Production Model Based on Lean Manufacturing, MRP, MPS and TPM to Reduce Losses in a MSE in the Bakery Sector

Open source

1Bibliographic record

Authors
Marcela Garay -Rimarachin, Diego Eduardo Mejia -Espinoza
Year
2023
Venue
International Conference on Industrial Engineering and Operations Management (IEOM)
Country
Peru
Segment
Bakery and pasta
Process family
Forming, baking and cooking
Study type
Before/after intervention
Extraction scope
Full text
Size
1 plants · — lines · — machines
Observation period
30 days
Data collection
questionnaire
Intervention
Show the setting as described by the study
The present study is a case study since it is based on only one specific topic in the baking industry.

2Risk of bias

Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 6High risk
ItemScore
Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product or sector is given but the equipment or process is only partly described.1 / 2
Is the observation period long enough and reported?Period reported and at least 30 days of production (or at least 100 recorded events).2 / 2
How were loss data collected?Interviews, estimates, or method not reported.0 / 2
Are OEE, loading time and the loss categories defined explicitly?No definition; metrics are reported as bare numbers.0 / 2
Does the loss breakdown account for the total loss it claims to explain?Only selected causes are reported and the total is unknown.0 / 2
Is there evidence of selective reporting of favourable results?Intervention study in which baseline and post-intervention periods differ in length or method.1 / 2
Are the reported numbers internally consistent?Small inconsistencies (2 to 10 percentage points) or values that cannot be cross-checked.1 / 2
Could conflicts of interest or the source of the data bias the result?Authors are employees of the plant or of an equipment/software vendor; no declaration.1 / 2

3Extracted data

Each datum with its classification and the verbatim quote that states it.
Reported causeLoss categoryMetricValueExtraction
Downtime rate
Show verbatim quote (Section 5.4 Validation)
The downtime rate: This decreased from 35.26% to 10%, using the 5S methodology, this was reduced thanks to the implementation of cleanliness and order in the plant
Not classifiable from the reportShare of lost time35.3 %Single extractor
Stock break
Show verbatim quote (Section 5.4 Validation)
Out of stock: This decreased thanks to the implementation of the MRP, down from 25% to 19%, with this indicator it was possible to know how much raw material is needed to be able to produce the final product.
Organizational or external stops (material or personnel shortage, utilities outage)Share of lost time25.0 %Single extractor
Machine failure
Show verbatim quote (Section 5.4 Validation)
Machine failure: This indicator decreased from 48% to 15%, thanks to the implementation of the TPM, thanks to this the company was able to have better productivity.
Equipment failure (breakdowns)Share of lost time48.0 %Single extractor
Defective products rate
Show verbatim quote (Section 5.4 Validation)
Defective product index: This indicator managed to drop from 10% to 5%, with this the company achieved better profitability and had fewer economic losses.
Process defects (scrap and rework)Defect rate10.0 %Single extractor
Downtime rate
Show verbatim quote (Section 5.4 Validation)
The downtime rate: This decreased from 35.26% to 10%, using the 5S methodology, this was reduced thanks to the implementation of cleanliness and order in the plant
Not classifiable from the reportShare of lost time10.0 %Single extractor
Stock break
Show verbatim quote (Section 5.4 Validation)
Out of stock: This decreased thanks to the implementation of the MRP, down from 25% to 19%, with this indicator it was possible to know how much raw material is needed to be able to produce the final product.
Organizational or external stops (material or personnel shortage, utilities outage)Share of lost time19.0 %Single extractor
Machine failure
Show verbatim quote (Section 5.4 Validation)
Machine failure: This indicator decreased from 48% to 15%, thanks to the implementation of the TPM, thanks to this the company was able to have better productivity.
Equipment failure (breakdowns)Share of lost time15.0 %Single extractor
Defective products rate
Show verbatim quote (Section 5.4 Validation)
Defective product index: This indicator managed to drop from 10% to 5%, with this the company achieved better profitability and had fewer economic losses.
Process defects (scrap and rework)Defect rate5.00 %Single extractor
—
Show verbatim quote (Table 1)
Downtime rate | percentage | 35.26%
Not classifiable from the reportShare of planned time35.3 %Single extractor
—
Show verbatim quote (Table 1)
Machine failure | percentage | 48%
Equipment failure (breakdowns)Share of lost time48.0 %Single extractor
—
Show verbatim quote (Table 1)
Stock break | percentage | 25%
Organizational or external stops (material or personnel shortage, utilities outage)Share of lost time25.0 %Single extractor
—
Show verbatim quote (Table 1)
Defective products rate | percentage | 10%
Process defects (scrap and rework)Defect rate10.0 %Single extractor
—
Show verbatim quote (Table 1)
Machine failure | percentage | 15%
Equipment failure (breakdowns)Share of lost time15.0 %Single extractor
—
Show verbatim quote (Table 1)
Stock break | percentage | 19%
Organizational or external stops (material or personnel shortage, utilities outage)Share of lost time19.0 %Single extractor
—
Show verbatim quote (Table 1)
Defective products rate | percentage | 5%
Process defects (scrap and rework)Defect rate5.00 %Single extractor

Observation units

  • Bakery MSE plant · Whole line or unspecified equipment · Baseline
  • Bakery MSE plant · Whole line or unspecified equipment · After intervention
  • bakery · Whole line or unspecified equipment · Baseline
  • bakery · Whole line or unspecified equipment · After intervention