecified equipment · After intervention
- bakery · Whole line or unspecified equipment · Baseline
- bakery · Whole line or unspecified equipment · After intervention