Proposal to Enhance Productivity by Applying Lean Manufacturing Tools in a Fish Canning Company

Open source

1Bibliographic record

Authors
Flavia Espinoza-Montero, Rodrigo R. Quintanilla-Chalan, Jorge Antonio Corzo-Chávez, Gino Viacava-Campos
Year
2026
Venue
Congreso Internacional de Ingeniería Industrial de la Universidad de Lima
Country
Peru
Segment
Meat, poultry and seafood
Process family
Slaughter, cutting and primary processing
Study type
Simulation (input data only)
Extraction scope
Full text
Size
1 plants · 1 lines · 2 machines
Observation period
30 days
Data collection
manual_logs
Intervention
Show the setting as described by the study
the studied company is a medium-sized fish canning processor operating two 8-hour shifts with an installed capacity of 180 tons per shift.

2Risk of bias

Scored with the rubric of the protocol: 2 low concern, 1 some concerns, 0 high concern.
Total score 9Moderate risk
ItemScore
Is the observed line, machine or plant described well enough to classify its segment, process and equipment?Product, process and equipment are all described.2 / 2
Is the observation period long enough and reported?Period reported and at least 30 days of production (or at least 100 recorded events).2 / 2
How were loss data collected?Manual logs or maintenance records with unknown completeness.1 / 2
Are OEE, loading time and the loss categories defined explicitly?No definition; metrics are reported as bare numbers.0 / 2
Does the loss breakdown account for the total loss it claims to explain?Only the top causes are reported and the unexplained remainder can be computed.1 / 2
Is there evidence of selective reporting of favourable results?Intervention study in which baseline and post-intervention periods differ in length or method.1 / 2
Are the reported numbers internally consistent?Inconsistencies above 10 percentage points, or OEE factors above 100%.0 / 2
Could conflicts of interest or the source of the data bias the result?Academic or independent study, or conflicts declared and unrelated to the result.2 / 2

3Extracted data

Each datum with its classification and the verbatim quote that states it.
Reported causeLoss categoryMetricValueExtraction
Overheating due to filter cloggingAutoclave
Show verbatim quote (Table III)
Overheating due to filter clogging 4 30 2.1
Equipment failure (breakdowns)Number of events4.00 occurrences/monthBoth extractors agreed
Control instrument misalignmentAutoclave
Show verbatim quote (Table III)
Control instrument misalignment 5 40 3.2
Equipment failure (breakdowns)Number of events5.00 occurrences/monthBoth extractors agreed
Sealing mechanism malfunctionAutoclave
Show verbatim quote (Table III)
Sealing mechanism malfunction 9 28 3.8
Equipment failure (breakdowns)Number of events9.00 occurrences/monthBoth extractors agreed
Pressure calibration failureAutoclave
Show verbatim quote (Table III)
Pressure calibration failure 12 35 4.5
Equipment failure (breakdowns)Number of events12.0 occurrences/monthBoth extractors agreed
Gasket wear and replacementAutoclave
Show verbatim quote (Table III)
Gasket wear and replacement 7 22 2.7
Equipment failure (breakdowns)Number of events7.00 occurrences/monthBoth extractors agreed
—
Show verbatim quote (Table IV)
Defect rate 13% 4.3%
Process defects (scrap and rework)Defect rate13.0 %Adjudicated
Overheating due to filter cloggingAutoclave
Show verbatim quote (Table III)
Overheating due to filter clogging 4 30 2.1
Equipment failure (breakdowns)Share of planned time2.10 %Both extractors agreed
Overheating due to filter cloggingAutoclave
Show verbatim quote (Table III)
Overheating due to filter clogging 4 30 2.1
Equipment failure (breakdowns)Mean event duration30.0 minBoth extractors agreed
—
Show verbatim quote (Abstract)
Labor productivity increased from 6 to 7 units/h
noneThroughput6.00 units/hBoth extractors agreed
Control instrument misalignmentAutoclave
Show verbatim quote (Table III)
Control instrument misalignment 5 40 3.2
Equipment failure (breakdowns)Share of planned time3.20 %Both extractors agreed
Control instrument misalignmentAutoclave
Show verbatim quote (Table III)
Control instrument misalignment 5 40 3.2
Equipment failure (breakdowns)Mean event duration40.0 minBoth extractors agreed
Sealing mechanism malfunctionAutoclave
Show verbatim quote (Table III)
Sealing mechanism malfunction 9 28 3.8
Equipment failure (breakdowns)Share of planned time3.80 %Both extractors agreed
Sealing mechanism malfunctionAutoclave
Show verbatim quote (Table III)
Sealing mechanism malfunction 9 28 3.8
Equipment failure (breakdowns)Mean event duration28.0 minBoth extractors agreed
Pressure calibration failureAutoclave
Show verbatim quote (Table III)
Pressure calibration failure 12 35 4.5
Equipment failure (breakdowns)Share of planned time4.50 %Both extractors agreed
Pressure calibration failureAutoclave
Show verbatim quote (Table III)
Pressure calibration failure 12 35 4.5
Equipment failure (breakdowns)Mean event duration35.0 minBoth extractors agreed
Gasket wear and replacementAutoclave
Show verbatim quote (Table III)
Gasket wear and replacement 7 22 2.7
Equipment failure (breakdowns)Share of planned time2.70 %Both extractors agreed
Gasket wear and replacementAutoclave
Show verbatim quote (Table III)
Gasket wear and replacement 7 22 2.7
Equipment failure (breakdowns)Mean event duration22.0 minBoth extractors agreed
—
Show verbatim quote (Section III Results, Fig. 10)
the OEE indicator initially stood at 63.2%, with a target of 85%.
noneOEE63.2 %Both extractors agreed
Calibration verificationSealing machine
Show verbatim quote (Table I)
Calibration verification 85 min X
Setup and adjustmentsLost time85.0 minSingle extractor
Daily cleaning of sealing headsSealing machine
Show verbatim quote (Table I)
Daily cleaning of sealing heads 65 s X
Setup and adjustmentsLost time65.0 sSingle extractor
Pressure adjustmentSealing machine
Show verbatim quote (Table I)
Pressure adjustment 60 s X
Setup and adjustmentsLost time60.0 sSingle extractor
Seal replacementSealing machine
Show verbatim quote (Table I)
Seal replacement 85 s X
Setup and adjustmentsLost time85.0 sSingle extractor
Inspection of worn partsSealing machine
Show verbatim quote (Table I)
Inspection of worn parts 60 s X
Setup and adjustmentsLost time60.0 sSingle extractor
Roller inspectionSealing machine
Show verbatim quote (Table I)
Roller inspection 70 s X
Setup and adjustmentsLost time70.0 sSingle extractor
Sealing mechanism adjustmentSealing machine
Show verbatim quote (Table I)
Sealing mechanism adjust- ment 90 s X
Setup and adjustmentsLost time90.0 sSingle extractor
Inspection and lubrication of moving partsSealing machine
Show verbatim quote (Table I)
Inspection and lubrication of moving parts 80 s X
Setup and adjustmentsLost time80.0 sSingle extractor
General equipment cleaningSealing machine
Show verbatim quote (Table I)
General equipment cleaning 120 s X
Setup and adjustmentsLost time120 sSingle extractor
Gasket replacementSealing machine
Show verbatim quote (Table I)
Gasket replacement 80 s X
Setup and adjustmentsLost time80.0 sSingle extractor
—Autoclave
Show verbatim quote (Section IV Discussion)
MTBF improved from 3.2 to 6.8 h, and MTTR decreased from 28 to 15 min, confirming increased equipment reliability and faster recovery.
Equipment failure (breakdowns)Time between events3.20 hSingle extractor
—Autoclave
Show verbatim quote (Section IV Discussion)
MTBF improved from 3.2 to 6.8 h, and MTTR decreased from 28 to 15 min, confirming increased equipment reliability and faster recovery.
Equipment failure (breakdowns)Mean event duration28.0 minSingle extractor
—
Show verbatim quote (Section IV Discussion)
The availability rate increased from 70.4% to 85.2%, closing 91.7% of the performance gap toward the 90% target.
noneAvailability70.4 %Single extractor
equipment failure rate
Show verbatim quote (Abstract)
equipment failure rates declined from 13.67% to 4.59%
Equipment failure (breakdowns)Share of lost time13.7 %Single extractor
—Sealing machine
Show verbatim quote (Results section, page 58)
the setup time of the sealing machine was reduced from 12.9 to 5.3 min
Setup and adjustmentsLost time12.9 minSingle extractor

Observation units

  • Autoclave · Sterilization (retort, UHT) · Baseline
  • Whole plant · Whole line or unspecified equipment · Baseline
  • Sealing machine · Capping and seaming · Baseline